Abstract. Indonesia is one of the other countries with a high productivity level in the construction industry.
As the construction industry increases, some things must be considered in construction management, namely
cost, time, and quality. In this study, the authors focus on the analysis of formwork in terms of cost by using
unit price analysis which refers to PUPR and unit prices in each province. This research resulted in an analysis
of the formwork method, which is more cost-effective in the shear wall work of the Faculty of Art and Design
Education Building. The results showed that using the aluminium formwork method has an average cost of
36% more economical than conventional methods, and semi-system methods.
____________________________________
*Corresponding author: aldhi.wiguna@binus.ac.id
© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative Commons Attribution License 4.0
(https://creativecommons.org/licenses/by/4.0/).
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023
2
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023
several formwork methods, namely the conventional Tabel 1 Volume Shear wall of the Faculty of Artand Design
method, the semi-PERI system method, and aluminum in Education
terms of cost.
Floors Qty (units) Volume (m2)
Basemant – 1st floor 4 370,80
4. Data analyis 2nd floor – 6th floor 10 865,20
In knowing the budget plan spent on shear wall formwork 7th floor 2 276,04
in the Faculty of Art and Design Education (FPSD) Total 16 1512,04
building, formwork volume data is needed. In this FPSD In addition to shear wall area data, unit labor price
building, shear walls and columns are one part. So the analysis data is also needed to be used in calculating the
formula for the area of the formwork used must be slightly budget plan. The unit prices to be reviewed are the unit
modified. The volume of shear wall formwork in the prices for materials, tools, and wages, which consist of the
Faculty of Art and Design Education Building can be seen coefficient values for each job description, and the unit
as follows: price for materials. The unit price analysis for shear wall
formwork is presented in Table 2.
No. Description Units Coefficient Unit Price (Rp.) Total price (Rp.)
LABOR
Worker OH 0,660 Rp 161.636 Rp 106.679,76
Carpenter OH 0,330 Rp 160.500 Rp 52.965,00
1
Chief Carpenter OH 0,033 Rp 177.600 Rp 5.860,80
Foreman OH 0,033 Rp 189.700 Rp 6.260,10
Total Manpower (A) Rp 171.765,66
MATERIAL
Class III wood m3 0,030 Rp 4.747.345 Rp 142.420,35
Nail Size 8 cm to 12 cm kg 0,400 Rp 22.000 Rp 8.800,00
Formwork Oil ltr 0,200 Rp 39.449 Rp 7.889,80
Class II wooden beams m3 0,020 Rp 6.265.890 Rp 125.317,80
2
Multiplex 12 mm (122 x 244) sheet 0,350 Rp 172.400 Rp 60.340,00
Dolken Wood, 8–10 cm pcs 3,000 Rp 43.100 Rp 129.300,00
Formwork Distance Guard / Spacer pcs 4,000 Rp 15.135 Rp 60.540,00
Total Material Prices (B) Rp 534.607,95
Total Material Price 3x Usage Rp 178.202,65
EQUIPMENT
3 -
Total Equipment Prices (C) -
4 Total Unit Price Rp 349.968,31
5 Overhead & Profit Rp 17.498,42
6 Work Unit Price Rp 367.466,73
Table 3 Analysis of the unit price for semi-system PERI Shear Wall Formwork
No. Description Units Coefficient Unit Price (Rp.) Total price (Rp.)
LABOR
Worker OH 0,660 Rp 161.636 Rp 106.679,76
Carpenter OH 0,330 Rp 160.500 Rp 52.965,00
1
Chief Carpenter OH 0,033 Rp 177.600 Rp 5.860,80
Foreman OH 0,033 Rp 189.700 Rp 6.260,10
Total manpower (A) Rp 171.765,66
3
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023
No. Description Units Coefficient Unit Price (Rp.) Total price (Rp.)
MATERIAL
Hollow 50x50 pcs 0,167 Rp 154.700 Rp 25.834,90
Hollow 50x100 pcs 0,167 Rp 276.800 Rp 46.225,60
Screw nails 12 mm pcs 24 Rp 500 Rp 12.000,00
2 Formwork Oil ltr 0,200 Rp 39.449 Rp 7.889,80
Tie Rod & Wing Nut set 1,000 Rp 68.500 Rp 68.500,00
Plywood 12 mm (Phenol Film) sheet 0,350 Rp 255.000 Rp 89.250,00
Total Material Price (B) Rp 249.700,30
Total Material Price 6x Usage Rp 41.616,72
EQUIPMENT
3
Total Equipment Prices (C)
4 Total Unit Price Rp 213.382,38
5 Overhead & Profit Rp 10.669,12
6 Work Unit Price Rp 224.051,50
Table 4 Analysis of the Unit Price for Aluminum Shear Wall Formwork
No. Description Units Coefficient Unit Price (Rp.) Total price (Rp.)
LABOR
Craftsman OH 0,330 Rp 160.500 Rp 52.965,00
1 Chief Craftsman OH 0,033 Rp 177.600 Rp 5.860,80
Foreman OH 0,033 Rp 189.700 Rp 6.260,10
Total Manpower (A) Rp 65.085,90
MATERIAL
Alumunium Panel m2 0,336 Rp 1.950.000 Rp 655.200,00
Round Pin pcs 2,000 Rp 5.000 Rp 10.000,00
Wedge Pin pcs 2,000 Rp 5.000 Rp 10.000,00
2 Flat tie pin pcs 2,000 Rp 5.000 Rp 10.000,00
Minyak Bekesting ltr 0,200 Rp 39.449 Rp 7.889,80
Pipe Support unit 0,368 Rp 450.000 Rp 165.600,00
Release pcs 0,368 Rp 207.000 Rp 76.176,00
Total Material Price (B) Rp 934.865,80
Total Material Price 8x Usage Rp 116.858,23
EQUIPMENT
3
Total Equipment Prices (C)
4 Total Unit Price Rp 181.944,13
5 Overhead & Profit Rp 9.097,21
6 Work Unit Price Rp 191.041,33
Type of Price
No Total Price (Rp)
formwork Material (Rp) Manpower (Rp)
1 Conventional Rp 286.798.320 Rp 272.702.376 Rp 559.500.696
2 PERI Semi-System Rp 105.319.841 Rp 272.701.820 Rp 378.021.661
3 Aluminum Rp 185.529.026 Rp 103.333.108 Rp 288.862.135
4
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023
5
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023
floors to be worked on, therefore the semi-PERI system December. United States: The McGraw-Hill
method can be used on these floors because the PERI Companies, (2011).
semi-system formwork can only be used 6 times. The use [3] R. Thiyagarajan, V. Panneerselvam, and K.
of formwork in shear wall work that is more than 6 times, Nagamani, “Aluminium Formwork System Using In
in buildings with the same characteristics as the building Highrise Buildings Construction,” Int. J. Adv. Res.
for the faculty of art and design education, it is Eng. Technol., vol. 8, no. 6, pp. 29–41, (2017),
recommended to use the aluminum formwork method. http://www.iaeme.com/IJARET/index.asp29http://w
ww.iaeme.com/ijaret/issues.asp?JType=IJARET&VT
This study has limitations on unit price data and the
ype=8&IType=6http://www.iaeme.com/ijaret/issues.a
coefficients used in each formwork method because sp?JType=IJARET&VType=8&IType=6http://www.i
researchers only use the coefficients found in other high- aeme.com/IJARET/index.asp30.
rise building construction due to limited data on the
[4] N. U. Barus, J. Sjah, and A. D. Rarasati,
projects studied. for the future, in researching unit prices, “Performance evaluation of woven polyethylene
researchers must analyze each job to obtain a valid formwork on tie beam and pile cap structure in terms
coefficient according to the consumables contained in the of cost and time,” Civ. Eng. Archit., vol. 8, no. 3, pp.
construction building and the recently constructed unit 305–311 (2020). doi: 10.13189/cea.2020.080314.
price. because each contractor has different unit prices and [5] N. Kabashi, C. Krasniqi, and Q. Kadiri, “Formwork
coefficients. for Modern and Visual Concrete,” no. July (2017)
https://www.researchgate.net/publication/318373680
%0AFORMWORK.
6. Conclusion
[6] H. S. Pratama, R. K. Anggraeni, A. Hidayat, and R.
Based on the results of the research conducted by the R. Khasani, “Analisa Perbandingan Penggunaan
author regarding the comparison of the formwork method Bekisting Konvensional, Semi Sistem, Dan Sistem
in the shear wall work of the Faculty of Art and Design (PERI) Pada Kolom Gedung Bertingkat,” Suparyanto
Education (UPI) building project, several conclusions were dan Rosad, vol. 6, no. 1, pp. 303–313 (2017).
http://ejournal-s1.undip.ac.id/index.php/jkts.
obtained. The following are the conclusions obtained from
the above research: [7] P. Arumsari and C. Xavier, “Cost and time analysis
1. The cost of formwork work on shear wall work in the on the selection of formwork installation method,”
FPSD building with reference to the West Java IOP Conf. Ser. Earth Environ. Sci., vol. 426, no. 1,
(2020) doi: 10.1088/1755-1315/426/1/012042.
Province Unit Price Book, with the conventional
method has a cost of up to Rp.559,500,696, for [8] J. Tistogondo, F. Kurniawan, and A. Firdaus, “The
aluminum formwork a fee of Rp.378,021,661 is Comparison between Semi Conventional and Peri
6FDIIROGLQJௗ&RVWDQG7LPH&RPSDULVRQDW
received, while for the PERI semi-system, it is
Tunjungan Plaza 6 Project in Surabaya The
Rp.378,021,661. Comparison between Semi Conventional and Peri
2. It can be concluded that for a building with 6FDIIROGLQJௗ&RVWDQG7LPH&RPSDULVRQDW
characteristics such as the FPSD building which has Tunjungan Plaza 6 Project in Sura,” no. November,
seven floors and a symmetrical structure, it is advisable (2015) doi: 10.13140/RG.2.1.4408.4566.
to use the aluminum method for the shear wall [9] O. Guspari, R. Hidayati, Z. Mirani, and P. Wike
formwork work. This is because the cost of work is Amelia, “Jurnal Ilmiah Rekayasa Sipil Analisis
more effective, compared to conventional methods and Perbandingan Biaya Pekerjaan Bekisting
semi-PERI systems which have an average difference Konvensional dan Bekisting Sistem Pada Bangunan
of 36% more expensive. Gedung,” vol. 19, no. 1, pp. 3–4 (2022)
http://ejournal2.pnp.ac.id/index.php/jirs/Terakreditasi
SINTAPeringkat5.
References [10] A. Muis and Trijeti, “Analisis Bekisting Metode Semi
Sistem Dan Metode Sistem Pada Bangunan Gedung,”
[1] Z. Huszár and É. Lublóy, “Examination of The Cost
Univ. Muhammadiyah, Jakarta, pp. 27–38 (2012)
Ratio of The Formwork,” Acta Tech. Jaurinensis, vol.
https://jurnal.umj.ac.id/index.php/konstruksia/article/
14, no. 2, pp. 155–170 (2021) doi:
view/261/237.
10.14513/actatechjaur.00598.
[11] D. Rahadianto, D. Perwitasari, and A. R. H. Mashur,
[2] R. L. Peurifoy and G. D. Oberlender, Formwork for
“Analisa Perbandingan Penggunaan Bekisting
Concrete Structures, McGrawHill., vol. 1999, no.
Aluminium, Bekisting Konvensional, Semi
6
E3S Web of Conferences 426, 02075 (2023) https://doi.org/10.1051/e3sconf/202342602075
ICOBAR 2023