TOTAL
NO SKETSA PERHITUNGAN VOLUME
VOLUME
I PEKERJAAN GALIAN ###
1 Pek. Galian Tanah Berlumpur
a STA : Pas Batu Sebelah Kiri
Panjang = 11.00 m
Lebar = 1.40 m
Tinggi = 1.00 m
Volume = 11.00 x 1.40 x 1.00 15.40
b STA : Kanan 2
Panjang = 0.80 m
Lebar 1 = 0.50 m
Lebar 2 = 1.00 m
Lebar rata-rata = 0.75 m
Tinggi = 1.30 m
Volume = 0.80 x 0.75 x 1.30 0.78
c STA : Kanan 3
Panjang = 2.60 m
Lebar 1 = 0.50 m
Lebar 2 = 1.00 m
Lebar rata-rata = 0.75 m
Tinggi = 2.00 m
Volume = 2.60 x 0.75 x 2.00 3.90
d STA : Kanan 4
Panjang = 4.60 m
Lebar 1 = 0.50 m
Lebar 2 = 1.00 m
Lebar rata-rata = 0.75 m
Tinggi = 2.00 m
Volume = 4.60 x 0.75 x 2.00 6.90
b STA : Sekoci
Panjang 1 = 1.80 m
Panjang 2 = 2.20 m
Panjang Rata2 = 2.00 m
Lebar 1 = 0.75 m
Lebar 2 = 0.90 m
Lebar rata-rata = 0.83 m
Tinggi = 2.55 m
Volume = 2.00 x 0.83 x 2.55 4.21
3 Plesteran
1 Pek. Plesteran Batu Sebelah Kanan
a STA : kanan 1
Panjang = 5.20 m
Lebar = 2.95 m
Volume = 5.20 x 2.95 x 15.34
b STA : kanan 2
Panjang = 0.80 m
Lebar = 2.25 m
Volume = 0.80 x 2.25 x 1.80
c STA : kanan 3
Panjang = 2.60 m
Lebar = 2.95 m
Volume = 2.60 x 2.95 x 7.67
d STA : kanan 4
Panjang = 4.60 m
Lebar = 2.50 m
Volume = 4.60 x 2.50 x 11.50
4 Acian
1 Pek. Acian Batu Sebelah Kanan
a STA : kanan 1
Panjang = 5.20 m
Lebar = 2.95 m
Volume = 5.20 x 2.95 x 15.34
b STA : kanan 2
Panjang = 0.80 m
Lebar = 2.25 m
Volume = 0.80 x 2.25 x 1.80
c STA : kanan 3
Panjang = 2.60 m
Lebar = 2.95 m
Volume = 2.60 x 2.95 x 7.67
d STA : kanan 4
Panjang = 4.60 m
Lebar = 2.50 m
Volume = 4.60 x 2.50 x 11.50
b STA : Kiri 2
TOTAL
NO SKETSA PERHITUNGAN VOLUME
VOLUME
Panjang = 5.00 m
Lebar = 2.00 m
Tinggi = 1.50 m
Volume = 5.00 x 2.00 x 1.50 15.000
c STA : Kiri 3
Panjang = 5.00 m
Lebar = 1.80 m
Tinggi = 1.00 m
Volume = 5.00 x 1.80 x 1.00 9.000
b STA : Kiri 2
Panjang = 8.00 m
Lebar = 1.00 m
Tinggi = 0.80 m
Volume = 8.00 x 1.00 x 0.80 6.400
Total Pek. Timbunan Sebelah Kiri dai atas pasangan batu 45.40 M3
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
REKAPITULASI ANGGARAN BIAYA PRASARANA
Tahun Anggaran : 2023
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
### ###
#REF!
REKAPITULASI RENCANA ANGGARAN BIAYA
JENIS KEGIATAN : Rehabilitasi Irigasi (dam parit) di Talao Bukik Canduah
LOKASI : Korong Pauh
NAGARI : Sicincin
KECAMATAN : 2 x 11 Enam Lingkung
TAHUN : 2023
BAHAN :
ALAT :
1,320,000 1,320,000
2 pemasangan bouwplank 18 m1
UPAH :
Pekerja 2.00 OH 110,000 220,000
Tukang 2.00 OH 150,000 300,000
BAHAN :
Kayu balok 5/7 0.22 m3 2,400,000 528,000
Paku 2", 3" 0.36 kg 20,000 7,200
Papan 3/20 0.13 m3 2,400,000 312,000
ALAT :
1,367,200 1,367,200
3 Pek. Galian tanah berlumpur 53.10 m3
UPAH
Pekerja 64.00 OH 110,000 7,040,000
BAHAN:
ALAT :
Keranjang 5 Bh 55,500 277,500
Cangkul 2 Bh 111,000 222,000
Sekop 2 Bh 166,500 333,000
Ember 6 Bh 27,750 166,500
gerobak 3 bh 555,000 1,665,000
JUMLAH 9,704,000 9,704,000
4 Pek. Galian tanah biasa 31.68 m3
UPAH
Pekerja 29.00 OH 110,000 3,190,000
BAHAN:
ALAT :
BAHAN :
Batu kali 105.00 m3 210,000 22,050,000
Semen 286.00 zak 86,580 24,761,880
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN KEGIATAN VOLUME SAT.
(Rp.) (Rp.) (Rp.)
Pasir Pasang 46.00 m3 160,000 7,360,000
ALAT :
6 Pek Plesteran
UPAH :
Pekerja 37.00 OH 110,000 4,070,000
Tukang 19.00 OH 150,000 2,850,000
BAHAN :
Semen 16.00 zak 86,580 1,385,280
Pasir Pasang 3 m3 160,000 480,000
ALAT :
JUMLAH 8,785,280 8,785,280
7 Acian
UPAH :
Pekerja 21.00 OH 110,000 2,310,000
Tukang 11.00 OH 150,000 1,650,000
BAHAN :
Semen 7 zak 86,580 606,060
ALAT :
JUMLAH 4,566,060 4,566,060
8 : Pintu Air / Sekoci
UPAH :
Pekerja 0.00 0.00 0 0
Tukang 0.00 0.00 0 0
BAHAN :
Pintu Air/ Sekoci dam 1 unit 9,000,000 9,000,000
Pintu Air/ Sekoci saluran irigasi 1 unit 3,000,000 3,000,000
ALAT :
JUMLAH 12,000,000 12,000,000
9 Plank kegiatan dan Prasasti
UPAH :
Pekerja 0.00 0.00 0 0
Tukang 0.00 0.00 0 0
BAHAN :
Plank Kegiatan 1 Unit 236,000 236,000
Prasasti 1 Unit 750,000 750,000
ALAT :
JUMLAH 986,000 986,000
10 Pasangan batu kosong
UPAH :
Pekerja 9.00 OH 110,000 990,000
Tukang 5.00 OH 150,000 750,000
BAHAN :
Batu Kali 14 m3 210,000 2,940,000
Pasir Urug 5 m3 150,000 750,000
ALAT :
JUMLAH 5,430,000 5,430,000
11 pek.Urugan Tanah
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN KEGIATAN VOLUME SAT.
(Rp.) (Rp.) (Rp.)
UPAH :
Pekerja 26.00 OH 110,000 2,860,000
BAHAN :
Tanah Urug 104 m3 80,000 8,320,000
ALAT :
JUMLAH 11,180,000 11,180,000
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN KEGIATAN VOLUME SAT.
(Rp.) (Rp.) (Rp.)
UPAH :
Pekerja 26.00 OH 110,000 2,860,000
BAHAN :
Tanah Urug 104 m3 80,000 8,320,000
ALAT :
JUMLAH 11,180,000 11,180,000
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 12.00 HOK 110,000 1,320,000.00
1….
Sub Total 1) Rp 1,320,000 Rp 1,320,000
2. BAHAN
Sub Total 2) Rp - Rp -
3. ALAT
3.1
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 1,320,000
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 2.00 OH Rp 110,000 Rp 220,000
1.2 Tukang 2.00 OH Rp 150,000 Rp 300,000
1….
Sub Total 1) Rp 520,000 Rp 520,000
2. BAHAN
2.1 Kayu balok 5/7 0.22 m3 Rp 2,400,000 Rp 528,000
2.2 Paku 2", 3" 0.36 kg Rp 20,000 Rp 7,200
2.3 Papan 3/20 0.13 m3 Rp 2,400,000 Rp 312,000
2.4
2.5
Sub Total 2) Rp 847,200 Rp 847,200
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 1,367,200
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 64.00 OH Rp 110,000 Rp 7,040,000
1.2
1….
Sub Total 1) Rp 7,040,000 Rp 7,040,000
2. BAHAN
2.1
2.2
2.3
2.4
2.5
Sub Total 2) Rp - Rp -
3. ALAT
3.1 Keranjang 5 Bh Rp 55,500 Rp 277,500
3.2 Cangkul 2 Bh Rp 111,000 Rp 222,000
3.3 Sekop 2 Bh Rp 166,500 Rp 333,000
3.4 Ember 6 Bh Rp 27,750 Rp 166,500
3.5 gerobak 3 bh Rp 555,000 Rp 1,665,000
Sub Total 3 ) Rp 2,664,000 Rp 2,664,000
Total Biaya Rp 9,704,000
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 29.00 OH Rp 110,000 Rp 3,190,000
1.2
1….
Sub Total 1) Rp 3,190,000 Rp 3,190,000
2. BAHAN
2.1
2.2
2.3
2.4
2.5
Sub Total 2) Rp - Rp -
3. ALAT
3.1
3.2
3.3
3.4
3.5
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 3,190,000
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 132.00 OH Rp 110,000 Rp 14,520,000
1.2 Tukang 66.00 OH Rp 150,000 Rp 9,900,000
1….
Sub Total 1) Rp 24,420,000 Rp 24,420,000
2. BAHAN
2.1 Batu kali 105.00 m3 Rp 210,000 Rp 22,050,000
2.2 Semen 286.00 zak Rp 86,580 Rp 24,761,880
2.3 Pasir Pasang 46.00 m3 Rp 160,000 Rp 7,360,000
2.4
2.5
Sub Total 2) Rp 54,171,880 Rp 54,171,880
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 78,591,880
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 9.00 OH Rp 110,000 Rp 990,000
1.2 Tukang 5.00 OH Rp 150,000 Rp 750,000
1….
Sub Total 1) Rp 1,740,000 Rp 1,740,000
2. BAHAN
2.1 Batu Kali 14.00 m3 Rp 210,000 Rp 2,940,000
2.2 Pasir Urug 5.00 m3 Rp 150,000 Rp 750,000
2.3
2.4
2.5
Sub Total 2) Rp 3,690,000 Rp 3,690,000
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 5,430,000
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja OH Rp -
1.2 Tukang
1….
Sub Total 1) Rp - Rp -
2. BAHAN
2.1 Pintu Air/ Sekoci dam 1.00 unit Rp 9,000,000 Rp 9,000,000
2.2 Pintu Air/ Sekoci saluran irigasi 1.00 unit Rp 3,000,000 Rp 3,000,000
2.3
2.4
2.5
Sub Total 2) Rp 12,000,000 Rp 12,000,000
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 12,000,000
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 37.00 OH Rp 110,000 Rp 4,070,000
1.2 Tukang 19.00 OH Rp 150,000 Rp 2,850,000
1….
Sub Total 1) Rp 6,920,000 Rp 6,920,000
2. BAHAN
2.1 Semen 16.00 zak Rp 86,580 Rp 1,385,280
2.2 Pasir Pasang 3.00 m3 Rp 160,000 Rp 480,000
2.3
2.4
2.5
Sub Total 2) Rp 1,865,280 Rp 1,865,280
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 8,785,280
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 21.00 OH Rp 110,000 Rp 2,310,000
1.2 Tukang 11.00 OH Rp 150,000 Rp 1,650,000
1….
Sub Total 1) Rp 3,960,000 Rp 3,960,000
2. BAHAN
2.1 Semen 7.00 zak Rp 86,580 Rp 606,060
2.2
2.3
2.4
2.5
Sub Total 2) Rp 606,060 Rp 606,060
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 4,566,060
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 0.00 OH Rp 110,000 Rp -
1.2 Tukang 0.00 OH Rp 150,000 Rp -
1….
Sub Total 1) Rp - Rp -
2. BAHAN
2.1 Semen #REF! zak Rp 78,000 #REF!
2.2 Pasir Pasang #REF! m3 Rp 150,000 #REF!
2.3 Kerikil Beton #REF! m3 Rp 150,000 #REF!
2.4
2.5
Sub Total 2) #REF! #REF!
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya #REF!
FEBRIWENDI FIRDAUS, S.Pt, M.Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
RENCANA ANGGARAN BIAYA (RAB)
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1
1.2
1….
Sub Total 1) Rp - Rp -
2. BAHAN
2.1 Plank Kegiatan 1.00 Unit Rp 236,000 Rp 236,000
2.2 Prasasti 1.00 Unit Rp 750,000 Rp 750,000
2.3
2.4
2.5
Sub Total 2) Rp 986,000 Rp 986,000
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 986,000
Jumlah Total
URAIAN Volume Satuan Harga Satuan (Rp.) (Rp.) Jumlah
a b c d e=bxd f
1. UPAH
1.1 Pekerja 26.00 OH Rp 110,000 Rp 2,860,000
1.2
1….
Sub Total 1) Rp 2,860,000 Rp 2,860,000
2. BAHAN
2.1 Tanah Urug 104.00 m3 Rp 80,000 Rp 8,320,000
2.2
2.3
2.4
2.5
Sub Total 2) Rp 8,320,000 Rp 8,320,000
3. ALAT
3.1
3.2
3.3
3.4
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya Rp 11,180,000
0.1 120.00 12
0.1
#REF!
#REF!
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
DAFTAR HARGA SATUAN UPAH, BAHAN DAN ALAT
1 2 3 7 8 9
A TENAGA / UPAH
1 Pekerja HOK Rp 110,000 Rp 110,000
2 Tukang HOK Rp 150,000 Rp 150,000
3
B BAHAN / MATERIAL
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
AKTUAL CEK
Kegiatan : Rehabilitasi Irigasi (dam parit) di Talao bukik canduah Korong Pauah
GAMBAR PERHITUNGAN
Panjang Lebar Tinggi byk Volume
1 Pembersihan Lapangan 15 x 8 = 120 m2
2 pemasangan bouwplank 18 18 m1
6 Pek Plesteran
panjang lebar
a. plesteran Pasangan Batu Sebelah Kanan 1 5.2 x 3.1 = 16.12 m2
panjang lebar
b. plesteran Pasangan Batu Sebelah Kanan 2 0.8 x 1.4 = 1.12 m2
panjang lebar
c. plesteran Pasangan Batu Sebelah Kanan 3 2.5 x 3.1 = 7.75 m2
panjang lebar
d. plesteran Pasangan Batu Sebelah Kanan 4 3.5 x 3.1 = 10.85 m2
e. plesteran Pasangan Batu Sebelah Kiri panjang lebar
11 x 3.1 = 34.1 m2
f. plesteran Pasangan Batu Mercu panjang lebar
2.4 x 4.65 = 11.16 m2
g. plesteran Pasangan Batu sekoci dam panjang lebar banyak
2 x 2.4 = 4.8 m2
2 x 0.8 = 1.6 m2
0.8 x 2.4 x 2 = 3.84 m2
2 1 = 2 m2
h. Plesteran Pasangan Batu Saluran panjang lebar banyak
3.5 x 1.1 2 = 7.7 m2
3.5 x 0.6 = 2.1 m2
i. Plesteran Pasangan Batu Lantai panjang lebar
2.5 x 4x 2 = 20 m2
7 Acian
panjang lebar
a. Acian Pasangan Batu Sebelah Kanan 1 5.2 x 3.1 = 16.12 m2
panjang lebar
b. Acian Pasangan Batu Sebelah Kanan 2 0.8 x 1.4 = 1.12 m2
panjang lebar
c. Acian Pasangan Batu Sebelah Kanan 3 2.5 x 3.1 = 7.75 m2
panjang lebar
d. Acian Pasangan Batu Sebelah Kanan 4 3.5 x 3.1 = 10.85 m2
e. Acian Pasangan Batu Sebelah Kiri panjang lebar
11 x 3.1 = 34.1 m2
f. Acian Pasangan Batu Mercu panjang lebar
2.4 x 4.65 = 11.16 m2
g. Acian Pasangan Batu sekoci dam panjang lebar banyak
2 x 2.4 = 4.8 m2
2 x 0.8 = 1.6 m2
0.8 x 2.4 x 2 = 3.84 m2
2 1 = 2 m2
h. Acian Pasangan Batu Saluran panjang lebar banyak
3.5 x 1.1 2 = 7.7 m2
9 pek.Urugan Tanah
a. Urugan tanah sebelah kiri panjang lebar tinggi
2x 1.7 x 1 = 3.4 m3
5x 2x 1.7 = 17 m3
5x 1.8 x 1 = 9 m3
29.4
b. Urugan Tanah sebelah kanan panjang lebar tinggi
4x 3x 1 = 12 m3
FEBRIWENDI FIRDAUS, S.Pt, M. Si GITO FADLI, S.Kom MULFIA AFRIMA PUTRI, S.AP
JUMLAH PENGGUNAAN BAHAN DAN MATERIAL
JUMLAH
NO TENAGA KERJA SATUAN UPAH JUMLAH
OH
1 PEKERJA 332 OH 110,000 36,520,000
2 TUKANG 103 OH 150,000 15,450,000
51,970,000
Rp 1,350,000
Rp 2,000,000
Rp140,470,420
PEMERINTAH KABUPATEN
PADANG PARIAMAN
TAHUN ANGGARAN