BOQ OLT PKE06 to JAW-JI-PNG-2091

No. Code Item Specification Unit M/S Quantity Remark

1 OLT,AGG
1.1 OLT,AGG
Workload including but not limited to:
1.1.1 350000475604 OLT Outdoor cabinet (pole type,including the installation of ground cable and power cable) Installation & Acceptance The Sow includes installation of Mini OLT outdoor cabinet(Including OLT equipment and rectifier Module,600 mm (H) × 220 mm (W) × 380 mm unit S
(D))and Battery cabinet (Including one bank 14Ah battery with 4 units,600 mm (H) × 220 mm (W) × 380 mm (D)). Layout and connection of
power/grounding cables, optical cables, and laying AC cable to the existing Power meter box.
1.1.2 350000480387 Supply and install 700*800*800mm steel cage for outdoor pole mounted OLT cabinet (LN specification) set M+S
Workload including but not limited to:
1.1.4 350000475607 Supply and install of labelling for OLT Outdoor cabinet(pole type) 1.Provision and installation of 20 pcs label for OLT Outdoor as per specification. set M+S
2.Make OLT label (paint) according to Linknet standards and affixed to the device & then sprayed using pilox)

Workload including but not limited to:


1.1.5 350000475608 AGG cabinet installation 1.Including the installation of AGG cabinet(1800*700*700mm) with rectifier,inverter,144ODF,patchcord and 34 labels set S
2.Including the installation of 100ah battery with 1 unit into cabinet.

Workload including but not limited to:


1.1.6 350000475609 Reinforced concrete Foundation for AGG Outdoor Cabinet 1.Excavation ,cushion ,supply and construction reinforced concrete foundation.The foundation size is 1000*1000*200mm set M+S
2.Removal of surplus excavated soil from site

1.1.7 350000475610 Supply and install steel cage for outdoor cabinet (LN specification) Workload including but not limited to: set M+S
Construction of steel cage with pad lock for outdoor cabinet (LN specification) as per specification, including bolts and accessaries.
1.The actual space permit fee will escalate to LN with email and aprove by Linknet
1.1.8 350000480384 AGG site space Permit fee(Legworks + Payment) 2.Fund advance fee will 6% of the actual space permi fee unit S
3.Permit provide by Suncon with work permit and permit letter from space owner

1.1.10 350000475613 Service for Permit of New PLN connection 16A 1 phase Workload including but not limited to: Site S
Apply and payment to PLN Permit.For Termination of Upgrade PLN connection for 16A 1 phase.
Workload including but not limited to:
1.1.11 350000475614 Supply and Installation of KWH 1-Phase box with 2 MCB Supply and Installation of KWH 1-Phase Power Meter,2pcs 16A MCB and Power meter Box(The dimension of KWH Box is 90mm*20mm*60mm.) Site M+S
according to Indonesia PLN requirement, included new power cable if needed.
1.2 Survey and design for OLT

Workload including but not limited to:


1.Surveyors are required to wear a complete uniform (polite and neat), wear shoes and use a company ID card
2.Bring the necessary survey equipment and stationery (roll meter, stationery, boards, paper, base map, GPS, camera, survey request form /
1.2.1 350000475615 Service for Site Survey for OLT Outdoor house count, and permit letter). site S
3.Site Area (has no history of flooding, secure place, easy to reach by maintenance team)
4.Accessibility to Power/electricity requirements including the calculation(AC & DC)
5.Electrical Power grounding requirements
6.Making Survey Minutes signed by related parties (management / security) and the results become joint decisions

Workload including but not limited to:


1. Design description: Design basis, design standards, design scope/division of labor, engineering scale, and major workload.
2. Plane layout and installation of equipment, distribution frame, and cabinet, protective grounding, and lightning protection
1.2.2 350000475616 Service for As Plan Drawing for OLT Outdoor 3. Port type/port distribution design, cable/pigtail/network cable design site S
4. Material selection design
5. Indoor Cable Tray Design New/Reuse
6. Cable trough design (new construction/reuse)