ENMG 611 - Unit C-2 - Aggregate Planning

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Aggregate Planning

Skycell, a major European cell phone manufacturer, is making production plans for the coming
year. Skycell has worked with its customers (the service providers) to come up with forecasts of
monthly requirements (in thousands of phones) as shown in the below table.
Manufacturing is primarily an assembly operation, and capacity is governed by the number of
people on the production line. The plant operates for 20 days a month, eight hours each day. One
person can assemble a phone every 10 minutes. Workers are paid 20 euros per hour and a 50
percent premium for overtime. The plant currently employs 1,250 workers. Component costs for
each cell phone total 20 euros. Given the rapid decline in component and finished-product prices,
carrying inventory from one month to the next incurs a cost of 3 euros per phone per month.
Skycell currently has a no-layoff policy in place. Overtime is limited to a maximum of 20 hours
per month per employee. Assume that Skycell has a starting inventory of 50,000 units and wants
to end the year with the same level of inventory.
Month Demand in 1000 units
January 1,000
February 1,100
March 1,000
April 1,200
May 1,500
June 1,600
July 1,600
August 900
September 1,100
October 800
November 1,400
December 1,700

a. Assuming no backlogs, no subcontracting, and no new hires, what is the optimum production
schedule? What is the annual cost of this schedule?
b. Is there any value for management to negotiate an increase of allowed overtime per employee
per month from 20 hours to 40?
c. Reconsider parts (a) and (b) if Skycell starts with only 1,200 employees. Reconsider parts (a)
and (b) if Skycell starts with 1,300 employees. What happens to the value of additional
overtime as the workforce size decreases?
d. Consider part (a) for the case in which Skycell aims for a level production schedule such that
the quantity produced each month does not exceed the average demand over the next 12
months (1,241,667) by 50,000 units. Thus, monthly production including overtime should be
no more than 1,291,667. What would be the cost of this level production schedule? What is
the value of overtime flexibility?

N. Nehme ENMG 611 Page 1 of 1

You might also like