Price Offer - RCC Road Construction After Drain Line Shifting - ACI

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Avah Engineering

123(1st Floor), New Kakrail Road,


BMIS GROUP
Ramna, Dhaka-1000, Bangladesh. www.bmislk.com
Ph: 01771777780, 01758910802

Price Offer
TO: DATE: March 6, 2024
The Managing Director PR NO: 1R240200496
Advanced Chemical Industries Ltd. CEP NO: ACI/551/22
7, Hajeegonj Road, Godnyl, Narayanganj-1400 Mr. Tushar Mazumder
Kind Atten:
Executive, SCM
RCC Road Construction after Drain Line Shifting
SL Material Code Material Name Description Unit Rate Quantity Amount (Tk)
Earth excavation work upto 3 feet depth as per instruction
of ACI Engineer In-charge. Work is including of existing
dewatering with sufficient pump & accessories. Top of
cutting surface will be a dry bed, all existing water have to
remove with proper dewatering system where all
dewatering pipe, pump, accessories, hardware, labor etc.
all are contractor's scope. ACI will provide nothing
regarding this working item. All cutting soil have to be
shifted to outside of factory on everyday where shifting
place arrangement, loading, unloading, transportation, all
1 5000028829 Earth Excavation works necessary equipment (for dismantling, carrying, dumping CFT 35.00 14520.00 508,200.00
etc. all necessary work) are in contractor's scope. Billing
quantity will be as per structure width (e.g. base width &
length). All resources (whatever is required) of this work
are contractor's scope. Cutting side & bottom level must
be maintain uniform level with leveling instrument as per
design & instruction of ACI Engineer. Any type of
property damage will be carried by vendor during work.

Mixing Bricks Macadam with filling sand (ratio- 2 : 1),


filling and compaction with Rammer/ Mini roller. ACI will
provide 2" khoa & sand only and these materials will be
dumped at road side (about 500ft far from working place)
which carrying work is contractor's scope. All others
Sand-khoa compaction necessary labor, tools, hardware, materials & equipment
2 5000035514 CFT 63.00 4840.00 304,920.00
work. will be vendor's scope. Top level must be maintain uniform
level with leveling instrument as per design & instruction
of ACI Engineer. Any type of property damage will be
carried by vendor during work.

# HVAC
# Project Planning System Solution # Fire/Electrical/Building
and Development # Energy Saving Solution Safety/MEP Solution
Avah Engineering
123(1st Floor), New Kakrail Road,
BMIS GROUP
Ramna, Dhaka-1000, Bangladesh. www.bmislk.com
Ph: 01771777780, 01758910802
polythene cutting, Single Layer Polythene Laying on top of
Sand- khoa compaction surface. ACI will provide only
polythene roll and others all materials, equipment labor
Single layer Polythene are contractor's scope. Lapping will be minimum 150mm
3 5000035515 sft 7.00 4840.00 33,880.00
Laying as per instruction of ACI Engineer. Any type of property
damage will be carried by vendor during work.

Brick Hering bone Soling and gap filling with vitty sand.
ACI will provide bricks & sand only and these materials
will be dumped at road side (about 500ft far from working
Brick on edges place) which carrying work is contractor's scope. All
4 5000045225 pavement in herring others necessary labor, tools, hardware, materials & sft 40.00 4840.00 193,600.00
bone bond (HBB) equipment will be vendor's scope. Top level must be
maintain uniform level with leveling instrument as per
design & instruction of ACI Engineer. Any type of
property damage will be carried by vendor during work.
MS Rod fabrication work including binding & placing
position complete. ACI will provide MS Rod only. MS Rod
will be dumped at road side (about 500ft far from working
place) which carrying work is contractor's scope. All
MS Rod Fabrication
5 5000001883 others necessary tools, hardware, materials & equipment, Kg 17.00 4400.00 74,800.00
Works
annealed binding wire of 24 gauge, cutting machine,
bending machine etc. will be contractor's scope. Any type
of property damage will be carried by vendor during
work.
Supply of all shuttering materials, form work making,
placing and remove after 48 hours of casting for all the
RCC work of tank as per attached drawing. ACI will
provide nothing regarding this working item. All
Wooden Shuttering shuttering materials, wood, plain sheet, nails, necessary
6 5000055167 sft 90.00 400.00 36,000.00
work tools, hardware, materials & equipment, annealed binding
wire etc. will be contractor's scope

# HVAC
# Project Planning System Solution # Fire/Electrical/Building
and Development # Energy Saving Solution Safety/MEP Solution
Avah Engineering
123(1st Floor), New Kakrail Road,
BMIS GROUP
Ramna, Dhaka-1000, Bangladesh. www.bmislk.com
Ph: 01771777780, 01758910802
Cement, sand, brick chips Carrying, mixing with mixture
machine, placing, leveling, curing of reinforced cement
concrete work. ACI will provide Cement, sand, brick chips
only and these materials will be dumped at road side
(about 500ft far from working place) which carrying work
is contractor's scope. All others necessary labor, tool,
RCC Work.. hardware, materials &
7 5000035517 CFT 55.00 4020.00 221,100.00
equipment, Mixture machine, vibrator with nozzle will be
vendor's scope. Top level must be maintain uniform level
with leveling instrument as per design & instruction of
ACI Engineer. Any type of property damage will be
carried by vendor during work.

Total Amount 1,372,500.00

VAT-10% 137,250.00

Grand Total Amount (BDT) 1,509,750.00

In Word: (BDT) Fifteen Lac Nine Thousand Seven Hundred Fifty Only.
Note:
CEP: ACI/551/22.ACI will not allow any accommodation inside factory premises. All works have to be completed within 12 days after receiving of PO (5 days for mobilization and 7
days for execution). All safety measures, PPE, safety barrier are on vendor's scope. After completion of work vendor have to handover the work with level & quality of works as per
standard & standardization will confirmed by ACI . Vendor must have 5years Experience of similar type of work in ACI/ similar Organization.

For Avah Engineering.

Engr. Azaharul Islam