Professional Documents
Culture Documents
Si7 Tarquin 162 198 Solucionario de Ingenieria Economica
Si7 Tarquin 162 198 Solucionario de Ingenieria Economica
Chapter 12
Independent Projects With Budget Limitation
12.1 Bundle: a collection of independent projects
Contingent project: has a condition placed on its acceptance or rejection
Dependent project: accepted or rejected based on the decision about another project(s)
12.4 There are a total of 24 = 16 possible bundles. No bundle with X and Y are listed; 12 remain.
12.5 (a) There are a total of 25 = 32 possible bundles; only 5 are within a budget constraint of
$34,000.
Total PW of
Bundle Investment, $
P 6,000
M 11,000
L 28,000
PM 17,000
PL 34,000
Total PW of Total PW of
Bundle Investment, $ Bundle Investment, $
P 6,000 PM 17,000
M 11,000 PL 34,000
L 28,000 PO 44,000
O 38,000 ML 39,000
N 43,000 LMP 45,000
12.6 There are 24 = 16 possible bundles. Considering the selection restrictions, the 9 viable
bundles are:
DN 4 34
1 13 123
3 23 234
12.7 There are 24 = 16 possible bundles. Considering the selection restriction and the $400
limitation, the viable bundles are:
Projects Investment
DN $ 0
2 150
3 75
4 235
2, 3 225
2, 4 385
3, 4 310
12.8 Select the bundle with the highest positive PW value that do not violate the budget
limit of $45,000. Select bundle 4.
(b) Of 24 = 16 bundles, list acceptable bundles and PW values. Select project 4 with highest
PW of $9600.
Bundle Investment PW
DN 0 0
2 $-25,000 $ 8,500
3 -20,000 500
4 -40,000 9,600
2,3 -45,000 9,000
Investment
Bundle $ Million PW, $
DN 0 0
A -1.5 420,564
B -3.0 686,760
C -1.8 550,296
A,C -3.3 970,860
Investment
Bundle $ Million PW, $
DN 0 0
A -1.5 420,564
B -3.0 686,760
C -1.8 550,296
A,B -4.5 1,107,313
A,C -3.3 970,860
(c) With no-limit, select all with PW > 0. Select projects A, B and C.
12.13 Hand calculate each project’s PW using P/F factors since all NCF are different each year.
Alternatively, use a spreadsheet.
12.14 Determine PW values at 0.5% per month by spreadsheet using the PV function
= -PV(0.5%,36,revenue) - cost, or by hand, as follows.
With 23 = 8 bundles and b = $70,000, select the last two features with PW = $63,049.
12.15 (a) Develop the bundles with up to $315,000 investment, and select the one with the
largest PW value.
Initial NCF,
Bundle Projects investment, $ $ per year PW at 10%, $
1 A -100,000 50,000 166,746
2 B -125,000 24,000 3,038
3 C -120,000 75,000 280,118
4 D -220,000 39,000 -11,939
5 E -200,000 82,000 237,462
6 AB -225,000 74,000 169,784
7 AC -220,000 125,000 446,864
8 AE -300,000 132,000 404,208
9 BC -245,000 99,000 283,156
10 DN 0 0 0
All other PW values are obtained by adding the respective PW for bundles 1 through 5.
(b) For mutually exclusive alternatives, select the single project with the largest PW. This
is C, with PW = $280,118.
12.16 (a) For b = $30,000 only 5 bundles are viable of the 32 possibilities.
Initial
Bundle Projects investment, $ PW at 12%, $
1 S -15,000 8,540
2 A -25,000 12,325
3 M -10,000 3,000
4 E -25,000 10
5 SM -25,000 11,540
Initial
Bundle Projects investment, $ PW at 12%, $
6 H -40,000 15,350
7 SA -40,000 20,865
8 SE -40,000 8,550
9 AM -35,000 15,325
10 AE -50,000 12,335
11 ME -35,000 3,010
12 MH -50,000 18,350
13 SAM -50,000 23,865
14 SME -50,000 11,550
(c) Select all projects since they each have PW > 0 at 12%.
12.17 (a) Hand: The bundles and PW values are determined at MARR = 8% per year.
Select PW = $1.285 million for projects 1 and 4 with $3.5 million invested.
(b) Spreadsheet: Set up a spreadsheet for all 7 bundles. Select projects 1 and 4 with the
largest PW = $1,284,730 and invest $3.5 million.
NCF for PW at
Bundle Projects Investment years 1-5, $ 12%, $_
1 1 $-5,000 1000,1700,2400, 3019
3000,3800
2 2 - 8,000 500,500,500, -523
500,10500
3 3 - 9,000 5000,5000,2000 874
12.19 Spreadsheet solution for Problem 12.18. Projects 1 and 3 are selected with PW = $3893
12.20 (a) Spreadsheet shows the solution. Select projects 1 and 2 for an investment of $3.0
million and PW = $753,139.
(b) The Goal Seek target cell is D17 to equal $753,139. Result is a reduced year-one NCF
for project 3 of $145,012. However, with these changes for project 3, the best
selection is now projects 1 and 3 with PW = $822,830.
12.21 To develop the 0-1 ILP formulation, first calculate PWE, since it was not included
in Table 12-2. All amounts are in $1000.
xk = 0 or 1 for k = 1 to 5
(a) For b = $20,000: The spreadsheet solution uses the template in Figure 12-5. MARR
is set to 15% and a budget constraint is set to $20,000 in Solver. Projects C and D are
selected (row 19) for a $14,000 investment with Z = $10,908 (cell I2), as in Example
12.1.
10
(b) b = $13,000: Reset the budget constraint to b = $13,000 in Solver and obtain a new
solution to select only project D with Z = $6120 and only $6000 of the $13,000
invested.
12.22 Use the capital budgeting problem template at 8% with an investment limit of $4 million.
Select projects 1 and 4 with $3.5 million invested and Z ≈ $1.285 million.
11
12.23 Enter the NCF values from Problem 12.20 into the capital budgeting template and
b = $3,000,000 into Solver. Select projects 1 and 2 for Z = $753,139 with $3.0 million
invested.
xk = 0 or 1 for k = 1 to 4
Spreadsheet solution: Enter the NCF values on a spreadsheet and b = $16,000 constraint
in Solver to obtain the answer:
This is the same as in Problem 12.18 where all viable mutually exclusive bundles were
evaluated by hand.
12
13
12.25 Build a spreadsheet and use Solver repeatedly at increasing values of b to find the
projects that maximize the value of Z. Develop a scatter chart.
PI = 60,000(P/A,15%,8)/│-325,000│
= 60,000(4.4873)/325,000
= 0.83
PW = -325,000 + 60,000(P/A,15%,8)
= -325,000 + 60,000(4.4873)
= $-55,762
(b) No, since IROR < 15%; PI < 1.0 and PW < 0 at MARR = 15%
14
12.28 (a) Hand solution: Find IROR for each project, rank by decreasing IROR and then select
projects within budget constraint of $97,000. RATE function used to find i* values.
12.29 (a) Hand : Find ROR for each project and then select highest ones within budget
constraint of $100 million.
15
Only two projects (W and Y) have rate of return ≥ MARR = 12%. Project X
not included since i* X = 6.5% < 12% = MARR.
Spreadsheet: Select Y and W after ranking (row 12); invest $57 million. Project X
not included since i* X = 6.5% < 12% = MARR.
(c) $43 million was not committed; assume it makes MARR = 12% elsewhere.
16
PI = 378,426/381,820
= 0.99
PIB = 2800(P/A,10%,10)/15,000
= 2800(6.1446)/15,000
= 1.15
PIC = 12,600(P/A,10%,10)/35,000
= 12,600(6.1446)/35,000
= 2.21
PID = 13,000(P/A,10%,10)/60,000
= 13,000(6.1446)/60,000
= 1.33
PIE = 8000(P/A,10%,10)/50,000
= 8000(6.1446)/50,000
= 0.98
PI order C A D B
Cum Inv, $1000 35 53 113 128
Select C, A, and D; invest a total of $113,000. E is eliminated with IROR < 10%
(c) Selection and total investment are the same for PI and IROR ranking.
17
12.32 The IROR, PI, and PW values are shown below. Sample calculations for project F are:
Projects G and K are eliminated since IROR, PI and PW are not acceptable.
(a) The projects selected by IROR are I, J, and H with $670,000 invested
IROR rank I J H F
Cum Inv, $1000 370 420 670 870
PI rank I J H F
Cum Inv, $1000 370 420 670 870
PW rank I H J F
Cum Inv, $1000 370 620 670 870
Answer is (d)
18
12.38 There are 5 possible bundles under the $25,000 limit: P,Q,R,S, and PR. Largest PW is for
project Q.
Answer is (b)
PI = 31,699/26,000
= 1.22
Answer is (b)
19
Chapter 13
Breakeven and Payback Analysis
13.1 (a) 0 = -FC + (589 – 340)9000
FC = $2,241,000 per year
v = 3,575,000/950
= $3763 per hwt
v = 6,975,000/850
= $8205 per hwt
0 = -926 + 11c(P/A,0.75%,60)
c = 926/11(48.1734)
= $1.75 per gallon
500,000 = 450,000
r-1
r – 1 = 450,000
500,000
Average revenue required for the new product only is 60¢ per call lower.
800 = 0.0258m(P/A,1%,36)
m = 800/0.0258(30.1075)
= 1030 miles/month
P = 263(50)(P/A,10%,5)
= 263(50)(3.7908)
= $49,849
0.035x = 147.73
x = 4221 miles per year
13.15 (a) Calculate QBE = FC/(r-v) for (r-v) increases of 1% through 15% and plot.
The breakeven point decreases linearly from 680,000 currently to 591,304 if a 15%
increase in (r-v) is experienced.
(b) If r and FC are constant, this means all the reduction must take place in a lower
variable cost per unit.
13.16 Rework the spreadsheet above to include an IF statement for the computation of QBE for
the reduced FC of $750,000. The breakeven point falls substantially to 521,739 when the
lower FC is in effect.
Note: To guarantee that the cell computations in column C correctly track when the
breakeven point falls below 600,000, the same IF statement is used in all cells. With this
feature, sensitivity analysis on the 600,000 estimate may also be performed.
FCtiller = -1200(A/P,10%,5)
= -1200(0.26380)
= $-316.56 per year
13.21 (a) Solve the relation AWbuy = AWmake for Q = number of units per year.
(b) Since 5000 > 3713, select the make option. It has the smaller slope of 5 versus
25 for the buy option.
13.22 Equate PW relations; solve for PS. Painting and blasting is not done at end of year 12.
1.79PS = 16,193.84
PS = $9045
I: PW = -P + 0.2P(P/F,8%,10) + 15,000(P/A,8%,10)
0 = -P + 0.2P(0.4632) + 15,000(6.7101)
P = $110,928
(b) Spreadsheet solution uses Goal Seek to find P for each scenario.
13.24 Let x = number of years for above-ground pool to last for break even
A spreadsheet solution involves the use of the Solver tool with a constraint
that the two PW values be equal.
(b) Since 12.5 < 16.74 miles, select alternative 2; it has the steeper slope.
13.26 (a) Let x = days per year to pump the lagoon. Set the AW relations equal.
(b) If the lagoon is pumped 52 times per year and P = cost of pipeline, the breakeven
equation becomes:
13.27 (a) Solve the relation AWN = AWA for H = number of hours per year.
Usage above 2328 hours will justify A since it has the smaller slope.
(b) Usage of 7(365) = 2555 exceeds breakeven; select Auto Green (A). AW values
are AWN = $-5441 and AWA = $-5367.
13.28 (a) Solve the relation AWlease - AWbuy = 0 for N = number of months
Monthly i = 1.25%.
-800 + 8500(A/P,1.25%,N) + 75 = 0
(b) Since n is greater than the useful period of 12 years, the asset should not be
purchased
(Note: As n → ∞, P/A goes to 6.25 and P/F goes to zero. Therefore, a 16% return
is not possible, no matter how long the equipment is used.)
(c) Spreadsheet shows nonlinear increase in payback as MARR increases. Note that at
16%, the payback cannot be calculate by the NPER function; it is too large for the
function. (See note above.)
For n = 3: PW = $-59
For n = 4: PW = $111.50
13.35 (a) Cash flows sum to $139,100, which exceeds the $75,000 first cost by 85%.
n = 4: PW = -70,201 +28,000(P/F,7%,4)
= $-48,840
n = 5: PW = -48,840 +105,000(P/F,7%,5)
= $26,025
Investment is paid back plus 7% during year 5, in part due to large cash flow at
sale time. A spreadsheet solution for all three parts follows.
10
n = 3: CR = -45,000(A/P,5%,3)
= -45,000(0.36721)
= $-16,524 per year
n = 5: CR = -45,000(A/P,5%,5)
= $-10,394 per year
n = 8: CR = -45,000(A/P,5%,8)
= $-6962 per year
n = 10: CR = -45,000(A/P,5%,10)
= $-5828 per year
PW = 5000(P/A,5%,10)
= -5000(7.7217)
= $38,609
Since $2000 per month will payback during the first year, the second
$10,000 can be neglected.
11
PW = -10,000 + 2000(P/A,0.75%,np)
(P/A,0.75%,n) = 5.0
13.38 (a) Sum NCF for n months until it turns positive. Payback between 6 and 7 months.
(b) Monthly i = 1.5%. Solve for np in PW relation. Payback just over 7 months.
13.39 Since cash flows after np are neglected in payback analysis, an alternative that produces
a higher return due to cash flows after the payback period may be rejected in favor of one
with a shorter payback period, In reality, the lower-payback alternative is not as profitable
from the rate of return perspective.
13.40 No-return payback neglects both the time value of money and all cash flows after the 0%
payback period. Alternatives that don’t payback at 0% may be acceptable if the cash flows
estimated to occur after np are considered. Thus, a PW or AW analysis at the MARR is a
better evaluation method for an alternative over its entire expected life.
12
13.41 (a) Plot shows maximum quantity at about 1350 units. Profit estimate is $20,175
Qp = -b/2a = -29.8/2(-.011)
= 1355 units
PW = Revenue – costs
0 = 50,000(P/F,10%,1) + R(P/A,10%,7)(P/F,10%,1)
-150,000 + 20,000(P/F,10%,8) – 42,000(P/A,10%,8)
13
13.45 Solve the relation AWI = AWO for N = number of tests per year
14
13.46 Spreadsheet used to calculate AW values for each N value; recorded in columns G
and H using ‘Paste Values’ function and then plotted.
13.47 It will raise the breakeven point. Outsourcing will cost $75, increasing to $93.75 in years
6- 8. Resolve for N.
Answer is (d)
15
Since slope of Make is lower, Make would be cheaper above breakeven point
Answer is (b)
Answer is (a)
13.55 Both the fixed and variable costs are lower for Y; Y is better
Answer is (a)
Answer is (c)
Answer is (b)
13.59 Set AW relations equal and solve for x, the cost of the enamel coating
Answer is (c)
Solve for np
np = 4.99 years
Answer is (b)
16
Answer is (d)
Answer is (b)
Answer is (c)
Answer is (d)
17
Sometimes, there is not a definitive answer to a case study exercise. Here are example responses.
2. A decrease in the efficiency of the aerator motor renders the selected alternative of “sludge
recirculation only” more attractive, because the cost of aeration would be higher, and,
therefore the net savings from its discontinuation would be greater.
3. If the cost of lime increased by 50%, the lime costs for “sludge recirculation only” and
“neither aeration nor sludge recirculation” would increase by 50% to $393 and $2070,
respectively. Therefore, the cost difference would increase.
4. If the efficiency of the sludge recirculation pump decreased from 90% to 70%, the net savings
between alternatives 3 and 4 would decrease. This is because the $262 saved by not
recirculating with a 90% efficient pump would increase to a monthly savings of $336 by not
recirculating with a 70% efficient pump.
5. If hardness removal were discontinued, the extra cost for its removal (column 4 in Table 13-
1) would be zero for all alternatives. The favored alternative under this scenario would be
alternative 4 (neither aeration nor sludge recirculation) with a total savings of $2,471 – 469 =
$2002 per month.
6. If the cost of electricity decreased to 8¢/kwh, the aeration only and sludge recirculation only
monthly costs would be $244 and $1952, respectively. The net savings for alternative 2
would then be $-1605, alternative 3 would save $845, and alternative four would save $347.
Therefore, the best alternative continues to be number 3.
7. (a) For alternatives 1 and 2 to breakeven, the total savings would have to be equal to
the total extra cost of $1,849. Thus,
18