100 530 GSH 00001 001
100 530 GSH 00001 001
: 26071-100-530-GSH-00001
1 of 17
Doc. No. : 26071-100-530-GSH-00001
REVISION LOG
2 of 17
Doc. No. : 26071-100-530-GSH-00001
HOLD LIST
NO HOLD
3 of 17
Doc. No. : 26071-100-530-GSH-00001
TABLE OF CONTENTS
1. PURPOSE ............................................................................................................................... 5
2. SCOPE .................................................................................................................................... 5
3. DEFINITIONS ........................................................................................................................ 5
4. REFERENCE ........................................................................................................................... 6
6. PROJECT BREAKDOWN....................................................................................................14
6.1 System........................................................................................................................................................ 14
6.2 Sub-system................................................................................................................................................ 14
4 of 17
Doc. No. : 26071-100-530-GSH-00001
1. PURPOSE
The purpose of this procedure is to describe the function of HPCM (Hyundai Pre-
commissioning and Commissioning Management), electronic management system to
manage, store and control data which reflects Pre-commissioning/Commissioning activities
for the Refinery Development Master Plan (RDMP) Project RU V Balikpapan (hereinafter
referred to as PROJECT).
2. SCOPE
This procedure covers the general description and workflow, system breakdown,
classification of completion database, verification of system completion of the HPCM
3. DEFINITIONS
Terms Definition
IPMT personnel.(PMC)
PMC Worley
5 of 17
Doc. No. : 26071-100-530-GSH-00001
4. REFERENCE
6 of 17
Doc. No. : 26071-100-530-GSH-00001
7 of 17
Doc. No. : 26071-100-530-GSH-00001
8 of 17
Doc. No. : 26071-100-530-GSH-00001
9 of 17
Doc. No. : 26071-100-530-GSH-00001
Site Manager
Construction
Supervisor HPCM Operator HCQM Operator
(Each Discipline)
10 of 17
Doc. No. : 26071-100-530-GSH-00001
IPMT
Commissioning
Team
HPCM
Construction QA/QC
Team
HCQM Team
IPMT
11 of 17
Doc. No. : 26071-100-530-GSH-00001
HCQM Administrator
He is responsible to setup and manage the HCQM. He also cordinates with
Construction team and Commissionning team.
HPCM Operator
He is responsible to input data to HCQM and export report. He also handle
the construction and QA/QC dossier.
5.5 Transfer of HCQM data into HPCM
After systemization is done, essential Construction data from HCQM should be linked
with HPCM in order to ensure that relevant system is ready for Pre-commissioning. (Ex.
Hydro test which belongs to construction activities should be done prior to flushing
activities.)
Contractor’s Commissioning team will select essential Construction data and move it
into HPCM. Below picture is sample from other Project showing that construction data
has been transferred into HPCM.
12 of 17
Doc. No. : 26071-100-530-GSH-00001
13 of 17
Doc. No. : 26071-100-530-GSH-00001
6. PROJECT BREAKDOWN
Contractor shall convert schedule monitoring from ‘area base’ to ‘system completion base’
when the construction progress is achieved around sixty percent (60%). The plant will be
controlled by subsystem basis. In order to optimize resources and Pre-commissioning &
Commissioning period, Plant will divided into further subdivision such as system,
subsystem.
6.1 System
A System is a major subdivision of an installation, being either process or utility, which
performs a major operational function of the plant.
6.2 Sub-system
A Sub-system is a further subdivision of a system, which performs a given operational
function, with no or little interference from the other subsystems for the commissioning
execution.
Most of the preparation and execution activities are performed within a subsystem
boundary.
The subsystem list must be compatible with the plant initial start-up sequence.
Equipment which have different steps of the start-up sequence must not belong to the
same subsystem.
Below is System/Sub-system sample for Diesel Hydrotreating Unit (Unit 054/083)
Unit No. Unit Description System No. System Description Subsystem No. Subsystem Description
14 of 17
Doc. No. : 26071-100-530-GSH-00001
Hand over the plant to the OWNER in full confidence with the required safety
15 of 17
Doc. No. : 26071-100-530-GSH-00001
MC
Subsystem B‐01
SMC
Process System B
Subsystem B‐02
Pre‐commissioning
Punch status will be extracted from HCQM and will be transfered to HPCM. SMC and MC
are easily verified by using status monitoring in HPCM. As shown below pictures, Punches
(A, B and C) and Pre-commissioning activities can be managed on subsystem basis in
HPCM.
Sequence Level 3 Sub System Sub System Description Punch Punch A Punch B Punch C
Total 2 2 3
MC2 41-P-01 MC2_Feed Section Cleared 2 1 1
Outstanding 1 2
Total 3 3 2
MC2 41-P-04 MC2_Recycle Gas Compressor Cleared 3 2 1
Outstanding 1 1
Total 2 4 5
MC2 41-P-05 MC2_Make-up Gas Compressor Cleared 2 3 2
Outstanding 1 3
16 of 17
Doc. No. : 26071-100-530-GSH-00001
PRE-COMMISSIONING
Sequence Level 3 Sub System Sub System Description Task CI COMM EL ME
SubTotal Prog(%)
LOOP SCLN LEAK LBOF CMCL SOLO MECK
Total Task 2 2 2 6
MC2 41-P-01 MC2_Feed Section Total Done 2 2 2 6 100
Remaining 0
Total 3 1 1 2 7
MC2 41-P-04 MC2_Recycle Gas Compressor Cleared 3 1 1 5 71.4
Outstanding 2 2
Total 1 2 2 5
MC2 41-P-05 MC2_Make-up Gas Compressor Cleared 1 2 2 5 100
Outstanding 0
Note
‐ Discipline : CI (Instrument), COMM(Commissioning), EL(Electrical), ME(Mechanical)
‐ Task Class : LOOP (Loop Test), SCLN (Flushing & Blowing), LEAK (Leak Test), LBOF ( Lube Oil Flushing)
CMCL (Chemical Cleaning), SOLO (Motor Solo Run), MECK (Vessel Final Box Up)
17 of 17