Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/300021102

Borehole Camera And Extensometers To Study Hanging Wall Stability – Case


Study Using Voussoir beam -Cuiabá Mine

Conference Paper · September 2014


DOI: 10.13140/RG.2.1.5044.0086

CITATIONS READS

0 530

2 authors, including:

Rodrigo Figueiredo
Universidade Federal de Ouro Preto
51 PUBLICATIONS 196 CITATIONS

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

ANÁLISE DAS TENSÕES IN SITU NA MINA CUIABÁ – SABARÁ – MINAS GERAIS - BRASIL View project

Open Pits View project

All content following this page was uploaded by Rodrigo Figueiredo on 08 April 2016.

The user has requested enhancement of the downloaded file.


Rock Mechanics for Natural Resources and Infrastructure
SBMR 2014 – ISRM Specialized Conference 09-13 September, Goiania, Brazil
© CBMR/ABMS and ISRM, 2014

Borehole Camera And Extensometers To Study Hanging Wall


Stability – Case Study Using Voussoir beam - Cuiabá Mine
Reuber Ferreira Cota
Anglogold Ashanti, Sabará, Brazil, rfcota@angolgoldashanti.com.br

Rodrigo Peluci de Figueiredo


Federal University of Ouro Preto, Ouro Preto, Brazil, rpfigueiredo@demin.ufop.br

SUMMARY: Cuiabá mine, owned by Anglogold Ashanti Córrego do Sítio Mineração, is located in
Sabara-MG, with excavations more than 1100m below surface, is one of the most important
underground gold mines in Brazil. In recent years, there have been significant problems of
instability of the hanging wall (HW) in some stopes (production excavation). In order to understand
and anticipate the problems of instability of the hanging wall, a monitoring system was
implemented consisting of televised boreholes, in the walls of the excavation. This was in addition
to the large number of Multiple Point Borehole Extensometers (MPBX) and SMART cables
(Stretch Measurement to Assess Reinforcement Tension) installed in the mine. This paper presents
an example of the identification from monitoring, in the Fonte Grande Sul orebody – level 10.2
stope (about 680m below surface), with evidence of instability in the hanging wall. The observation
of borehole cracks, shears, failures, and displacements, indicated the beginning of instability in the
hanging wall, which allowed measures to be taken to stabilize this area. A detailed follow-up
confirmed the stabilization after actions have been implemented. In order to exploit the data
collected during the process of study and to attempt to validate a simple method for evaluating the
stability of the hanging wall in schist, a stability study was performed using the voussoir arch
theory. Despite the identification of the thickness of the beams formed within the hanging wall, the
geological complexity, evidenced by interbedded rocks with different elastic characteristics and
strength, folds and boudinage, which was beyond the simplification of the calculations, did not
allow a proper assessment of the stability of the studied area using the voussoir arch theory.

KEYWORDS: Underground mine, rock mechanics, borehole camera, extensometers, voussoir


beam.

1 INTRODUCTION with borehole cameras of boreholes with


borehole cameras and extensometers MPBX
Cuiabá mine, owned by Anglogold Ashanti (Multi Point Borehole Extensometer) and
Córrego do Sítio Mineração, located in Sabara- SMART (Stretch Measurement to Assess
MG, with excavations more than 1100m below Reinforcement Tension) cables.
the surface, is one of the most important A case study was conducted in Fonte Grande
underground gold mines in Brazil, with annual Sul (FGS), Level 10.2 stope, located between
production of approximately 9 tons of gold. 700m and 665m below surface, which showed
Following an increase in production in that working with the data collected by
beginning of 2007, problems of instability, extensometers and the filming of boreholes, can
mainly in hanging wall, were identified in be a powerful tool to recognize timely evidence
mining excavations (stopes). A study to of instability of the hanging wall, allowing that
understand and predict these problems was mitigation activities can be implemented to
implemented comprising of constant monitoring stabilize the area.

SBMR 2014
After processing the data related specifically instability.
to filmed boreholes, it was possible to recognize
the thicknesses of the beams formed by the
shear and cracks identified inside the holes in 2 CASE STUDY – 10.2 FONTE GRANDE
schistose rock in the hanging wall, thus, SUL STOPE (FGS)
together with the identification of other
parameters, an assessment was done on the For a better understanding of all the
applicability of the analogy of voussoir arch mechanisms involved in this study, site
theory for the stability assessment of the characterization is presented, covering location,
hanging wall for the study area. geometric characterization of the mining panel
as well as the geological and geotechnical
1.1 Location characteristics.
After describing the study case, the
Cuiabá mine is located close to Sabara city, interpretation of data obtained mainly by the
Minas Gerais state (Figure 1), 35 km from Belo filmed holes, it was possible to define the
Horizonte. thickness of the beam, caused by the separation
of cracks and schistose shears located in the
hanging wall.
With the geomechanical characterization of
the hanging wall, the geometry of the
excavation and knowledge of the thicknesses of
the beams, it was possible to evaluate the
applicability of the method voussoir modified
by Diederichs and Kaiser (1999a), for the study
of stability of schistose hanging wall.

2.1 Case Study Location

Figure 1. Cuiabá mine location. Case study is located in Fonte Grande Sul
(FGS) orebody, level 10.2 between 700 and
1.2 Objectives 665m below surface (Figure 2).

The main objectives of this work are listed as


follows:

• Study the evolution of deterioration in the


stability of the hanging wall during the process
of mining activities;
• Assess the effectiveness of the monitoring
systems used, extensometers and filming of
boreholes, as tools to identify timeously, the Figure 2. Case Study location.
indications of instability in the hanging wall;
• Evaluate the effectiveness of mitigation 2.2 Characterization
activities for the stabilization for area with
evidence of instability; 2.2.1 Stope Geometry
• To study the applicability of the analogy of
voussoir arch theory as a mechanism for the Stope 10.2 FGS has a vertical height of 35m,
stability of the area with indications of strike of 460m, with the predominant dip of the

SBMR 2014
orebody at 30 °. The mining method applied is all of the hanging wall exposures were
cut and fill with backfilling of waste rock and classified in bad rock mass with scores between
hydraulic fill. 1 and 4.

2.2.2 Geological and Geotechnical


Characterization

Fonte Grande Sul orebody is located in the


normal limb of the large tubular fold in Cuiabá
mine. Orebodies located in the normal limb, in
general have the following lithological
sequence, from bottom to top, schistose meta-
basalts and schistose meta-andesite, forming
foot wall; banded iron formation with sulfides,
defining the ore (in the study area the thickness
range between 7 and 8m); a layer of graphite
phylite and sericite schist, both forming the Figure 4. Rock mass map for 10.2 FGS orebody.
hanging wall.
Two major discontinuity families have been Laboratory tests were done to characterize
identified in the area. One family is defined by hanging wall rocks. These results can be
schistosity that is the main structure of the visualized in the table 1.
mine; the other family is defined by
discontinuities with the same direction of Table 1- Laboratory test results for hanging wall rock.
schistosity, but with a 180o difference of plunge Amount
Uniaxial Compressive
Poisson
Elastic
Strength (MPa)
Lithology of Module E
direction (Figure 3). (ν)
samples (GPa)
Minimun Average Maximum

Grafite
9 12 63 149 0,13-0,25 12-51
phylite

Sericite
52 36 66 141 0,15-0,26 39-78
schist

2.2.3 Support Characterization

Plain strand Cablebolting, 9.5m in length and


maximum axial strength of 25t to 27t were used
in the hanging wall on a 1.5x1.5m pattern
(Figure 5). Plates and barrels were installed on
Figure 3. Family of discontinuities (Software DIPS 5.0).
the cables. Approximately 1500 cables are
Geomechanical classification of wall hanging installed on a monthly basis at Cuiabá mine.
was carried out for 10.2 FGS stope using the
Hanging Wall
Rock Mass Rating (RMR) classification Ore
(Bieniawski, 1989) and Q - Rock Tunnelling
Quality Index (Barton et al, 1974.). It can be
noted that there is little variation in the quality
of the rock mass along the wall hanging (See
Figure 4). The average hanging wall RMR was Foot Wall
rated between 60 and 41. Q values for almost
Figure 5. Stope 10.2 FGS with visualization of support.

SBMR 2014
2.3 Visual Scale of Cracks and Shears 8). For stable areas, in general, a typical
displacement is of ± 1.5cm near the HW face
Borehole camera monitoring was started in after blasting. Therefore this high displacement
Cuiabá mine for the identificiation and was a first indication of instability in this area.
classification of cracks and shears. Following
the collection of a large dataset, it was possible
to make a visual scale of cracks and shears
(Figure 6). This scale allow different levels of
cracks and shears.
Borehole camera monitoring of holes in the
hanging wall (HW), with mining evolution,
assisted to identify intense shearing in the
schistose mainly when the holes were more Figure 7. Vertical cross section in 10.2 FGS.
further from stope face.

Figure 6. Visual scale of cracks and shears for holes with


a diameter of 5 cm.

2.4 Monitoring and Actions Evolution

For more adequate understanding of the case


study, it is necessary to know the chronology of
events that occurred, from the identification of
signs of instability to the rehabilitation of the
Figure 8. Displacement graph (A) SMART cable and (B)
area with mitigation actions. The development
MPBX.
of research and interventions are listed as
follow: • 29/01/2008 - Monitoring with borehole
camera allowed the captuirng of images inside
• 15/11/2007 - A SMART cable (9.5m long) and the borehole in the hanging wall. The inspected
an extensometer MPBX (15m long) were hole had a length of 15.5m and it was almost
installed, about 2m far from each other (along perpendicular to the schistosity. Shears of level
the direction of the layer) on the hanging wall. 1 were identified approximately 7.0, 1.1, 0.5
In this moment the vertical height of the mining and 0.05 m, measured from the face of the HW
panel was about 15.5 m. The geometry of the (Figure 9).
stope can be seen in Figure 7. • 07/02/2008 - Another important displacement
• 05/12/2007 - Significant displacement was was recorded by the SMART cable and MPBX
recorded (2.8 to 2.5 cm near the surface of the (about 3cm near the face of the HW - Figure
hanging wall) after the production blast. The 10). There was no activity at this location
behavior of the displacements recorded by the during this period. It indicated, again, that this
SMART cable and MPBX was similar (Figure area was with serious stability problems in the

SBMR 2014
hanging wall (HW). After the identification of the deterioration of
rock mass conditions, cablebolting were
installed plus the installation of plates and
barrels as reinforcement. Hydraulic filling was
also done in this stope.
• 14/03/2008 – Borehole 1 was again filmed.
Progresses in shears were identified when
compared to the previous recording (Figure 12).

Figure 9. Vertical section with cracks and shears inside


hole 1 on 29/01/08.

Figure 12. Vertical section with cracks and shears inside


hole 1 on14/03/08.

• 29/03/2008 – Production blasting was done at


the study area.
• 09/04/2008 - Borehole 1 was again filmed to
evaluate the condition of the HW after blasting.
High level of shearing was identified 7m
(measured from the surface) blocking the hole
(Figure 13). The extensometer MPBX
apparently reached the limit of measurement,
Figure 10. Displacement graph A) SMART cable and B) not detecting further displacement (Figure 14).
MPBX.

• 14/02/2008 – The borehole camera was used


in borehole 1 and level 1 shears were identified
approximately 8.0, 7.5, 7.0, 6.1, 4.5, 4.0, 3.5,
3.0, 2.5, 1.1, 0.8. , 0.75, 0.6 and 0.5 m measured
from the surface of the HW (Figure 11).

Figure 13. Vertical section with cracks and shears inside


hole 1 on 09/04/08.
Figure 11. Vertical section with cracks and shears inside
hole 1 on14/02/08.

SBMR 2014
Extensive mechanical rock scaling was
required to remove broken rock material . A
brow of ± 2.5m was formed in the HW with a
length of ± 10m , along the direction of
schistosity, and 13m along the dip (Figure 16).

Figure 14. MPBX displacement graph with televised hole


information.

Recordings with the borehole camera allowed


the study to gradually evaluate the evolution of
shearing over time. Some images of the
development of shears can be viewed as a
function of time for certain positions within the
rock mass in Figure 15.
Figure 16. Vertical section with cracks and shears and
HW picture with brow after scaler machine working.

A new MPBX was installed and other holes


were drilled for borehole camera monitoring.
The evolution of shear and crack and the
identificiation by means of borehole camera
filming in holes 1, 2, 3, 4, 5 and 6 can be seen
in Figure 17. The quantity and magnitude of
cracks and shears decreased after reinforcement
with cableblolting was done. This is the most
important indicator with respect to the borehole
camera information, indicating the
improvement of the HW geomechanical rock
mass condition.

Figure 15. Shear evolution over time for 1.1 and 7 m into
the HW.

In order to continue monitoring this site more


holes were drilled for monitoring of with the Figure 17. Cracks and shear evolution. In the hole 6 there
borehole camera. Cablebolting were installed on was no cracks or shears.
denser pattern of 1.0 x 1.0 m and 9.6m length.

SBMR 2014
A comparison between the displacements
collected by the 1st MPBX, the phase of
instability of HW, and the 2nd MPBX installed
subsequently after installation of cablebolting
reinforcement can be seen in Figure 18.

Figure 19. Study area after mining activities.

2.5 Voussoir Arch Theory

In order to exploit the data collected during the


process of study and to attempt to validate a
simple method for evaluating the stability of the
hanging wall in schist, a stability study was
performed using the voussoir arch theory.
First of all it was necessary to find the rigid
limit below hydraulic/rockfill floor to be
considered. For trying to solve this problem, 6
displacement graphs from MPBX and SMART
cables were analyzed after they were covered
with hydraulic/rockfill in the same stope; five
extensometers did not identify displacement
after blast number 3 (Figure 20) after being
Figure 18. Displacement graphs (A) MPBX with covered, or 6m along ore dip below the floor.
instability indication and (B) MPBX 2 after reinforcement
Then span considered was normal span plus 6m.
installation.

Through the analysis of Figure 18, we can


identify significant difference in displacement
between the instruments. It is noteworthy that
the measuring time for MPBX 2 is much larger
than for MPBX 1, furthermore the larger
amount of blasting that occurred in the study
area. The MPBX 2 installed after the
application of reinforcement show typical
displacement for areas without signs of
instability.
Figure 20. Displacement graph with blasting and moment
Mining activities has been successfully
of covered extensometer.
completed in the area. This was due to the
identification of signs of instability, the In order to minimize errors related to
installation of reinforcement and constant lithologic recognition in all televising of holes
monitoring using extensometers and borehole in the study area, the interbedded graphite
camera. A current photo of the study area can be phylite was recognized immersed in sericite
seen in Figure 19. /chlorite schist (Figure 21).

SBMR 2014
allowed measurements could be done to
stabilize the site. The success achieved after the
implementation of stabilization measures,
attested by monitoring, demonstrates the
efficiency of extensometers and borehole
camera as important tools to minimize the risk
of fall of ground in the hanging wall.
The analysis performed by calculation using
Figure 21. Graphite phylite immersed in sericite/chlorite the analogy of voussoir indicated a very stable
schist. situation. This result disagrees with the data
obtained by monitoring. The difference between
The thickness of the beam to be used is 2.5 m
the stability analyzes, voussoir and monitoring,
on the graphite phylite which was removed with
may be associated with frequent intercalations
the scaler equipment. Another simulation used a
of rocks with different elastic properties and
beam thickness of 4.7 m because of the
strengths that were identified within the hanging
crack/shear identified in the first and second
wall (Figure 23), beyond the possibility of
hole at the same depth within the hanging wall
improper choice of the beam thicknesses
(Figure 22).
studied.

Figure 21. Beam thickness used.

All parameters used in the voussoir analogy e


results for both simulation can be visualized in
the table 2.
The results do not indicate instability for both
simulation.

Table 2- Parameters used in the voussoir analogy to the


simulation 1 and 2 and the results obtained. Figure 22. Example of graphite phylite intercalation.
Parameter Simulation 1 Simulation 2
Span (m) 25 25
Thickness (m) 2.5 4.7
Rock Mass Elastic Modulus (GPa) 13.3 13.3 REFERENCES
Specific Weight (KN/m 3) 28 28
Bedding angle 30 30 Diederichs, M.S., Kaiser, P.K. (1999a). Stability of Large
UCS (MPa) 63 63
Support pressure (KPa) 87.1 109
Excavations in Laminated Hard Rock Masses: The
Buckling Limit (<35%) 2% 2% Voussoir Analogue Revisited, International Journal of
Crush Safety Factor 369.7 80.8 Rock Mechanics and Mining Sciences, Canada, v. 36, 97-
117p.
Diederichs, M.S., Kaiser, P.K. (1999b). Tensile Strength
and Abutment Relaxation as Failure Control Mechanisms
3 RESULTS in Underground Excavations, International Journal of
Rock Mechanics and Mining Sciences, Canada, v. 36, 69-
The timely detection by the extensometers and 96p.
the images obtained by borehole camera Hutchinson, D.J, Diederichs, M.S. (1996). Cablebolting
in Underground Mines, Bitech Publishers Ltd, British
monitoring in the area with signs of instability, Columbia, Canadá, 406p.

SBMR 2014

View publication stats

You might also like