QUESTION 1:
ACTIVITY PREDECESSOR DAYS
A - 3
B A 8
C B 5
D B 7
E B 3
F C, E 3
G F 6
Connect the nodes and dependencies for all the activities and calculate the Early Start
(ES), Early Finish (EF), Late Start (LS) and Late Finish (LF). The connection of the
activities and the outcome of the calculation of ES, EF, LS and LF should be illustrated in
a diagramme. (21 marks)
TOTAL MARKS = 21 X 5 %