.049 - Management of Change For Project HSE
.049 - Management of Change For Project HSE
Document Document
TL Q&HSE (MP&TS) TL Standards
Author: Coordinator:
1.0 Purpose/Scope
Projects undergo several changes during its lifecycle. While project alternatives and
changes are considered actively during the Front End of the project; (that is during
Identification and Concept Selection stages) once the Front End Engineering Design
(FEED) is finalized, any changes will have impact on the project. Such changes are
routinely monitored and controlled by existing project management practices in KOC.
Further, the Project Gate System (PGS) is the governing framework used by KOC for
selecting, planning and managing capital programs / projects in a consistent and
disciplined manner.
This Management of Change for Project HSE is intended to ensure that all HSE impacts
due to changes to projects after Gate Closures are reviewed and any risks involved are
mitigated prior to approval of the changes,
To this purpose, the procedure interfaces with the CTTP / Authorization of Scope of
Change and PGS processes and focuses on actions required to review changes,
identify and analyze HSE impacts and mitigate any risks involved.
The procedure will also supplement the PGS process by defining and tracking the
impacts on HSE due to changes in projects.
The request for change may arise from any source, called the Initiator of the proposed
change, and can be from any directorates, Contractors/Vendors or other stakeholders
of the Company. This Management of Change for Project HSE establishes the
requirements necessary to identify and control potential hazards or effects associated
with change. The procedure will further ensure that the impacts due to such changes
affecting the environment as well as the health and safety of personnel or potential
hazard to plant and equipment is properly recognized, reviewed, mitigated,
communicated and documented.
Control Tier 3 Revision Date: March 9, 2014
Uncontrolled Copy if Printed
KOC.GE.049 - Management of Change for Project HSE
Page 2 of 14
This procedure is associated with frozen or finalized baseline documentation and hence
excludes Stage1 (Identification) and Stage 2 (Concept Selection) stages of the project.
2.0 Definitions
2.1 Management of Change for Project HSE: For the purpose of applying the procedure
a change to the project will be considered in the following two cases:
4.1 Management of Change for Project HSE (After Closure of Gate 3.1-FEED
Stage)
Responsible Team Action required
4.1.1 Initiator of the Change Propose changes to the project scope,
specification, etc. as defined in 2.1..1 &
2.1.2. (Procedures as per Project Gate
System requirements)
4.1.2 Approves in principle for the proposed
Asset OTS (Requesting Team) changes
4.1.3 Controlling Team Receives request
(Major Projects / Project
Management /Any other KOC
Controlling Team)
No impact on HSE.
Proceed as per existing procedures &
PGS.
4.1.5 Controlling Team Conduct Meeting with concerned Teams to
(Major Projects / review the Form- MOCP-1 and finalize
Project Management/any other actions.
KOC Controlling Team
Signs at Section A.6 of the Form & attaches
the same to CTTP/SCOW Authorization
Form.
Participation by Q&HSE
(MP&TSD)Team(if the project handled by
Major project)Requesting Team, OTS &
Asset HSE
4.1.6 Requesting Team Authorization of actions by signing at
Section B of the Form
4.1.7 Controlling Team Receives the Form and attaches the same
(Major Projects / to the documentation required for
Project Management / any other reopening Gate 3.1 & forwards to Project
KOC Team Review Committee (PRC) for approval
4.1.8 Project Review Committee Approval for reopening Gate 3.1 from
(PRC) PRC.
Proceed as per PGS procedures.
4.1.9 Controlling Team Implement review Team action items as
(Major Projects / per Form MOCP-1
Project Management/any other
KOC Team Close out action items as per Form
MOCP-1 & Complete Section C of MOCP-
1
5.0 Procedure
During course of a project after closure of Gate 3.1, the ‘Changes to the Projects
(CTTP)’ form (Appendix C) is initiated by the concerned Major Projects Team whenever
there is any change to the project scope / technical specifications. In the CTTP Form, if
answer to the ‘HSE Impact’ item is yes, then Form MOCP-1– Assessment & Action for
HSE Impacts attached as Appendix E to the procedure has to be filled.
Meeting shall be conducted with all stake holders for review of the completed Form
MOCP-1 and finalization of actions. Form MOCP-1 shall be signed by the Engineer in
charge of design (PMC) and by the Team Leader of the Controlling Team.
The Form MOCP-1 shall be attached to the CTTP form and forwarded to Requesting
Team.
Requesting Team approves the CTTP form and the Form MOCP-1. On receipt of the
approval, Team Leader (Controlling Team) attaches the approved CTTP form and Form
MOCP-1, to the documentation required to reopen the Gate 3.1 and submits the same
to Project Review Committee.
Once approval for re-opening the Gate 3.1 is received the action in Form MOCP-1 shall
be implemented.
The change shall be accordance with Appendix-A – Management of Change for Project
HSE – Flow Chart (After Closure of Gate 3.1).
Meeting shall be conducted with all stakeholders for review of the completed form
PHSE-1 and finalization of actions. Form MOCP-1 shall be signed by the Engineer in
charge of design and by Team Leader Project Management Requesting Team.
Requesting Team approves the ‘Authorization to SCOW change’ Form as well as Form
MOCP-1 & the approved forms. Same are attached to the documentation required to
reopen the Gate 3.1 and submitted to the Project Review Committee.
Once approval for reopening the Gate 3.1 is received, the actions in Form MOCP-1 shall
be implemented. Please see, Appendix-A – Management of Change for Project HSE –
Flowchart (After closure of Gate 3.1) for further workflow.
5.2.1 After Closure of Gate 3.2, the contract is awarded and the project execution stage
starts. Changes to the project during project execution can be from KOC or the
Contractor.
In both the cases, a formal change notification shall be initiated by the contractor as per
existing project management practices. Additionally, the contractor shall be requested
to fill in the form MOCP-2 – Assessment & Actions for HSE impacts attached as
Appendix F and attach it along with the change notification. It shall be responsibility of
the contractor to fill in Form MOCP-2 and attach it with the change notifications.
5.2.2 Team Leader (Controlling Team) reviews the contractor’s notification and the
completed form MOCP-2 as per existing procedures. If there is an agreement on
contractors notification, then action items identified Form MOCP-2 are taken up and
implemented.
The change shall accordance with Appendix-B – Management of Change for Project
HSE-Stage 4 – Flow Chart for the further workflow.
The level of detail for such meeting should be appropriate for the complexity of the
proposed change and for the potential hazard the change poses. The meeting should
recommend any additional PHA studies including Fault Tree Analysis, Failure Modes
and Effects Criticality Analysis, HAZOP, Safety Integrity Level Assessment,
Environmental Impact Assessment, etc., as found appropriate and necessary to ensure
identification of HSE risks and its mitigation. Results of the meeting should be
documented.
Controlling Team should ensure that the documentation is in proper order and follow up
on the implementation process to ensure it is carried out as authorized.
Project HSE Plan shall be suitably updated to include the actions, if any arising out of
application of this procedure.
After the change has been implemented, Controlling Team must verify the following
(post-implementation tasks) & close out the management of change process:
Changes are performed as intended.
All affected personnel are aware of the change.
Essential training requirements are carried out.
Documentation is prepared properly and in order.
All Relevant Documents and Drawings are revised/ updated.
Each Form MOCP-1 or MOCP-2 in shall be designated a unique number utilizing the
following numbering system to maintain uniformity:
7.0 Abbreviations
CR : Concession Request
CTTP : Changes To The Project
SCOW : Scope of Work
PRC : Project Review Committee
PGS : Project Gate System
MP : Major Project
PM : Project Management
PHA : Process Hazard Analysis
PMC : Project Management Consultant
OTS : Operations Technical Services
MOCP-1: Management of Change for Project Form-1
MOCP-2: Management of Change for Project Form-2
Appendix A - Management of Change for Project HSE: Flowchart (After Closure of Gate 3.1-FEED Stage)
RESPONSIBILITY ACTION BY
Initiator of the Change Originator of the
Propose changes to the project scope Change/Initiator
(Procedures as per Project Gate System requirements)
1.0
Controlling Team • Evaluates the request as per existing PGS Procedures Team Leader
(Major Projects/Project 1.4 (Controlling Team)
• Checks the appropriate box in CTTP /SCOW Authorization Form if there is any impact
Management/Other) on HSE due to the proposed changes (Major Projects/Project
Management/Other)
1.5.1 1.5.2
Impact on HSE. No impact on HSE.
Fill in Form MOCP-1 for Assessing & Proceed as per existing procedures &
Identifying actions PGS
Controlling Team Sr. Engineer (Major
(Major Projects/Project Project
Management/Other) 1.6
Sr. Engineer / Project
Conduct Meeting with concerned Teams to review the Form-MOCP-1 and finalize actions. Management.
Sign at Section A.6 of the Form & attach the same to CTTP/SCOW Authorization Form.
Participation by Q&HSE
Team, Requesting Team,
OTS & Asset HSE
Requesting Team
1.7
Authorization of actions by signing at Section B of the Form Team Leader
Requesting Team
No 1.9
Approval for
Proceed as per PGS
reopening
procedures
Gate 3.1 from
PRC
Yes
Contractor Contractor
2.3 2.4
Not agreed.
Form returned to
Agree with contractor’s contractor with comments
change request for resubmittal.
2.6
Close out action items
2.7
Verifies the closure of action
Items by the Contractor
Attachments:
(Drawings/References):
HSE Impact Yes No (If yes, please complete Form MOCP-1 as per change Management for HSE, i.e. Project Procedure
Schedule Impact:
Cc:
__________________
XXXXXXXXXXXXXX
Please obtain in principle, approval from KOC Management in order to proceed with relevant AFE (‘s).
Concurrence to Proceed:
We have reviewed your recommendations and impacts
We have received authorization from KOC management to proceed
Please proceed as per your recommendations and required revision to the relevant AFE’s
Comments:
TL OTS / Requesting Team Signature: Date:______________________
Manager Concerned Asset Group Approval:
Date:______________________
Appendix D
__________________________________
Team Leader Project Management (Controlling Team)
cc: File
Appendix E
Form: MOCP-1
Management of Change for Project HSE (After Closure of Gate 3.1-FEED Stage)
Attachment to: CTTP / SCOW Authorization
Assessment & Actions for HSE impacts
Project No. & Stage: Previous Gate
(PGS) closed:
A. Assessment of the requested change
1. Brief description of the changes:
3.2 Safety
3.3 Environment
3.4 Others:
B. Authorization
Concurrence to Proceed as per 5 above: Team Leader (Requesting Team) Date:
C. Action Taken Report:
1. Studies revisited:
2. Recommendations closed:
Name & Sign. of Sr. Engineer In –Charge of design: Date Team Leader(Controlling Team) Date:
Appendix F
Form: MOCP-2
Management of Change for Project HSE (After Closure of Gate 3.2-Project Execution) Attachment to
Change Notification
Assessment & Actions for HSE impacts (To be filled by the Contractor)
3.2 Safety
3.3 Environment
3.4 Others:
B. Authorization
Concurrence to Proceed as per 5 above: Team Leader (Controlling Team). Date:
C. Action Taken Report:
1. Studies revisited:
2. Recommendations closed:
Name & Signature of Contractor’s Representative: