PROJECT TITLE
Function to test
CO-PS - Country
Functional and technical specification ajuste ZCO_INTEGRACION
Date 16.06.2023
INDEX
Description…………………………………………………………………….1
Test I……………………………………………………………………………1
Step I…………………………………………………………….…….1
Step II……………………………………………………….…………1
Step III…………………………………………………………………1
Step IV…………………………………………………………………1
Step V………………………………………………………………….1
Test II……………………………………………………………………………2
Step I…………………………………………………………………...2
Step II…………………………………………………………………...2
Step III…………………………………………………………………..2
Step IV…………………………………………………………………..2
Step V…………………………………………………………………...2
Conclusion………………………………………………………………………..3
1. Description
#8
Adjustment ZCO_INTEGRACION
2. Test I
Description Run Glow report for creation of orders
Step I
SAP –> Update the internal table ZFI_ORDENES_SOC
Call transaction for update (special authorization) ZCO_UPD_ORDENES_SOC
Table before
Run transaction
Table After
Step II
Environment->GLOW UI14-> transferring data to Q4G
Description Go to main screen Delivery – Projects – Edit orders
Evidence
c. Step IV file
Globant Proprietary | Confidential information
7
3. Conclusion
Comments: On this scenario the report run ok and can create on SAP and GLOW the SAP Order
a. : Test I PASS