Professional Documents
Culture Documents
Finals CE38
Finals CE38
1. Explain the meaning of Course, and mortar cover of 5/8 in. (16 mm) on
Wythe used in masonry exterior faces and 1/2 in. (13 mm)
construction. on interior faces.
Course - a horizontal layer of 5. Estimate the amount of mortar
brick in the plane of the wall. required for the brick wall of Problem
Wythe - a vertical section one 3 if the joint between wythes is 5 ⁄8
brick thick. in. (16 mm). Assume 25% mortar
2. Describe how masonry units should waste.
be stored at a construction site. 6. Find the maximum safe unsupported
Concrete masonry units should height of a 6-in. (150-mm) solid brick
be stored and laid in a dry wall if the design wind load is 15
condition. lb/sq ft (0.72 kPa).
3. Why and how should masonry walls 7. In what situations might the methods
be protected before the building roof for reinforcing concrete block walls
is put in place? illustrated in Figure 14–15 be
Masonry walls should be needed?
protected before the building roof At the top of the wall, a concrete
is put in place because of: bond beam (A) is created by filling
- Weather protection - a U-shaped block (called a lintel
unprotected masonry walls block or beam block) with
are vulnerable to weather reinforced concrete. Vertical
elements. reinforcement is provided by
- Thermal expansion and placing reinforcing steel in some
contraction - masonry of the block cores and filling
materials expand and these cores with concrete (B).
contract when the Additional horizontal
temperature changes. reinforcement is obtained from
- Construction debris - reinforcing steel placed in the
materials, tools, and mortar joints (D). This type of
equipment can cause construction is appropriate for
accidental damage to the areas of high design loads, such
masonry walls. as earthquake and hurricane
- Mortar curing - masonry zones.
walls require sufficient 8. How long after initial mixing may
time for the mortar to cure mortar be used before discarding?
and gain strength. Mortar should be discarded 2 1/2
4. What minimum mortar cover is h after initial mixing
required for a No. 3 rebar located
near the exterior face of a reinforced
concrete masonry wall exposed to
weather?
Masonry reinforcement not
exceeding ¼ in. (6 mm) in
MASONRY
1. What are the ten terms applied to the
components of a brick wall? Define each 3. Differentiate each type of pattern bond
term. of brick masonry
Course - Horizontal layer of Brick in the Running bond- uses only a stretcher course
plane of the wall in which head joints are centered over
Stretcher - a horizontal layer of brick in the stretchers.
top course Common bond- uses only a header course
Wythe - a vertical section which is one brick every fifth, sixth, and seventh interval. It
thick also provides structural bonding between
Header - brick placed with its long axis wythes.
perpendicular to the direction of the wall. English bond- alternates between headers
Bed joint - horizontal layer mortar on which and stretchers in which headers are
bricks are being placed. centered on stretchers.
Head joints - vertical mortar joints between Flemish bond- alternates between stretcher
brick ends and headers in which headers are centered
Collar joint - vertical joint between brick over stretchers
wythes Stack bond- mostly used for architectural
Troweled joint - formed by cutting off excess purposes, however horizontal reinforcement
mortar with the trowel and then compacting must be applied to provide lateral bonding.
the joint with the tip of the trowel.
Tooled joint - formed by using a unique tool 4. What masonry cavity walls are made
to compact and shape the mortar in the up of and what are the advantages over a
joint, they are the most watertight joint single bonded masonry wall?
Raked joint - used for architectural design or
appearance but are challenging to make Masonry cavity walls are made up of two
completely watertight. masonry wythes that have an open air
space of 2 in or more and they are tied with
2. Define each principal mortar type metal ties. The advantages of cavity walls
(types M S N O PM and PL) are that they offer greater resistance to
moisture, better thermal and acoustic
Type M - high strength mortar used for insulation, and excellent fire resistance.
whenever high compressive strength and
durability is required 5.) What are brick cavity walls?
Type S - medium-high strength mortar used
for general purposes They combine an exterior and interior wythe
Type N - medium strength mortar used for of brick, with an structural clay tile, or
general purposes, should not be used below concrete masonry.
natural grade line
Type O - low strength mortar used for
non-load bearing partitions and fireproofing
Type PM and PL - used for reinforced
masonry
6.) Explain the usage of RBM 10. Differentiate solid concrete block and
hollow block?
RBM is a reinforced brick masonry in which
they are reinforced with steel to offer greater Solid concrete block must have at least 75%
strength of its cross sectional area made up of
concrete while hollow block must have more
7.) What is a utility wall and compare it to than 25% of its cross sectional area empty,
a cavity wall? and has a core area of 40% to 50% of its
cross section
It is a masonry bonded wall constructed of
utility brick, utility walls are not as water 11. Why do you need to use a bonding
resistant compared to cavity walls, however agent on a concrete block?
when constructed properly, they resist water
penetration far better than cavity walls. When a concrete block is laid without mortar
joints, a bonding agent must be applied to a
8. Compare Bond beams and Lintels stacked concrete block to ensure that the
block has structural strength and resistance
A bond beam is a continuously reinforced to water penetration.
beam of concrete or masonry designed to
provide additional strength and to prevent 12. What is Reinforced Concrete
cracking in a masonry wall. At the same Masonry?
time, Lintels are short beams of wood, steel,
stone, or reinforced brick masonry that are When masonry is reinforced with concrete,
used to span openings in masonry walls. it provides additional strength and prevents
cracking.
2.) Explain the process of steel Structural steel members are often
construction carelessly handled during unloading at a job
site. Some may throw them off the truck or a
There are three major procedures in which it railcar and stack them up in a manner that
is advanced planning, steel fabrication, and will distort the member. In unloading
delivery to the job site, and field operations.
trusses, double slings must be used to 13.) Compare and Contrast the 3
avoid bending the member. types standard-open web steel
joists
9.) Explain the process of shaking
out Series K - Series K are parallel chord joists
that span up to 60 ft with a max depth of 30
It is the process of sorting it out by in.
identifying each member, and storing it in Longspan Joists (LH) - LH joists are
such a manner that it can be easily obtained available with parallel chords or with the top
during erection. chord pitched one way or two ways. LH
joists span up to 96 ft with a max depth of
10.) In a work site, how do you 48 in.
store steel before erecting it? Deep Longspan Joists (DLH) - DLH joists
are available with parallel chords or with the
It should be stored off platforms, skids, or top chord pitched one way or two ways.
other supports, and protected from dirt, DLH joists span up to 144 ft with a max
grease, and corrosion. depth of 72 in.
11.) Briefly describe the The three series are designed to support
characteristics of weathering uniform loads.
steel?
14.) How do you design a
It is a type of steel that develops a castellated steel beam?
protective oxide coat on its surface upon
exposure to the elements so that painting is They are created by standard rolled shapes
not required for protection against most by shearing one side and then joining two
corrosion. sections together to create the shape.
These have a deeper and have a higher
strength/weight ratio than standard rolled
12.) Mention and briefly explain the sections.
3 types of joists
15.) Enumerate the crews of the
Open - web steel joists (K, LH, and DLH) - procedure of steel erection, and
Lightweight open trusses that are strong briefly explain them.
and economical, mostly used in supporting
floors and roofs of buildings. Raising Crew - it lifts the steel member into
Bar joists - diagonal members consist of position and makes temporary bolted
steel bars. connections that will hold the member safely
Joist Girders - similar to open-web steel in place.
joists, however they are designed to to Fitting Crew - brings the member into proper
support panel point loads. alignment and tightens enough bolts to hold
the structure in alignment until final
connections are made.
Fastening Crew - Makes the final Lifelines and Safety belts - Standard
connections, to meet specifications requirements where potential fall exceeds 2
requirements. stories