Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

MASONRY diameter should have a minimum

1. Explain the meaning of Course, and mortar cover of 5/8 in. (16 mm) on
Wythe used in masonry exterior faces and 1/2 in. (13 mm)
construction. on interior faces.
Course - a horizontal layer of 5. Estimate the amount of mortar
brick in the plane of the wall. required for the brick wall of Problem
Wythe - a vertical section one 3 if the joint between wythes is 5 ⁄8
brick thick. in. (16 mm). Assume 25% mortar
2. Describe how masonry units should waste.
be stored at a construction site. 6. Find the maximum safe unsupported
Concrete masonry units should height of a 6-in. (150-mm) solid brick
be stored and laid in a dry wall if the design wind load is 15
condition. lb/sq ft (0.72 kPa).
3. Why and how should masonry walls 7. In what situations might the methods
be protected before the building roof for reinforcing concrete block walls
is put in place? illustrated in Figure 14–15 be
Masonry walls should be needed?
protected before the building roof At the top of the wall, a concrete
is put in place because of: bond beam (A) is created by filling
- Weather protection - a U-shaped block (called a lintel
unprotected masonry walls block or beam block) with
are vulnerable to weather reinforced concrete. Vertical
elements. reinforcement is provided by
- Thermal expansion and placing reinforcing steel in some
contraction - masonry of the block cores and filling
materials expand and these cores with concrete (B).
contract when the Additional horizontal
temperature changes. reinforcement is obtained from
- Construction debris - reinforcing steel placed in the
materials, tools, and mortar joints (D). This type of
equipment can cause construction is appropriate for
accidental damage to the areas of high design loads, such
masonry walls. as earthquake and hurricane
- Mortar curing - masonry zones.
walls require sufficient 8. How long after initial mixing may
time for the mortar to cure mortar be used before discarding?
and gain strength. Mortar should be discarded 2 1/2
4. What minimum mortar cover is h after initial mixing
required for a No. 3 rebar located
near the exterior face of a reinforced
concrete masonry wall exposed to
weather?
Masonry reinforcement not
exceeding ¼ in. (6 mm) in
MASONRY
1. What are the ten terms applied to the
components of a brick wall? Define each 3. Differentiate each type of pattern bond
term. of brick masonry

Course - Horizontal layer of Brick in the Running bond- uses only a stretcher course
plane of the wall in which head joints are centered over
Stretcher - a horizontal layer of brick in the stretchers.
top course Common bond- uses only a header course
Wythe - a vertical section which is one brick every fifth, sixth, and seventh interval. It
thick also provides structural bonding between
Header - brick placed with its long axis wythes.
perpendicular to the direction of the wall. English bond- alternates between headers
Bed joint - horizontal layer mortar on which and stretchers in which headers are
bricks are being placed. centered on stretchers.
Head joints - vertical mortar joints between Flemish bond- alternates between stretcher
brick ends and headers in which headers are centered
Collar joint - vertical joint between brick over stretchers
wythes Stack bond- mostly used for architectural
Troweled joint - formed by cutting off excess purposes, however horizontal reinforcement
mortar with the trowel and then compacting must be applied to provide lateral bonding.
the joint with the tip of the trowel.
Tooled joint - formed by using a unique tool 4. What masonry cavity walls are made
to compact and shape the mortar in the up of and what are the advantages over a
joint, they are the most watertight joint single bonded masonry wall?
Raked joint - used for architectural design or
appearance but are challenging to make Masonry cavity walls are made up of two
completely watertight. masonry wythes that have an open air
space of 2 in or more and they are tied with
2. Define each principal mortar type metal ties. The advantages of cavity walls
(types M S N O PM and PL) are that they offer greater resistance to
moisture, better thermal and acoustic
Type M - high strength mortar used for insulation, and excellent fire resistance.
whenever high compressive strength and
durability is required 5.) What are brick cavity walls?
Type S - medium-high strength mortar used
for general purposes They combine an exterior and interior wythe
Type N - medium strength mortar used for of brick, with an structural clay tile, or
general purposes, should not be used below concrete masonry.
natural grade line
Type O - low strength mortar used for
non-load bearing partitions and fireproofing
Type PM and PL - used for reinforced
masonry
6.) Explain the usage of RBM 10. Differentiate solid concrete block and
hollow block?
RBM is a reinforced brick masonry in which
they are reinforced with steel to offer greater Solid concrete block must have at least 75%
strength of its cross sectional area made up of
concrete while hollow block must have more
7.) What is a utility wall and compare it to than 25% of its cross sectional area empty,
a cavity wall? and has a core area of 40% to 50% of its
cross section
It is a masonry bonded wall constructed of
utility brick, utility walls are not as water 11. Why do you need to use a bonding
resistant compared to cavity walls, however agent on a concrete block?
when constructed properly, they resist water
penetration far better than cavity walls. When a concrete block is laid without mortar
joints, a bonding agent must be applied to a
8. Compare Bond beams and Lintels stacked concrete block to ensure that the
block has structural strength and resistance
A bond beam is a continuously reinforced to water penetration.
beam of concrete or masonry designed to
provide additional strength and to prevent 12. What is Reinforced Concrete
cracking in a masonry wall. At the same Masonry?
time, Lintels are short beams of wood, steel,
stone, or reinforced brick masonry that are When masonry is reinforced with concrete,
used to span openings in masonry walls. it provides additional strength and prevents
cracking.

9. Compare and contrast Control Joints 13. What is ashlar masonry?


and Flashing
These are commonly used to identify
Expansion joints are used to permit masonry of any material which uses
differential movement between wall sections rectangular units larger than brick laid in a
caused by shrinkage cracking from pattern.
foundation and floor slabs, temperature and
moisture changes, and foundation 14. Give at least 2-3 materials used in
settlement. Flashing consists of impervious Concrete masonry and define each
layers used to seal out moisture or to direct
any moisture that does penetrate back to Stone Veneer - held in place with ties
the outside. Control joints are used at embedded in mortar joints
window and door openings while flashing is Shaped Stone - used for window sills,
used in vertical sections like in parapet lintels, parapet coping caps, and wall
walls. panels.
15. What are the five steps in estimating make the masonry units not fit for
the number of bricks required for a construction.
masonry wall?
19. What is masonry grout and self
Calculating the area of the wall, calculating consolidating grouts?
the surface area of the brick, dividing the
wall area by surface area of the brick, thus Masonry grout is a fluid mixture of cement,
multiplying the quantity by the number of water, and sand or cement and water while
wythes and its wall thickness and adding an consolidating grouts uses a super
amount for waste. plasticizing admixture to produce an
extremely fluid grout capable of easily filling
16. Why must masonry walls be small gaps in a masonry unit.
designed to safely resist all expected
walls, including dead, live, and wind 20. What are the weather protection for
loads? concrete masonry units? During hot
weather, what are the recommendations
To ensure safe structural design, when the to reduce the effects?
building is erected, the design should also
determine the support requirements of the
loads during construction.

17. What is the proper procedure of


removing braces of a masonry wall?

Shores, forms, and bracing must not be


removed until the mortar has the sufficient
strength to carry all construction loads.
Concentrated loads should not be applied to
a masonry wall or column until 3d
construction.

17. What are Harsh mortars? and what


hash mortars produce?

Harsh mortars produced by sand having


insufficient fines while excess fines will
result in having good workability but lower
strength and high porosity.

18. Why should concrete masonry units


be stored and laid in a dry condition?

Because of moisture, the masonry units


might develop shrinkage cracking and will
STEEL CONSTRUCTION bolts are a preferred choice for their
precise tensioning, safety benefits,
1.) Explain the term blocking as used time efficiency, and potential cost
in steel construction. savings.
- Blocking is the name applied to
notching beams to provide the 6.) Briefly describe 5 methods for
necessary clearance when beams determining the quality of welds
connect to columns or other beams. in structural steel connections.
- Visual Inspection: It is the quickest,
2.) Identify the maximum fabrication easiest, and most widely used
tolerance of a steel column in inspection method. However it
terms of depth, width, and length requires the use of highly trained
and squareness. and experienced inspection
3.) personnel.
- - Destructive testing: This is used
primarily in welder qualification
4.) When erecting a steel building procedures. It is also used to
structure, what is the maximum determine the actual strength of
height that the erection deck can be welds.
above the highest completed - Radiographic inspection: This
permanent floor? method involves producing an X-ray
- The erection deck cannot be more picture of the weld. When it is
than 8 stories. executed properly it can detect a
defect as small as 2% of the joint
5.) What advantages do tension thickness.
control bolts have over - Ultrasonic inspection: This method
conventional steel bolts in making uses high-frequency vibration to
bolted steel connections? detect defects. The nature of the
- Tension control bolts incorporate a signals that are reflected back from
torque control groove so that the the weld gives an indication of the
stem breaks off under a specified type, size, and location of any
torque, therefore, Tension control defect.
bolts offer several advantages over - Liquid-penetrant inspection: This
conventional steel bolts in making involves spraying the weld with a
bolted steel connections. They liquid penetrant, drying the surface,
provide precise and consistent and then applying a developing
tightening, enhancing safety and liquid. This method is inexpensive
structural integrity. The installation and easy to use but can only detect
process is simplified, saving time. flaws on an open surface.
Though they may have a higher
initial cost, tension control bolts can 7.) What is the yield strength of type
lead to long-term cost savings by A36 steel?
reducing maintenance and repair - 36ksi (36000lb/sq in or 248.2MPA)
expenses. Overall, tension control
8.) Describe the Characteristics of 3.) Explain the process of Divisioning
Series LH open-web steel joists.
- The characteristics of Series LH It is the process of dividing a structure into
open-web steel joists are, they have units called divisions in which are used to
a span upto 96 ft with a maximum schedule the fabrication and delivery of
depth of 48 in, and this type of joist structural steel members to the job site.
are formed by built-up steel
members in which they are 4.) How do you plan erection
lightweight open trusses that are procedures?
strong and economical.
The type of equipment utilized and the
9.) Describe how high-strength steel procedures to be followed are determined
bolts may be identified by the type of structure being erected and
- To identify high-strength steel bolts the anticipated site conditions.
ASTM has prescribed special
markings for high-strength bolts. To 5.) How do you plan shop
identify high-strength steel bolts in fabrications?
the Philippines, there are a few key The size and weight of large members must
methods: checking for markings be checked against plant capacity,
indicating grade or strength, transportation size, weight limits, and the
verifying certification or test reports capacity of erection equipment.
from manufacturers, considering the
reputation of suppliers, and ensuring 6.) What is field operations?
compliance with recognized
standards. Consulting with experts is It includes receiving and unloading, sorting,
advised for accurate identification inspecting, storing, and erecting the steel.
and selection of high-strength steel
bolts in construction projects. 7.) Briefly explain the term “yarding”

STEEL CONSTRUCTION (Predictions) It is the process of unloading steel to a


temporary storage area and then moving it
1.) How do you plan large and from storage to the point of erection.
complex projects
8.) What are the common mistakes in
Advanced planning includes divisioning the unloading steel at a job site and
steel and planning shipping and erection how do you mitigate such
procedures. mistakes?

2.) Explain the process of steel Structural steel members are often
construction carelessly handled during unloading at a job
site. Some may throw them off the truck or a
There are three major procedures in which it railcar and stack them up in a manner that
is advanced planning, steel fabrication, and will distort the member. In unloading
delivery to the job site, and field operations.
trusses, double slings must be used to 13.) Compare and Contrast the 3
avoid bending the member. types standard-open web steel
joists
9.) Explain the process of shaking
out Series K - Series K are parallel chord joists
that span up to 60 ft with a max depth of 30
It is the process of sorting it out by in.
identifying each member, and storing it in Longspan Joists (LH) - LH joists are
such a manner that it can be easily obtained available with parallel chords or with the top
during erection. chord pitched one way or two ways. LH
joists span up to 96 ft with a max depth of
10.) In a work site, how do you 48 in.
store steel before erecting it? Deep Longspan Joists (DLH) - DLH joists
are available with parallel chords or with the
It should be stored off platforms, skids, or top chord pitched one way or two ways.
other supports, and protected from dirt, DLH joists span up to 144 ft with a max
grease, and corrosion. depth of 72 in.

11.) Briefly describe the The three series are designed to support
characteristics of weathering uniform loads.
steel?
14.) How do you design a
It is a type of steel that develops a castellated steel beam?
protective oxide coat on its surface upon
exposure to the elements so that painting is They are created by standard rolled shapes
not required for protection against most by shearing one side and then joining two
corrosion. sections together to create the shape.
These have a deeper and have a higher
strength/weight ratio than standard rolled
12.) Mention and briefly explain the sections.
3 types of joists
15.) Enumerate the crews of the
Open - web steel joists (K, LH, and DLH) - procedure of steel erection, and
Lightweight open trusses that are strong briefly explain them.
and economical, mostly used in supporting
floors and roofs of buildings. Raising Crew - it lifts the steel member into
Bar joists - diagonal members consist of position and makes temporary bolted
steel bars. connections that will hold the member safely
Joist Girders - similar to open-web steel in place.
joists, however they are designed to to Fitting Crew - brings the member into proper
support panel point loads. alignment and tightens enough bolts to hold
the structure in alignment until final
connections are made.
Fastening Crew - Makes the final Lifelines and Safety belts - Standard
connections, to meet specifications requirements where potential fall exceeds 2
requirements. stories

16.) What does OSHA mean by the


term structural integrity?

The ability of a structure to safely stand up


during erection and has prescribed safety
measures to ensure structural integrity. An
example would be that the erection deck
cannot be more than 8 stories above the
highest completed permanent floor.

17.) What are the two bolted


connections and briefly describe

Interference - body or interference- fit bolts -


Bolts that are driven into place and use
oversize shanks to prevent turning during
tightening.

Tension control bolts or Tension set bolts -


Bolts that incorporate a torque control
groove so that the stem breaks off under a
specified torque.

18.) Explain the usage and


purpose of bolt-tension calibrator

To calibrate both impact wrenches and


hand-indicator torque wrenches.

19.) Cite and explain the OSHA’s


regulations on PPE
Hardhats and Gloves - Standard
requirements for steel erection
Eye protection - requirements for welders,
cutting, and chipping operations.
Temporary Floors and Scaffolds -
Employees working above ground level
provide protective measures against fall.
20 - IMPROVING PRODUCTIVITY AND - Other techniques available to
PERFORMANCE assist the construction
manager in improving
1. What is Productivity? construction productivity and
- The output of construction cost-effectiveness include
goods and services per unit network planning methods,
of labor input. Such a economic analyses, safety
definition ignores the programs, quantitive
contribution of technology management methods,
and capital investment. simulation, and the use of
2. Explain the Tools for Better computers.
Management. 5. Explain PREPLANNING
- Management is responsible - A detailed planning of work
for planning, organizing, and equipment and procedures
controlling the work. If these before the start of work.
management responsibilities 6. Explain TIME STUDIES
were adequately carried out, - Time studies are used to
there would be few cases of collect time data relating to a
idle workers waiting for job construction activity for the
assignments, tools, or purpose of either statistical
instructions. The scope of analysis or of determining
management responsibility is the level of work activity.
excellent, and the techniques 7. Explain WORK SAMPLING
for efficiently carrying out - It is the name for a time
these responsibilities are study conducted to
varied and complex. determine the level of activity
3. What is WORK IMPROVEMENT? of an operation.
- It is one of the primary tools 8. What are the types of work
for improving construction sampling? Explain each type.
productivity. - The types of work sampling
- The scientific study and performed to determine labor
optimization of work utilization and effectiveness
methods. include field ratings and
4. What are the techniques of Work 5-min ratings.
Improvement? - Field ratings are used to
- Work simplification measure the level of activity
- Motion and time study of a large workforce. Each
- Work study worker is observed and
- Methods analysis instantaneously classified as
- Human factors also play an either working or nonworking
essential part in productivity. at the selected random
- Workers’ physical capacity, times.
site working conditions, - The number of working
morale, and motivation observations divided by the
total number of observations creating traffic conflicts or
yields the activity level. safety hazards.
- Another type is a 5-min 13. What is a FLOW DIAGRAM?
rating - it is used primarily to - Flow diagram is similar to a
measure the level of activity layout diagram but also
of a crew. shows the path followed by
9. What is used for recording time the worker and the material
studies? being recorded on a flow
- Traditionally, it is made using process chart.
stopwatches and data - Flow process charts, flow
sheets, and there is growing diagrams, and layout
use of time-lapse diagrams must be studied
photography and video together for maximum benefit
time-lapse. and must be consistent with
10. What is the use of FLOW PROCESS each other.
CHARTS? 14. What is a CREW BALANCE
- It traces the flow of material CHARTS?
of work through a series of - A crew balance chart uses a
processing steps (classified graphical format to document
as operations, transportation, the activities of each member
inspections, delays, or of a group of workers during
storage). one complete cycle of an
11. What is the next step after preparing operation.
a flow process chart? - Sometimes referred to as
- It should be analyzed and multi-man charts. Charts
revised to reduce the number showing crew activities and
of operations, movements, machine utilization are called
storage, delays, and the man-machine charts or
control factor to a minimum. multi-man-and-machine
12. Explain LAYOUT DIAGRAMS charts.
- It's a scaled diagram that 15. Give five worker demotivators.
shows the location of all - Disrespectful treatment of
physical facilities, machines, workers
and materials involved in a - Lack of sense of
process. accomplishment
- Layout diagrams assist in - Nonavailability of materials
reducing the number of and tools
material movements and the - Necessity to redo work
distance between operations. - Confusion about the project
- The objective is to position 16. Give five worker motivators.
the materials and machines - Good relations between
so that the shortest possible crafts
path can be used without - Good worker orientation
programs
- Good pay - Forms the basis for
- Enjoyable work managers to issue
- Well-planned projects. instructions to subordinates.
17. Briefly discuss the influence of - Establishes the planned
human factors on construction sequence for using
productivity. personnel, materials,
- It is important to remember machines, and money.
that people are essential to 3. During Construction
the construction process. - Enables the manager to
Workers who are fatigued, prepare a checklist of key
bored, or hostile will never dates, activities, resources,
perform at an optimum level etc.
of effectiveness. - Provides a means for
evaluating the effect of
16 - PLANNING AND SCHEDULING changes and delays.
1. Explain PLANNING and - Serves as the basis for
SCHEDULING evaluating progress
- PLANNING must be done to - Aids in coordinating
perform any function with resources
minimal wasted time and 4. After completion of Construction
effort. - Permits a review and
- SCHEDULING is utilized for analysis of the project as
many phases of the carried out.
construction process, from - Provides historical data for
master planning through improving future planning
facility construction to facility and estimating.
operation and maintenance. 5. What are the SCHEDULING
- SCHEDULE is nothing more PRINCIPLES?
than a time-phased plan. - Establish a logical sequence
- SCHEDULES are used as of operations
guides during the - Do not exceed the available
performance of an operation resources' capabilities
to control the pace of - Provide for continuity of
activities and permit the operations
operation completion at the - Start project controlling (or
desired or required time. critical) activities early.
2. Before starting PLANNING AND 6. How important is the accuracy of
SCHEDULING scheduling?
- Provides an estimate of the - The accuracy of an estimate
time required for each portion of the time it will take to
of the project and the total perform a construction
project. operation is a function of the
- Establishes the planned rate kind of work involved and
of progress
prior experience in doing that
sort of work.
7. Planner’s work
- The planner must thoroughly
understand the nature of the
work to be performed and the
relationship between the
various work items making
up the project.
8. Explain BAR GRAPH METHOD
- The bar graph or bar chart
schedule is a graphical
schedule relating the
progress of work items to a
schedule.
- Gantt charts, developed by
Henry L. Gantt
9. What schedule form is widely used
in construction work?
- Bar graph schedule is still the
most widely used schedule
form found in construction
work because it is an easily
understood format.

You might also like