BOQ SUMMARY

Project Name: Le_Jardin

Element : Column

No. Material Unit Quantity Rate ₱ Cost ₱


1 Concrete C21 (cum) 33.74 3500.00 118090
Sub Total 33.74 1,18,090

2 Rebar #10 (Fy276) (kg) 3264.04 50.00 163202


3 Rebar #10 (Fy410) (kg) 86.65 50.00 4333
4 Rebar #10 (Fy414) (kg) 86.47 50.00 4324
5 Rebar #12 (Fy276) (kg) 528.26 50.00 26413
6 Rebar #16 (Fy276) (kg) 1869.00 50.00 93450
7 Rebar #20 (Fy276) (kg) 1737.00 50.00 86850
8 Rebar #20 (Fy410) (kg) 15.00 50.00 750
9 Rebar #25 (Fy276) (kg) 616.00 50.00 30800
10 Rebar #25 (Fy410) (kg) 121.00 50.00 6050
11 Rebar #25 (Fy414) (kg) 146.00 50.00 7300
12 Rebar #32 (Fy276) (kg) 75.00 50.00 3750
Sub Total 8544.42 4,27,221

13 Shuttering (sqm) 221.22 1500.00 331830


Sub Total 3,31,830

Grand Total 8,77,141

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 253.24 kg/cum
2 Consumption : Reinforcement/Planarea = 24.41 kg/sqm
3 Consumption : Concrete/Planarea = 0.10 cum/sqm
4 Concrete % C21 = 100.00 %
5 Shuttering = 6.56 sqm/cum