Quality Control Plan in Medium Construct
Quality Control Plan in Medium Construct
WALEED
ABD EL-RAHAMN
IBRAHEM
ELMALLAH
Student ID:
UM34553BPR43127
ACKNOWLEDGMENTS
I’m deeply thankful to Allah by His Grace the present work was realized
I would like to express my best regards and appreciation to
ATLANTIC INTERNATIONAL UNIVERSITY specially the Advisor
Dr. Rosa Hilda and Tutors Mrs. Amaila Aldrett, Mr. Edward Lambert and
Mrs. Lourdes Puente for his instructive supervision, providing facilities,
continuous advice and encouragement.
I would like to express my deep and sincere gratitude and a special
acknowledgment to Eng. Abd Elrahman Elmallah my father and my
teacher for his encouragement, support and most of all his patience for
which I am truly grateful.
Grateful thanks to Prof. Dr. Eng. Ashraf Bastawisy, PhD the project
consultant, Professor of Architecture, National Center for Buildings
Research, for his fruitful help during the whole work of this thesis.
Can’t forget the preferred of Oryx Construction Industry team
specially Eng. Tamer Adham Oryx’s CEO.
My deep feelings towards my beloved mother, for her sincere help,
support and enduring the difficult times during this work.
A special debt of gratitude is gladly acknowledged to my wife Rania
for her help and encouragement and words could never express.
My gratitude is also extended to my Brother Eng. Amr Elmallah
CEO of Elmallah for Engineering & Contracting,
My deep feelings to my daughter Hana for helping and supporting
me and my baby Jana
Finally, I am also grateful to my Father and Mother in law for their
encouraging and supporting me.
PREFACE
In this thesis, Quality Control Plan have been investigated in a case study
which helped to realize how the construction industry works with this
concept. The research has been carried out from June 2014 to December
2014, at the Department of Civil Engineering, Atlantic International
University, USA.
The thesis has been carried out with Oryx Construction Industry,
a contracting company, where National Bank of Egypt VIP branch project
has been investigated in order to do this research. The research has also
been supervised by Atlantic International University and an examination
of the thesis regarding the language and formatting was made by Dr. Rania
Eltelbany, MSc. We appreciate for their help in this thesis.
TABLE OF CONTENT
Abstract
Abbreviations
Chapter 1
Introduction
Chapter 2
Project Description
Chapter 3
Project Organization
Chapter 4
Quality Control Method
Chapter 5
Inspection
Chapter 6
Field Testing Procedure
Chapter 7
Submittals
Chapter 8
Documentations
Chapter 9
Revision to Work
Chapter 10
Definable Features of Work
Chapter 11
Pictures of the Project After & Before Implementation
Appendix
References
LIST OF FIGURE
Figure 1.1 The outline of the thesis
ABSTRACT
Project Quality Management includes the processes and activities of the
performing organization that determine quality policies, objectives, and
responsibilities so that the project will satisfy the needs for which it was
undertaken. It implements the quality management system through
policy and procedures with continuous process improvement activities
conducted throughout, as appropriate.
The Project Quality Management processes include the following:
- Plan Quality: The process of identifying quality requirements
and/or standards for the project and product, and documenting how
the project will demonstrate compliance.
- Perform Quality Assurance: The process of auditing the quality
requirements and the results from quality control measurements to
ensure appropriate quality standards and operational definitions are
used.
- Perform Quality Control: The process of monitoring and recording
results of executing the quality activities to assess performance and
recommend necessary changes.
These processes interact with each other and with the processes in the
other Knowledge Areas. Each process can involve effort from one or
more persons or groups based on the project requirements. Each process
occurs at least once in every project and occurs in one or more of the
project phases, if the project is divided into phases. Although the
processes are presented here as discrete elements with well-defined
interfaces, in practice they may overlap and interact in ways not detailed
here.
Project Quality Management addresses the management of the project
and the product of the project. It applies to all projects, regardless of the
nature of their product. Product quality measures and techniques are
specific to the type of product produced by the project. While quality
management of software products uses different approaches and
ABBREVATIONS
NBE National Bank of Egypt Client
QC Quality Control
1. INTRODUCTION
This QCP (Quality Control Plan) will be implemented to ensure
remedial and construction procedures are performed in compliance with
the plans and specifications under the contract of The NBE (National
Bank of Egypt).
The quality control measures as presented herein include quality control
organization; methods of performing, documenting, and enforcing quality
control operations from ORYX (Oryx Construction industry)
(including inspection and testing); inspections to be performed; and
protocol describing corrective actions.
Overall management of the QCP (Quality Control Plan) will be the
responsibility of QCM (ORYX Quality Control Manager).
The QCM will have the authority to act in all matters and will be
responsible for ensuring that all materials and work comply with the
contract specifications. All inspection and testing firms will be at the
disposal of the QCM to ensure that all aspects of work are compliant with
the contract. The QCM will report any deviations from the QCP
independently to the On-site Project Manager. The resume of the ORYX’s
team designated attached.
1.1 Purpose
The purpose of this master thesis is to evaluate how the QCP process
is used in the construction industry and how the practitioners are
managing it every day. The theory of the quality control management
process will be compared to the actual practice in order to investigate
similarities and differences. In other words, the main idea is to see if
the construction industry is working with QCP as it is described in
the literature regarding the methods and techniques presented.
1.2 Limitations
The research focuses on the construction industry and is based on
theories of QCP described in the literature. The research was
complemented by a study of a construction project in Oryx
DEFINABLE
REVISIONS FEATURES
TO WORK OF WORK
RESULT
INTRODUCTION THEORY
QUALITY CONCLUSION
PROJECT CONTROL
INFORMATION METHODS
2. PROJECT DESCRIPTION
2.1 LOCATION
The building in Elmarghany St - Masr El-Jadeda – Cairo – Egypt.
Latitude: 30° 5'15.17"N Longitude: 31°20'2.98"E
3. PROJECT ORGANIZATION
The ORYX’s key personnel assigned to this project have possessed a
broad range of remedial action experience and skills. All have experience
dealing with the handling of contaminated wastes and should be familiar
with requirements of day-to-day work under this contract.
The ORYX’s proposed project organization for this project and the
resumes of key personnel, along with their job titles, will be submitted for
review and approval. A conceptual project
Organizational Chart is included in Appendix.
The functional responsibilities of key technical personnel are summarized
as follows.
President
CEO
On-Site
Project QCM
Manager
Technical Civil
Mechanical Elec.
Office
Engineer Engineer Engineer
Engineer
Oryx CEO
On-site Project Manager
Quality Control Manager
The Quality Control Manager will report directly to the On-site Project
Manager with matters concerning quality control. He will have both the
authority and the duty to halt any operation appearing to be out of
compliance with contract specifications.
The QCM is responsible for keeping and maintaining all records related
to personnel, supplies, equipment use, and equipment calibration and
sampling. His function will be to ensure compliance with the contract
plans and specifications.
• Serving as main point of contact at the site for client questions and
discussions on quality and technical issues.
• Delegating duties to alternate QCMs and notifying consultant to whom
what duties have been delegated.
The QCM or an alternate will be on-site when work is being performed.
4.1 IMPLEMENTATION
The QCM will be responsible for implementing the QCP by ensuring that
quality materials and supplies are provided for the proposed project, and
that good workmanship is provided in all aspects of this contract. The
QCM will report directly to the On-site Project Manager and will
complete daily site inspections to ensure compliance with the quality
control specifications.
Daily reports will be completed listing all field testing and sampling
activities. These reports will be submitted to ACH on a daily basis. The
QCM will be responsible for ensuring that all materials and work comply
with the contract plans and specifications, and that all performance
standards are met.
It is anticipated that the ACH and the QCM will meet frequently in order
to forecast and/or prevent any potential problems from arising. An on-site
quality control meeting will be conducted on a weekly basis as part of the
weekly progress meeting in order to review performance during the
previous one-week period, and prepare for the upcoming two-week
period. It is anticipated that the ORYX’s On-site Project Manager, Health
and Safety
Officer and ACH will attend this meeting.
4.2 DOCUMENTING
The QCM will record project activities in a daily quality control report
maintained on site at all times. All site activities, site inspections, and
field testing of materials will be recorded on a daily basis, along with any
unacceptable site occurrences or deficiencies and their associated
corrective actions. Each daily entry into the report will be signed by the
QCM. Quality control reports will be submitted on a daily basis during
all field project activities.
5. INSPECTIONS
To ensure that all finishing and remedial activities comply with the
project specifications, the
QCM will complete, in conjunction with the subcontractors, three phases
of site inspections for each feature of work. These inspections will include
the following:
7. SUBMITTALS
This section describes the procedures for ACH processing of submittals.
The QCM will administer and control the processing of submittals.
After being reviewed for completeness, submittal documents will be
transmitted to the relevant project staff for review and verification for
compliance with contract requirements.
The submittal’s disposition will be noted on the submittal, which will be
signed, dated and returned. If required, ORYX will revise the submittal,
incorporating the comments and will resubmit it for review and
verification for compliance. Submittals will be logged and copies will be
retained in the project files. The ACH will follow standard procedures
concerning submittals, including the use of the QCM or ORYX
transmittal form. Each submittal form may contain more than one
submittal specific to that specification section.
This includes reviews of materials and suppliers’ catalog cuts, as well as
subcontractor submittals.
7.1 SUBMITTAL SCHEDULE
ORYX will submit and maintain a submittal schedule. The QCM will
review and after consulting ACH will approve the submittal schedule.
The schedule will be initially submitted within 14 days after the award
of the contract and then monthly with the monthly baseline schedule
updates.
The QCM shall work with the contractor to prioritize and sequence
submittals so that the most critical submittals are received and processed
first.
The submittal schedule will become the baseline against which receipt
of all required submittals will be compared. The approved submittal
schedule will be forwarded to NBE.
8. DOCUMENTATION
All testing results will be recorded on the daily quality control report. A
sample Daily QC report is included in Appendix. Any concerns or
deviations from the required material specifications and the actions taken
to correct the problems will be noted on the report. Information recorded
on the daily quality control report will include:
• Definable features of work that was addressed.
• Description of trades working on the project.
• Numbers of personnel.
• Types and numbers of tests performed.
• Results of testing.
• Nature of defects or cause for rejection.
• Proposed corrective action(s).
• Corrective action taken and date.
• Delays encountered.
• Directions received from the Engineer and actions taken.
• Health and safety issues or deficiencies and how they were
resolved.
• Deficiencies.
As example Pre-Final Inspection Checklist include:-
- Electrical
1. All lights
2. All outlets
3. Exhaust fans
4. Ceiling fans, attic fans
5. Breaker panel is properly labeled
6. Electrical system is properly grounded
- Plumbing
1. Each fixture has a shut off valve
2. Fixture drains properly
3. Floor drains work correctly
- Smoke detectors
1. Smoke detectors installed per plans
2. Smoke detectors work properly
3. Batteries installed in each unit
- Tempered glass
1. Tempered glass installed in proper locations (bathroom
tub surrounds, in doors, windows, next to doors, etc.)
- Windows and doors
1. All exterior doors close and lock
2. All openable windows open and lock
9. REVISIONS TO WORK
ORYX will be responsible for ensuring total compliance of field work to
the project specifications. Should modifications or revisions to the
specifications become necessary, ORYX will make the request, in
writing, to ACH Approval from ACH must be received prior to allowing
the modifications or revisions to be made in the field. The QCM will be
informed of and record all such requests in his daily log and on the daily
quality control report.
9.1 Design Review
Before starting implementation the entire design was reviewed by the
technical office Department it reviewed all of the design documents, the
QC plan and require compliance and documentation.
All major reconstruction projects will be reviewed by the Department at
key stages of development. These “Phase” reviews will take place at the
plan submittal.
Mechanical work
Pluming work
AC work
Firefighting Work
Electrical work
Low current electricity work
CCTV work
Demobilization
According to project BOQ
Construction Activities Contractor Primary Contact
☐ Force Mains
☐ Masonry
☐ HVAC
☐ Plumbing
☐ Electrical
☐ Proofing
APPENDIX
TYPICAL CONSTRUCTION FORMS
Construction QC/QA Plan
The following typical forms are used:
Distribution System
PROJECT NAME:
PRECIPITATION: INCH(S)
MEETING:
Certification: I certify that the above report is complete and correct and that I, or my representative, have
inspected the work performed this day by the Subcontractors and have determined that all materials,
equipment, and workmanship are in strict compliance with the Contract Documents, Plans
and Specifications. Any exceptions to these contract requirements will be noted above.
EXCAVATION OF TRENCHING
a) Is bedding fully compacted to support pipe or utility at line, grade, and slope required and
verified by inspector?
QC SIGNATURE: DATE:
CONTRACTOR:-------------------------------------------------------------------------------------------------------------------------
TYPE OF DELIVERY:----------------------------------------------------------------------------------------------------------------
WEATHER CONDITIONS:----------------------------------------------------------------------------------------------------------
CONDITION OF FINISH:----------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------------------
OBSERVATIONS/REMARKS:-------------------------------------------------------------------------------------------------------
REPLACEMENT VERIFICATION
1. ELECTRICAL SUPERVISOR: ITEMS TO BE CHECKED
CABLES/GROUND WIRE CONDUIT BOXES OTHER
COMPLETE/ACCEPTABLE TO DRAWING ---------- REV-----------------
-------------------- ---------------
SIGNATURE DATE
2. MECH./PIPING SUPERVISOR: ITEMS TO BE CHECKED
MECHANICAL INSERTS PIPING SLEEVES MECH. FRAMES OTHER
COMPLETE/ACCEPTABLE TO DRAWING---------- REV. -------------
--------------------- --------------
-------------------------------------------------------------- SIGNATURE DATE
3. CIVIL/STRUCT. SUPERVISOR: ITEMS TO BE CHECKED
ROCK CROSS SECTIONS TAKEN ROCK SURFACES PREPARED
SCREEDS SET LINE AND GRADE ESTABLISHED
FORMS REINFORCING STEEL
ALIGNMENT BRACING/SHORING CORRECT SIZE/GRADE LOCATION
INTERIOR SURFACE RELEASE AGENT LAPS. ADEQ. SECURED LEAN
CONSTRUCTION JOINTS PREPARED WATER STOPS WIRE TIES/FORM RODS
PLACEMENT/CONSOLIDATION EQUIPMENT AVAILABLE/ADEQUATE
SAFETY PRECAUTIONS OBSERVED FINAL CLEANING ACCEPTABLE
ACCEPTABLE TO DRAWING REV.--------------- ---------------------- ----------------------------
SIGNATURE DATE
QUALITY CONTROL INSPECTION VERIFICATION ---------------------------- ----------------------------
SIGNATURE DATE
OBSERVATIONS/REMARKS -------------------------------------------------------------------------------------------------------------
AUTHORIZATION FOR PLACEMENT -------------------------------------------- ----------------------------------
QC MANAGER: DATE
Set on pallet or dunnage to prevent contact with the ground or rain water?
Isolated from other material to prevent contamination?
MATERIALS
BRICK WORKING
Are Wall thickness and opening locations match with shop drawings?
Are Grade and walls within tolerance?
Continuing Raising of wall height acceptable and or within allowable limit?
REMARKS:
QC SIGNATURE: DATE:
REMARKS:
QC SIGNATURE: DATE:
Is cement Portland?
Water quality good?
Is fine aggregate free from mud and impurities?
Is used equipment are adequate?
Is cement slurry thickness and mix ok?
REMARKS:
QC SIGNATURE: DATE:
MATERIALS
Types of paints are according to specification?
Is corresponding color?
All required equipment’s are available?
PAINTING
Check wall surface is ready for painting?
Applicable color and finishing type are ok?
Used materials are match with specification?
Provide adequate equipment?
Colors are match with required?
Finishing processes are according to requirement?
Weather condition good for process?
Painting materials have required concentration?
Applied surfaces are free from brush marks?
Finishing surfaces are according to approved drawings?
REMARKS:
QC SIGNATURE: DATE:
Appendix ORQ9: Electrical Inspection Check List for Cable & Cable
Accessories / Panel
Board / Wiring Devices
Low voltage power cable in outlet box and panel board properly connected?
Cable size color code is correct and identification tags are installed at panel board/outlet
boxes?
Installed terminal lugs are correct size and application?
All conduit and outlet boxes and panel board properly grounded?
Continuity and grounding test complete?
QC SIGNATURE: DATE:
Appendix ORQ10: Electrical Inspection Test Sheet for Electrical Service and Distribution System
REMARKS:
QC SIGNATURE: DATE:
Lighting fixture and fittings are installed correctly and tightly as specified in
the specification?
Lighting fixture fitted with fuse holder and enclosure cover?
Cable wire color code is correct and identification tags installed at panel
board? Continuity and grounding test completed?
All wire entries are sealed with a non-setting sealant?
Lighting photo cell control is correctly installed?
REMARKS:
QC SIGNATURE: DATE:
All sanitary appliances are as specified in material schedules, specifications and AFC
drawings?
Pipe ends are properly cleaned before applying the solvent cement and joining ?
Pipes are properly stored and free of debris?
All tests as specified are proposed in the sewerage piping network and test packs are
signed off?
REMARKS:
QC SIGNATURE: DATE:
Pipe sizes, types, makes are as specified in material schedules /AFC drawings/specifications
Valves are installed properly, can be accessed easily, no obstructions for turning valve
handles?
Pumps are installed with all accessories, slope of suction pipe is maintained properly as given
in AFC drawing and specifications, proper workmanship practice are used so that no air
entrapped in the suction pipe?
Materials of pipe supports are used as specified in project specifications?
Distance between supports is as per close 5.3 of Section 3 (Water supply and sewerage) of
project specification?
Pipes are stored properly and internal surface is free of debris?
Pipe ends are properly cleaned and prepared before applying solvent cement and joining?
Visual inspection of pipe joints, all joints are solvent cement bonded?
Specified testing is in the water supply piping network is performed and test packs are signed
off?
REMARKS
QC SIGNATURE: DATE:
Name:
Project
No:
Date of
Inspection:
Inspector:
Punch
Description of Completion or Correction
Item
Acceptance
Electrical
1. All lights
2. All outlets
3. Exhaust fans
4. Ceiling fans, attic fans
5. Breaker panel is properly labeled
6. Electrical system is properly grounded
Notes:
Plumbing
1. Each fixture has a shut off valve
2. Fixture drains properly
3. Floor drains work correctly
Notes:
Smoke detectors
1. Smoke detectors installed per plans
2. Smoke detectors work properly
3. Batteries installed in each unit
Notes:
Tempered glass
1. Tempered glass installed in proper locations (bathroom tub
surrounds, in doors, windows, next to doors, etc.)
Notes:
Notes:
Miscellaneous
1.
2.
References
2- Construction Management
(second edation) – By Daniel W Halpin Purdue University - Ronald W.
Woodhead University of New south Wales 1998.