Professional Documents
Culture Documents
Section 20 - Geotechnical Works
Section 20 - Geotechnical Works
S20 - i
20.3.5 INSTALLATION.................................................................................................................... S20-12
20.3.5.1 General .......................................................................................................................S20-12
20.3.5.2 Fill Material ...............................................................................................................S20-12
20.3.5.3 Installation of Geogrid for Reinforced Slope..............................................................S20-13
20.3.5.4 Protection of Completed Geogrid Reinforced Slopes from Erosion ...........................S20-13
20.4 PREFABRICATED VERTICAL DRAINS (PVD) ............................................................... S20-13
20.4.1 GENERAL............................................................................................................................ S20-13
20.4.2 MATERIALS ........................................................................................................................ S20-14
20.4.2.1 Prefabricated Vertical Drains ....................................................................................S20-14
20.4.2.2 Geotextile Separator ...................................................................................................S20-15
20.4.2.3 Drainage Blanket ........................................................................................................S20-15
20.4.3 INSTALLATION.................................................................................................................... S20-16
20.4.3.1 Prefabricated Vertical Drain (PVD) ..........................................................................S20-16
20.4.3.2 Geotextile Separator ...................................................................................................S20-18
20.4.3.3 Fill Surcharge .............................................................................................................S20-19
20.4.3.4 Instrumentation ...........................................................................................................S20-19
20.5 SURCHARGE / PRE-LOADING .......................................................................................... S20-20
20.6 STONE COLUMN .................................................................................................................. S20-21
20.6.1 GENERAL............................................................................................................................ S20-21
20.6.1.1 Design Requirements. .................................................................................................S20-21
20.6.2 STANDARDS AND DEFINITIONS ........................................................................................... S20-21
20.6.3 TOLERANCES ...................................................................................................................... S20-21
20.6.3.1 Setting Out ..................................................................................................................S20-21
20.6.3.2 Position .......................................................................................................................S20-21
20.6.4 PERSONNEL ........................................................................................................................ S20-21
20.6.5 DAMAGE TO STONE COLUMN ............................................................................................. S20-21
20.6.6 LOAD TESTS ON PRELIMINARY STONE COLUMNS .............................................................. S20-22
20.6.6.1 Plate Load Test on Preliminary Stone Column ..........................................................S20-22
20.6.6.2 S.O.’s Instruction to Commence Installation of Stone Columns .................................S20-22
20.6.7 DIAMETER AND LENGTH OF THE STONE COLUMNS ............................................................ S20-22
20.6.8 STONE CONSUMPTION ........................................................................................................ S20-22
20.6.9 VIBROFLOT......................................................................................................................... S20-22
20.6.10 OBSTRUCTIONS .............................................................................................................. S20-23
20.6.11 PROCEDURE FOR COMPACTION OF STONE COLUMNS ..................................................... S20-23
20.6.12 MATERIALS .................................................................................................................... S20-24
20.6.12.1 Stones ..........................................................................................................................S20-24
20.6.13 STONE COLUMN RECORDS ............................................................................................. S20-24
20.6.14 DISPOSAL OF ARISING .................................................................................................... S20-25
20.6.15 PLATE LOAD TESTS ON STONE COLUMNS ...................................................................... S20-25
20.6.15.1 General .......................................................................................................................S20-25
20.6.15.2 Safety Precautions Applicable to Plate Load Tests on Stone Columns ......................S20-25
20.6.15.3 Reaction System ..........................................................................................................S20-25
20.6.15.4 Equipment for Loading and Load Measurements .......................................................S20-26
20.6.15.5 Method of Measuring the Movement of the Bearing and the Surrounding
Ground Surface...........................................................................................................S20-26
20.6.15.6 Plate Dimensions ........................................................................................................S20-26
20.6.15.7 Locations ....................................................................................................................S20-26
20.6.15.8 Preparation of Top of Stone Column ..........................................................................S20-26
20.6.15.9 Protection of Testing Equipment and Supervision ......................................................S20-26
20.6.15.10 Test Procedure for Maintained Load Test ..............................................................S20-27
20.6.15.11 Plate Load Test Records .........................................................................................S20-27
20.6.15.12 Records Confidential ..............................................................................................S20-27
20.7 TERRAMESH WALL ............................................................................................................ S20-28
20.7.1 MATERIALS SPECIFICATION ............................................................................................... S20-28
20.7.1.1 Introduction ................................................................................................................S20-28
20.7.1.2 Definitions ..................................................................................................................S20-28
S20 - ii
20.7.1.3 General Description ...................................................................................................S20-28
20.7.1.4 Steel Wire ....................................................................................................................S20-28
20.7.1.5 Wire Mesh ...................................................................................................................S20-31
20.7.1.6 Selvedges ....................................................................................................................S20-31
20.7.1.7 Diaphragms and End Panels ......................................................................................S20-32
20.7.1.8 Lacing And Bracing Wire ...........................................................................................S20-32
20.7.1.9 Unit Sizes ....................................................................................................................S20-32
20.7.1.10 Stone Fill For Facing Box ..........................................................................................S20-32
20.7.1.11 Structural Embankment ..............................................................................................S20-32
20.7.2 ASSEMBLY AND ERECTION SPECIFICATION FOR TERRAMESH SYSTEM UNIT
REINFORCED WALLS .......................................................................................................... S20-33
20.7.2.1 Scope...........................................................................................................................S20-33
20.7.2.2 Preparation .................................................................................................................S20-33
20.7.2.3 Erection ......................................................................................................................S20-33
20.7.2.4 Geotextile ....................................................................................................................S20-34
20.7.2.5 Stretching ....................................................................................................................S20-34
20.7.2.6 Filling .........................................................................................................................S20-34
20.7.2.7 Structural Embankment Material ...............................................................................S20-34
20.7.2.8 Compaction of Backfill ...............................................................................................S20-34
20.8 GABION RETAINING WALL .............................................................................................. S20-35
20.9 REINFORCED SOIL WALL WITH CONCRETE FACING PANELS ............................ S20-35
20.9.1 GENERAL............................................................................................................................ S20-35
20.9.2 DEFINITIONS ....................................................................................................................... S20-35
20.9.3 DIMENSIONS ....................................................................................................................... S20-35
20.9.4 CODES OF PRACTICE AND TECHNICAL MEMORANDUM...................................................... S20-35
20.9.5 MATERIALS ........................................................................................................................ S20-36
20.9.5.1 Reinforcing Elements ..................................................................................................S20-36
20.9.5.2 Facings .......................................................................................................................S20-36
20.9.5.3 Fasteners ....................................................................................................................S20-36
20.9.5.4 Facing Unit Joint Filler Material ...............................................................................S20-37
20.9.5.5 Fill ..............................................................................................................................S20-37
20.9.5.6 Material Compatibility ...............................................................................................S20-37
20.9.6 DESIGN METHODOLOGY AND CRITERIA ............................................................................. S20-37
20.9.6.1 Design of Reinforcing Elements .................................................................................S20-37
20.9.6.2 Design of Facings and Fasteners ...............................................................................S20-38
20.9.7 REINFORCING ELEMENTS ................................................................................................... S20-39
20.9.7.1 Deadman Anchor Walls ..............................................................................................S20-39
20.9.7.2 Reinforced Earth Walls ...............................................................................................S20-40
20.9.8 FRICTIONAL FILL ................................................................................................................ S20-40
20.9.8.1 Selected Fill for Reinforced Soil Retaining Wall ........................................................S20-40
20.9.8.2 Grain Size Distribution ...............................................................................................S20-40
20.9.8.3 Angle of Friction .........................................................................................................S20-40
20.9.8.4 Chemical and Electrical Properties............................................................................S20-41
20.9.9 FIXINGS AND FASTENERS ................................................................................................... S20-41
20.9.9.1 Fasteners for Deadman Anchor and Reinforced Earth Walls ....................................S20-41
20.9.10 FACINGS ......................................................................................................................... S20-43
20.9.11 JOINT FILLERS ................................................................................................................ S20-43
20.9.12 GRANULAR FILL BEHIND REINFORCED SOIL RETAINING WALL ..................................... S20-43
20.9.13 CONSTRUCTION .............................................................................................................. S20-43
20.9.13.1 Fill ..............................................................................................................................S20-43
20.9.13.2 Wall Erection - Concrete Panels ................................................................................S20-44
20.9.13.3 Fabrication and Handling ..........................................................................................S20-44
20.9.13.4 Tolerances ..................................................................................................................S20-45
20.9.14 TESTING OF FILL MATERIAL .......................................................................................... S20-45
20.9.14.1 General .......................................................................................................................S20-45
20.9.14.2 Testing of Fill for Reinforced Soil ..............................................................................S20-45
20.9.14.3 Testing of Chloride Content (Reinforced Earth and Deadman Anchor Walls) ..........S20-46
20.9.14.4 Testing Of Resistivity (Reinforced Earth and Deadman Anchor Walls) .....................S20-46
20.9.14.5 Testing of Redox Potential (Reinforced Earth and Deadman Anchor Walls) .............S20-46
S20 - iii
20.9.15 GALVANIZATION TESTS FOR REINFORCING ELEMENTS (REINFORCED AND
DEADMAN ANCHOR WALLS) .......................................................................................... S20-48
20.9.16 PULL OUT TESTS FOR REINFORCING ELEMENTS ............................................................. S20-48
20.10 RUBBLE MASONRY WALL ................................................................................................ S20-48
20.10.1 DESCRIPTION .................................................................................................................. S20-48
20.10.2 MATERIALS .................................................................................................................... S20-48
20.10.3 CONSTRUCTION METHODS ............................................................................................. S20-48
20.11 HORIZONTAL DRAIN .......................................................................................................... S20-49
20.11.1 GENERAL........................................................................................................................ S20-49
20.11.2 SETTING OUT ................................................................................................................. S20-49
20.11.3 MATERIALS .................................................................................................................... S20-49
20.11.3.1 Polyvinyl Chloride (PVC) Pipes Technical Properties ...............................................S20-49
20.11.3.2 Perforations of PVC Pipe ...........................................................................................S20-49
20.11.3.3 Filter Cloth Technical Properties ...............................................................................S20-49
20.11.4 PRODUCT QUALITY ASSURANCE PVC PIPE AND FILTER CLOTH .................................... S20-50
20.11.5 HANDLING AND STORAGE .............................................................................................. S20-50
20.11.5.1 Product Labelling .......................................................................................................S20-50
20.11.5.2 Product Packaging .....................................................................................................S20-50
20.11.5.3 Storage at Site .............................................................................................................S20-51
20.11.6 INSTALLATION ................................................................................................................ S20-51
20.11.6.1 Drilling .......................................................................................................................S20-51
20.11.6.2 Pipe Installation .........................................................................................................S20-51
20.11.6.3 Horizontal Drain beside Soil Nail/Ground Anchor/Rock Bolt....................................S20-52
20.11.6.4 Concrete Lined Chutes ...............................................................................................S20-52
20.11.7 SUBMITTALS ................................................................................................................... S20-52
20.12 SOIL NAILING ....................................................................................................................... S20-52
20.12.1 SCOPE ............................................................................................................................. S20-52
20.12.2 REFERENCE STANDARD .................................................................................................. S20-52
20.12.3 METHOD OF CONSTRUCTION .......................................................................................... S20-53
20.12.4 MATERIAL CERTIFICATION............................................................................................. S20-53
20.12.5 WORKMANSHIP RESPONSIBILITY.................................................................................... S20-53
20.12.6 REINFORCEMENT ............................................................................................................ S20-53
20.12.7 SLOPE TRIMMING ........................................................................................................... S20-54
20.12.8 TEMPORARY STAGING .................................................................................................... S20-54
20.12.9 DRILLING ....................................................................................................................... S20-54
20.12.10 GROUTING ...................................................................................................................... S20-54
20.12.11 CONSTRUCTION OF GUNITE ............................................................................................ S20-54
20.12.12 CORROSION PROTECTION OF SOIL NAIL HEAD AND STEEL PLATE ................................. S20-54
20.12.13 FITTING OF SOIL NAIL HEAD .......................................................................................... S20-54
20.12.14 SOIL NAIL STRESSING .................................................................................................... S20-54
20.13 GUNITING .............................................................................................................................. S20-55
20.13.1 GENERAL........................................................................................................................ S20-55
20.13.2 MATERIALS .................................................................................................................... S20-55
20.13.3 PROPORTIONING ............................................................................................................. S20-55
20.13.4 EQUIPMENT AND WORKMANSHIP ................................................................................... S20-55
20.13.5 PREPARATION ................................................................................................................. S20-56
20.13.6 APPLICATION .................................................................................................................. S20-56
20.13.7 CURING .......................................................................................................................... S20-57
20.13.8 SAFETY OF WORKS ......................................................................................................... S20-57
20.13.9 TESTING AND REPAIRS ................................................................................................... S20-57
20.14 STONE PITCHING SLOPE .................................................................................................. S20-57
20.14.1 DESCRIPTION .................................................................................................................. S20-57
20.14.2 MATERIALS .................................................................................................................... S20-57
20.14.2.1 Stone ...........................................................................................................................S20-57
20.14.2.2 Cement Mortar ...........................................................................................................S20-57
S20 - iv
20.14.2.3 Draining Material behind Stone Pitching Slope .........................................................S20-58
20.14.3 CONSTRUCTION METHODS ............................................................................................. S20-58
20.15 GEOCELL ............................................................................................................................... S20-58
20.15.1 SCOPE ............................................................................................................................. S20-58
20.15.2 CONTRACTOR TO PROVIDE ............................................................................................. S20-58
20.15.3 SETTING-OUT ................................................................................................................. S20-58
20.15.4 LOCALLY PRODUCED PRODUCTS.................................................................................... S20-59
20.15.5 PACKAGING AND STORAGE ............................................................................................ S20-59
20.15.5.1 Product Labelling .......................................................................................................S20-59
20.15.5.2 Product Packaging .....................................................................................................S20-59
20.15.5.3 Storage at Site .............................................................................................................S20-59
20.15.6 TESTING ......................................................................................................................... S20-59
20.15.6.1 General .......................................................................................................................S20-59
20.15.6.2 Consignment Certificate .............................................................................................S20-59
20.15.7 MATERIAL PROPERTIES .................................................................................................. S20-60
20.15.7.1 Product and Applications ...........................................................................................S20-60
20.15.7.2 Technical Properties ...................................................................................................S20-60
20.15.8 INSTALLATION ................................................................................................................ S20-61
20.15.8.1 General .......................................................................................................................S20-61
20.15.8.2 Installation of Cellular Retention System ...................................................................S20-61
20.15.8.3 Infill Material Placement ............................................................................................S20-61
20.16 ROCK STABILIZATION WORKS ...................................................................................... S20-61
20.16.1 GENERAL........................................................................................................................ S20-61
20.16.2 ACCESS TO ROCK SLOPES............................................................................................... S20-62
20.16.3 REMOVAL OF UNSTABLE ROCK MASS ............................................................................ S20-62
20.16.4 PREPARATION OF ROCK SURFACES ................................................................................ S20-62
20.16.5 SPRAYED CONCRETE ...................................................................................................... S20-62
20.16.6 PROTECTIVE SCREEN/ ROCKFALL NETTING ................................................................... S20-64
20.16.7 PRE-STRESSED ROCK BOLTS ........................................................................................ S20-65
20.16.7.1 General ......................................................................................................................S20-65
20.16.7.2 Materials ................................................................................................................S20-65
20.16.7.3 Construction Requirements.........................................................................................S20-66
20.16.8 ROCK DOWEL (UNTENSIONED ROCK BOLTS) ................................................................. S20-70
20.16.8.1 General .......................................................................................................................S20-70
20.16.8.2 Materials .....................................................................................................................S20-70
20.16.8.3 Construction Requirements.........................................................................................S20-71
20.17 APPENDIX 20A....................................................................................................................... S20-73
S20 - v
SECTION 20 – GEOTECHNICAL WORKS
20.1.2 Determination of Depth for Removing Unsuitable Material with JKR or Mackintosh
Probes
20.1.2.1 Description
The JKR or Mackintosh probes shall be carried out at locations shown in the Drawings or as
indicated by the S.O. and shall consist of driving a standard probe into the ground and
recording the resistance of penetration, to determine depth of unsuitable material.
20.1.2.2 Equipment
The apparatus used shall be the standard JKR probes or the normal Mackintosh probes. Details
of the JKR and Mackintosh probes are shown in Figure 20.1 and Figure 20.2
The probing rig shall consist of a stable frame for driving the extension rods and cone
vertically, with a guide to provide lateral support for the part of the extension rods protruding
above the soil or exposed in water, a means of handling and operating the driving device, and a
means of extracting the rods and cone. The guide shall be such that not more than 1.2 m of rod
is unsupported at any one time, and if the driving device is not separately provided with a
guide then not more than 0.6 m of rod shall be supported where the blow count is in excess of
15 blows per 300 mm.
S20 - 1
Table 20.1: Compares the JKR and Mackintosh Probe
20.1.2.3 Procedures
(a) The probing rig shall be erected so that the deviation from the vertical of the first
extension rod shall not be greater than 2 per cent. Maximum deviation from the vertical
of the extension rods during driving shall be 5 per cent.
(b) The driving shall be as continuous as possible but in no case shall interruptions longer
than 5 minutes be allowed. The hammer shall be raised in such a way as not to carry it
more or less as the defined height above the driving head. The cone shall be driven at a
rate of between 15 to 30 blows per minute, and the number of blows shall be recorded
for each 300 mm increment of penetration.
(c) The probing shall be stopped when the resistance has reached 400 blows/300 mm
penetrations or the depth has reached 15 metres, whichever is reached earlier, unless
otherwise directed by the S.O.
However, in the case of the criteria for the removal of unsuitable material not shown on the
Drawings, the unsuitable material shall be removed to a depth of 40 blows/300 mm probe
resistance OR up to a maximum depth of 3.0m, whichever is the earlier; all subject to the
S.O. approval.
20.2 GEOTEXTILE
20.2.1 General
20.2.1.1 Scope
This specification covers the technical and general requirements for the supply and installation
of geotextile as described herein. All materials used shall meet the requirements of this
specification and all works shall be executed in accordance with the details shown on the
Drawings.
S20 - 2
20.2.1.3 Contractor to Provide
The Contractor shall provide all necessary resources including materials, skilled workers, and
plants/equipment to execute and complete the works related to supply and laying of geotextile
as shown on the Drawings.
20.2.1.4 Setting-Out
The Contractor shall be responsible for the true and proper setting-out of the areas to which the
geotextile is to be placed and for the correctness of the lines, widths, levels and slopes.
The Contractor is solely responsible for the good condition of the geotextile stored at the
worksite and in the event of damages or deteriorations of the geotextile due to improper
storage, he shall be liable to replace the affected materials at his own cost when directed to do
so by the S.O.
S20 - 3
20.2.3 Testing of Geotextile
20.2.3.1 General
Prior to the procurement of materials, the Contractor shall provide a sample and the
Manufacturer's Independent Test Report (ITR), showing full compliance of the proposed
geotextile to all the specified property values corresponding to their respective test methods,
for the approval of the S.O.
All tests shall be carried out in accordance with the codes of practices and standards as
provided within this specification, unless otherwise approved by the S.O. The independent test
report and tests shall be prepared and carried out at reputable institution or laboratory such as
SIRIM, IKRAM, UTM, UKM, UPM, UM or other accredited laboratories approved by the
S.O.
Routine sample testing, when requested and specified, shall be carried out at factory or at an
independent laboratory witnessed by the S.O's representative. The Contractor shall submit test
report showing compliance of the specification by independent testing authority or laboratory
such as listed above or an accredited laboratory approved by the S.O.
(viii) Product composition and information on the raw material used as type of fibre, their
proportions and the type of connection between the elements of the fabric.
Where the individual samples fail to satisfy the requirements of this Specification on the
geotextile, the roll from which the sample is obtained shall be rejected. Two additional samples
shall then be selected from two other rolls of the same batch.
If either of these two additional samples fails to comply with the requirements, the entire batch
represented by the samples shall be rejected.
S20 - 4
(a) the weakness of the sub grade upon which the geotextile is directly placed with respect
to the potential for mud waving during the backfill operation;
(b) the material and labour costs of deploying individual geotextile panels with extra
material required for the overlap versus the material and labour costs of seaming and
installing large, fabricated panels; and
(c) the feasibility of deploying individual geotextile panels in poor access and/or climatic
conditions.
The expected seam strength shall be more than 70% of the original strength of the geotextile.
Samples of such sewn seam assembly shall be tested in accordance with ASTM D4884 as
deemed necessary by the S.O.
(i) Prayer Seam (ii) J Seam (iii) Butterfly Seam - with double thread ‘lock stitch’
S20 - 5
durable and resistant to naturally occurring chemical, fungi and bacteria when installed in
contact with the materials to be separated. Non-woven geotextile shall be free of any flaws that
may have an adverse effect on the physical and mechanical properties of the non-woven
geotextile.
Unless otherwise approved by the S.O, non-woven geotextile shall be needle punched staple
fibre geotextile in accordance with the Specification and shall be used as shown and described
on the Drawings or as directed by the S.O.
Non-woven geotextile shall be stabilized against ultra-violet radiation to the degree that one
month's exposure of the geotextile to sunlight shall not reduce its strength to less than 90% of
the specified strength rating in the specification.
S20 - 6
(v) Effective opening size (095);
(e) Seaming
The seaming of non-woven geotextile has been described above in Clause 20.2.4.2. The
sewing thread used shall be of polyester or polypropylene with a minimum of 3 stitches per
25mm and a breaking load of not less than 200N.
S20 - 7
The width of each roll of woven geotextile shall be 5.40m.
Test
No. Description Unit Limit Properties
Standard
HS HS HS HS HS HS HS
1. Type (or equivalent)
100/50 150/50 200/50 300/50 400/50 600/50 800/50
2. Mechanical Properties
Ultimate Tensile Strength ASTM kN/
a. > 100 150 200 300 400 600 800
– Warp (MD) D4595 m
Elongation at Tensile ASTM
b. % < 10.0
Strength – Warp (MD) D4595
Ultimate Tensile Strength ASTM kN/
c. > 50.0
– Weft (CD) D4595 m
Elongation at Tensile ASTM
d. % < 12.0
Strength – Weft (CD) D4595
Tearing Strength – ASTM 800/ 1200/ 1000/ 2500/ 2500/ 4600/ 4900/
e. N >
MD/CD min D4533 400 400 400 500 700 700 700
ASTM
f. Puncture Strength N > 500 1000 1000 1800 2200 2800 3200
D4833
Creep at 50% of Ultimate ASTM
g. % < 1.0
Load After 2 Years D5262
3. Physical Properties
ASTM
a. Mass Per Unit Area g/m2 > 330 330 430 540 700 100 1300
D5261-92
ASTM
b. Nominal Thickness mm > 0.65 0.75 0.85 1.1 1.6 2.1 3.1
D5199
ASTM
c. Apparent Pore Size (O95) mm < 0.212 0.212 0.15 0.3 0.425 0.425 0.425
D4751
d. Minimum Unsewn Width m 5.0
(b) Earthwork
The surface upon which the woven geotextile is to be laid shall be prepared or excavated/cut
and trimmed to the required level as shown in the contract Drawings.
The surface shall be smooth firm, unyielding and free of large vegetation, protruding sticks,
sharp rocks, void spaces, etc., that can damage the Geotextile during installation.
(d) Seaming
The seaming of woven geotextile has been described above in Clause 20.2.4.2. The sewing
thread used shall be of high tenacity polyester with a minimum of 3 stitches per 25mm and a
breaking load of not less than 200N.
S20 - 8
(e) Damage Repair
If the woven geotextile is damaged (torn, punctured, perforated, etc.) during installation it snail
be repaired by laying an additional layer of woven geotextile extending at least lm beyond the
damaged area, subject to the approval of the S.O.
To ensure the proper tensioning to the woven geotextile during the filling process, backfilling
shall start at the embankment edges forming bunds, which serve to anchor the woven
geotextile. The protruding ends of the woven geotextile shall then be wrapped around these
bunds and further weighed down with more fill materials before the central region of the
embankment is being backfilled.
The backfilling process is a continuous one with filling works on the embankment edges
leading the filling works to the centre of the embankment. At no one time shall the filling
exceed 500mm thick at this stage.
The height of the embankment shall be raised to the required level by not more than 500mm at
a time following the backfilling procedures described above and compacted in
accordance to the Specifications.
20.3 GEOGRID
20.3.1 General
20.3.1.1 Scope
This specification covers the general and technical requirements for the supply and
installation of Geogrid as described herein. All materials used shall meet the
requirements of this specification and all works shall be executed in accordance with the
details as shown on the drawings and the procedures described herein.
20.3.1.3 Setting-Out
The Contractor shall be responsible for the true and proper setting -out of the areas to
which the Geogrid is to be placed and for the correctness of the lines, widths, levels and
slopes.
S20 - 9
20.3.2 Packaging and Storage
20.3.2.1 Product Labelling
The geogrid shall be supplied with the Manufacturer's Label/Logo on each roll showing
the following identifications:-
The Contractor is solely responsible for the good condition of the geogrid stored at the
worksite and in the event of damages or deteriorations of the geogrid due to improper
storage, he shall be liable to replace the affected materials at his own cost when directed
to do so by the S.O.
Information relating to the durability of the geogrid shall be submitted as required by the
S.O. for his approval. The decision of the S.O. on the adequacy of the geogrid against
durability shall be final.
20.3.3 Testing
20.3.3.1 General
Prior to the procurement of materials, the contractor shall provide a sample and the
Manufacturer's Independent Test Report (ITR), showing full compliance of the proposed
geogrid to all the above-specified property values corresponding to their respective test
methods, for the approval of the S.O..
All tests shall be carried out in accordance with the codes of Practices and Standards as
provided within this specification, unless otherwise approved by the S.O. The
S20 - 10
independent test report and tests shall be prepared and carried out at reputable institution
or laboratory such as SIRIM, IKRAM, UTM, UKM, UPM, UM or other accredited
independent laboratories approved by the S.O.
Routine sample testing, when required and specified, shall be carried out at factory or at
independent laboratory witnessed by the S.O.'s representative. The Contractor shall
submit test report showing compliance of the specification by independent testing
authority or laboratory such as listed above or an accredited independent laboratory
approved by the S.O.
Bonding at the cross-over points shall be such that the properties as required by the
Contract are not affected. The strength of the bond shall be such as to ensure the function
of the geogrid;
(b) all free ends shall be sealed to completely prevent ingress of moisture;
The weft elements shall be the same quality material as the warp elements.
S20 - 11
20.3.4.2 Technical Properties
The properties of the Geogrid shall meet or exceed the minimum or maximum values
corresponding to the respectively test methods as shown in Tables 20.5a and 20.5b
below:
Test GD GD GD GD GD
No. Description Unit
Standard 30/30 50/30 55/30 80/30 100/30
Ultimate Warp Tensile ASTM D4595
1. kN/m 30 50 55 55 100
Strength ISO 10319
Ultimate Weft Tensile ASTM D4595
2. kN/m 30 30 30 30 30
Strength ISO 10319
Ultimate Warp & ASTM D4595
3. % 11 11 11 11 11
Weft Elongation ISO 10319
Creep limited strength
4. ASTM D5262 kN/m 18 30 33 48 60
(LTDS) 120 years
Creep at 50% Ultimate
5. ASTM D5262 % 2 2 2 2 2
Load After 2 years
6. Mass per Unit Area ASTM D5261 g/m2 200 250 270 350 415
7. Mesh Size (± 5.0mm) - mm 25 x 25 25 x 25 25 x 25 25 x 25 25 x 25
8. Width (± 0.1m) - m 5 5 5 5 5
9. Length (Standard) - m 50 or 100
Test GD GD GD GD GD GD
No. Description Unit
Standard 120/30 150/30 160/30 200/30 200/50 400/200
Ultimate Warp Tensile ASTM D4595
1. kN/m 120 150 160 200 200 400
Strength ISO 10319
Ultimate Weft Tensile ASTM D4595
2. kN/m 30 30 30 30 50 200
Strength ISO 10319
Ultimate Warp & ASTM D4595
3. % 12 12 12 12 12 12
Weft Elongation ISO 10319
Creep limited strength
4. ASTM D5262 kN/m 72 90 96 120 120 240
(LTDS) 120 years
Creep at 50% Ultimate
5. ASTM D5262 % 2 2 2 2 2 2
Load After 2 years
6. Mass per Unit Area ASTM D5261 g/m2 450 540 570 700 750 1865
7. Mesh Size (± 5.0mm) - mm 25 x 25 25 x 25 25 x 25 25 x 25 25 x 25 25 x 25
8. Width (± 0.1m) - m 5 5 5 5 5 5
9. Length (Standard) - m 50 or 100 50
20.3.5 Installation
20.3.5.1 General
Installation of geogrid shall be carried out by qualified and experienced workers under
the supervision of a qualified engineer. The geogrid shall be installed in compliance to
Manufacturer's instructions utilizing approved plants/equipment.
S20 - 12
When well graded granular and dry cohesive soils are used, the soil immediately behind
the facing shall consist of a 200mm thick layer of topsoil or as shown on the drawings.
Soiling, grassing and hydraulic mulch grass seeding shall be carried out to the
requirements of the Specifications.
During backfill placement, trucks and heavy vehicles shall be kept back at least 2m from
the face of the Geogrid Reinforced Slope.
The deposition, spreading, levelling and compaction of the fill shall be carried out
generally m a direction parallel to the facing and shall be executed in stapes to alternate
with the placing and fixing of the reinforcing elements and the facing.
Care shall be taken to ensure that the reinforcing elements and facing are not damaged or
displaced during deposition, spreading, levelling and compaction of the fill. The program
of filling shall be arranged so that no machines or vehicles r un on the reinforcing
elements.
The fill within 2m of the face of the Geogrid Reinforced Slope shall be compacted using
one of the following:-
(c) Vibrating roller having a mass per metre width of not more than 1300k g and a total
mass of not more than 1000kg
The rear of the Geogrid Reinforcing Slope shall be adequately supported either by
temporary shoring or by phasing the work in order to ensure the contemporaneous
deposition of the retained fill material.
The Contractor shall provide all necessary resources including materials, skilled workers, and
plants/equipment to execute and complete the works related to supply and laying of PVD as
shown on the drawings.
The Contractor shall be responsible for the true and proper setting-out of the areas to which the
PVD is to be placed and for the correctness of the lines, widths and levels.
S20 - 13
20.4.2 Materials
20.4.2.1 Prefabricated Vertical Drains
20.4.2.1.1 General Requirements
Prefabricated vertical drains shall be from an approved manufacturer and consist of a polymer
core enclosed within an external non-woven filter jacket, and shall comply with the
requirements as indicated in the Table 20.6. The PVD shall be fully of Malaysian origin. The
PVD shall be produced by local factory with ISO certification and equipped with testing
laboratory, where sampling and testing can be readily carried out.
The filter jacket shall be capable of resisting all bending, puncturing and tensioning subjected
during installation and design life of the drain.
The core shall be made of continuous plastic material fabricated to facilitate drainage along the
axis of the vertical drain.
The prefabricated vertical drain shall be resistant against rotting, mildew, bacterial action,
insect, salts, acids, alkalis, solvent and other constituents in ground water.
During transportation and storage, the drain shall be wrapped in heavy paper, burlap or similar
heavy duty protection covering. The drain shall be protected from sunlight, mud, dirt, dust,
debris and other detrimental substances during transport and on site storage.
The Contractor shall ensure that the PVD is properly stored in a covered area at the worksite.
If no covered area is available, the PVD may be stored on raised platform and covered with a
waterproof canvas.
The Contractor is solely responsible for the good condition of the PVD stored at the worksite
and in the event of damages or deteriorations of the PVD due to improper storage, he shall be
liable to replace the affected materials at his own cost when directed to do so by the S.O.
All materials which are damaged during transportation, handling or storage and do not meet
the minimum requirements of the vertical drain specifications shall be rejected by the S.O. No
payment of any kind shall be made on the rejected product.
All tests shall be carried out in accordance with the codes of Practices and Standards as
provided within this specification, unless otherwise approved by the S.O. The independent test
report and tests shall be prepared and carried out at reputable institution or laboratory such as
SIRIM, IKRAM, UTM, UKM, UPM, UM or other accredited independent laboratories
approved by the S.O.
Routine sample testing, when requested and specified, shall be carried out at factory or at an
independent laboratory witnessed by the S.O's representative. The Contractor shall submit test
report showing compliance of the specification by independent testing authority or laboratory
such as listed above or an accredited independent laboratory approved by the S.O.
S20 - 14
The actual vertical drain to be used shall be tested at the option of the contractor subject to the
approval of the S.O.
The Contractor shall indicate the proposed source of the materials prior to delivery to site. The
contractor shall also submit samples and Manufacturer's certificates to verify the physical,
mechanical and hydraulic properties of the drain to be used for S.O.'s approval.
Prior to installation and at the discretion of the S.O, individual test sample shall be cut from at
least one roll selected at random to represent each batch or every 100,000 metres, whichever is
lesser. Individual sample shall be no less than 3 metres in length and shall be full width.
Samples submitted for tests shall indicate the linear metres of drain and manufacturer's
identifications represented by the sample.
The sand drainage material for depositing in water shall be deposited without the associated
use of compaction plant.
The sand drainage layer shall be built up evenly in horizontal layers each of not more than
300mm thick. Filling shall commence from the lowest level, and each layer shall cover the full
area of the intended total fill area at that level before deposition of the subsequent layer
commences.
S20 - 15
20.4.3 Installation
20.4.3.1 Prefabricated Vertical Drain (PVD)
20.4.3.1.1 Equipment
Prefabricated Vertical Drain (PVD) shall be installed with approved modern equipment of a
type which will cause a minimum of disturbance of the sub-soil during the installation
operation and maintain the mandrel in a vertical position.
PVD shall be installed using a mandrel or sleeve and shall be inserted (i.e. pushed or vibrated)
into the soil. The mandrel or sleeve shall protect the drain material from tears, cuts, and
abrasion during installation, and shall be retracted after each drain is installed.
The size and shape of the mandrel or sleeve shall be as close as possible to the size and shape
of the drains in order to minimize disturbance to the soil. The length of the mandrel shall be
not less than the maximum length of the drain. The mandrel shall be capable of making a clean
puncture through any geotextile if necessary.
The mandrel or sleeve shall be provided with an anchor plate or similar arrangement at the
bottom to prevent the soil from entering the bottom of the mandrel during the installation of
the drain and to anchor the drain tip at the required depth at the time of mandrel withdrawal.
The dimension of the anchor shall conform as closely as possible to the dimensions of the
mandrel so as to minimize soil disturbance. The Engineer shall determine the acceptability of
the anchorage system and procedure.
20.4.3.1.2 Approval
4 weeks prior to the beginning of trial of PVD installation, the Contractor shall submit full
details of the materials, equipment, sequence and method proposed for PVD installation to the
Engineer for review and approval. Approval by the Engineer of installation sequence and
methods shall not relieve the Contractor of his responsibility to install drains in accordance
with the plans and specifications.
Prior to the installation of PVD, the Contractor shall demonstrate that the equipment, method,
and materials produce a satisfactory installation in accordance with these specifications. For
this purpose, the Contractor will be required to install 2 trial drains totalling approximately 16
linear metres at locations designated by the S.O.
Approval by the S.O. of the method or equipment used to install the trial drains shall not
constitute, necessarily, acceptance of the method for the remainder of the project. If, at any
lime, the S.O. considers that the method of installation does not produce satisfactory PVD, the
Contractor shall alter his method and/or equipment as necessary to comply with these
specifications.
PVD that are more than 150mm from design plan location or are damaged or improperly
install, it will be rejected and abandoned in place.
PVD shall be installed from the working surface to the depth shown on the drawings, or to
such depth as directed by the S.O. who may vary the depths, spacing, or the number of drains
to be installed, and may revise the plan limits for this work as necessary.
S20 - 16
During PVD installation, the Contractor shall provide the S.O. with suitable means of
determining the depth of the advancing drain at any given time and the length of drain installed
at each location.
The Contractor shall supply to the S.O. at the end of each working day a summary of the PVD
installed that day. The summary shall include drain type, locations and length (to nearest
50mm) of PVD installed at each location.
Equipment for installing PVD shall be plumbed prior to installing each drain and shall not
deviate from the vertical more than 1 in 50 during installing of any drain.
PVD shall be installed using a continuous push using static weight or vibration to the specified
depth approved by the S.O.
Installation techniques using driving will not be permitted. Jetting techniques will be permitted
only after receiving written approval from the S.O.
The installation shall be performed, without any damage to the drain during advancement or
retraction of the mandrel. In no case will alternate raising or lowering of the mandrel during
advancement be permitted. Raising of the mandrel will only be permitted after completion of
an installation.
The mandrel penetration rate should be between 150mm and 600mm per second.
The completed PVD shall be cut off neatly 300mm above the working grade, or as otherwise
specified on the contract drawings.
The Contractor shall observe precautions necessary for protection of any field instrumentation
devices.
The Contractor shall replace, at his own expense, any instrumentation equipment that has been
damaged or become unreliable as a result of his operations prior to continuing with drain
installation or other construction activities.
20.4.3.1.4 Pre-augering/Obstructions
The Contractor shall be responsible for penetrating any overlying material as necessary to
install the drains.
Where obstructions are encountered below the working surface which cannot be penetrated by
the installation equipment, the Contractor shall complete the drain from the elevation of the
working surface to the obstruction and notify the S.O. prior to installing any more drains.
At the direction of the S.O. and under his review, the Contractor shall attempt to install a new
drain within 600mm horizontally from the obstructed drain. A maximum of two attempts shall
be made as directed by the S.O. If the drain still cannot be installed to the design tip elevation,
the drain location shall be abandoned and the installation equipment shall be moved to the next
location, or other action shall be taken as directed by the S.O.
The Contractor shall be responsible for penetrating overlying fill material as necessary to
satisfactorily install the PVD. Satisfactory installation may require clearing obstructions
defined as any man-made or natural object or strata that prevent the proper insertion of the
mandrel and installation of the PVD.
The Contractor may use augering, spudding, or other approved methods to loosen the soil and
any obstruction material prior to the installation of PVD. The obstruction clearance procedure
is subjected to the approval of the S.O.; however, such, approval shall not relieve the
Contractor of his responsibility to clear obstructions in accordance with the specification.
If augering is the selected method, the augers shall have a minimum outside diameter equal to
the largest horizontal dimension of the mandrel, shoe or anchor, whichever is greater.
S20 - 17
20.4.3.1.5 Splicing
Splicing of PV drain material shall be done by stapling in a workmanlike manner and so as to
ensure structural and hydraulic continuity of the drain. At the splice, lower portion of the
jacket shall be external to the upper portion.
A maximum of 1 splice per drain installed will be permitted without specific permission from
the S.O.
The jacket and core shall be overlapped a minimum of 150 mm at any splice.
Prior to the laying of the geotextile fabric, site clearance shall be carried out in accordance
with the Specification and Drawing or as directed by the S.O. All voids shall be filled with
suitable material and the area cleared of large stones and exposed tree root systems or other
such like protrusions.
Geotextile fabric shall be installed to the shape and requirements as specified herein or as
shown and described on the Drawings. The geotextile shall be unrolled smoothly on the
prepared ground as approved by the S.O. and generally in a direction perpendicular to the edge
of the platform, embankment or area of fill as approved by the S.O. Adjacent geotextile rolls
shall be overlapped and sewn in accordance with this Specification. On curves and corners
geotextile may be folded or cut to conform to the direction as approved by the S.O. Adjacent
geotextile rolls shall be overlapped and sewn in accordance with this Specification. On curves
and corners geotextile may be folded or cut or conform to the direction as approved by the
S.O. Overlapping of geotextiles without sewn connections shall only be allowed by the S.O.
Geotextile fabrics shall be placed just in advance of placement of the specified overlying fill
material. Geotextiles so placed shall be covered by the relevant fill within 7 days of being
placed. Installation proposals and trials as deemed required shall be carried out for approval by
the S.O. prior to the acceptance of the placement method for the main works. The installation
trials shall include the placement operations of the overlying fill materials, including
excavation of such materials thereafter for examination of the geotextile fabric installation and
fill materials placement method with respect to the prevailing ground conditions and
constraints.
The geotextile fabric shall be joined using an approved portable industrial sewing machine and
by sewing a double chain stitch with 'J' or 'prayer' seam (minimum lap of 50mm) with high
tenacity polyester thread and a minimum of 3 stitches per 25mm shall be required. The thread
shall have a breaking lead of not less than 160N.
The specified overlying fill material on the geotextile fabric shall be placed in accordance with
the requirements shown and described in the Drawings or as directed by the S.O. These fill
materials shall be deposited in layers not exceeding 300mm loose depth and shall be spread
simultaneously with the dumping in a manner to prevent any localized distress or failure of the
ground.
In water logged or swampy areas, the geotextiles shall be sunk after jointing by ballasting with
sufficient sandbags. To control the location of the mattress, buoys shall be fixed with ropes on
the edges of the geotextile. As soon as possible after positioning, the mattress shall be
ballasted.
S20 - 18
No traffic shall travel directly on the geotextile and there shall be no sudden stops, starts or
turns on the fill materials by the construction equipment or other such actions which may
cause damage to the geotextile.
Extra fill shall be placed to thickness specified in the Drawings as surcharge to speed up rate of
embankment settlement.
Surcharging fill shall be maintained for a period of time indicated in the Drawing and shall be
removed only with the approval of or when instructed by the S.O.
The fill be capable of being compacted to the requirements as indicated on the drawing and
shall not comprise of:-
(d) clay of liquid limit exceeding 80% and/or plasticity index exceeding 55%
20.4.3.4 Instrumentation
20.4.3.4.1 General
The Contractor shall install instruments to enable measurements (monitoring) of vertical
movements and pore water pressure and carry out measurements (monitoring) of the
movements and water pressures and water levels during the currency of the works.
The depths and locations of all instruments shall be determined by the S.O. on site.
The Contractor shall be responsible for and shall follow the instructions of the manufacturer in
the installation, calibration and testing of all measuring instruments and equipment, which shall
be carried out under the direct supervision of the S.O. The Contractor shall inform the S.O. at
least 2 days prior to undertaking installation of the equipment or taking measurements. The
Contractor shall make due allowances in his construction programme for delays which may
arise on account of the installation of the instruments and their maintenance.
The Contractor shall take all necessary measures to protect settlement gauges from damage by
the plant and vehicles and shall repair any such damage to the satisfaction of the S.O. at his
own expense. He shall erect substantial and readily visible barriers at a distance of 750mm
around each gauge;
S20 - 19
The Contractor shall replace any damaged settlement gauges within five days; at his own
expense should any settlement gauge be damaged in such a way as to make it useless for its
purpose.
20.4.3.4.5 Installation
The method of installation shall be the most advantageous method recommended by the
manufacturer and shall be subjected to the approval of the S.O.
The Contractor shall install settlement gauges and reference settlement stations before
commencement of earthworks.
(a) Construction the embankment to the surcharge levels and to the extent as shown on the
Drawings or as directed by the S.O.
(b) Permit the embankment to undergo settlement over the rest period given in the
Drawings or as directed by the S.O.
The date of commencement of the rest period in any one shall be the date at which the
Contractor completes the embankment to the prescribed surcharge level in that area.
Material used for constructing the embankment up to the specified surcharge level shall
comply with the requirements of Clause 2.2.1(e) "Suitable Material". Forming the
embankment shall comply with Clause 2.2.4 "Earth Embankment".
S20 - 20
On completion of the surcharge period the Contractor shall excavate the remainder surcharge
to the final formation level for subgrade preparation.
If the CBR of the material for the top 300mm of subgrade does not comply with the
requirements of Paragraph 1 of Clause 2.2.7, the material to a depth of 300mm below the
formation level shall be removed and replaced with compacted suitable material complying
with the requirements of Clause 2.2.7.
If the CBR of material for the top 300mm of the subgrade complies with the requirements of
Paragraph 1 of Clause 2.2.7, the top 300mm shall be sacrificed and compacted to 95% the
maximum dry density (MDD) as determined in the B.S 1377 Compaction Test (4.5kg rammer)
under 4 days soaked conditions all in accordance with the requirements of Clause 2.2.7.
20.6.3 Tolerances
20.6.3.1 Setting Out
Setting out shall be carried out by the Contractor from reference lines and points shown on the
Drawings. Immediately before installation of the Stone Column, the Stone Column positions
shall be marked with suitable identifiable pins or markers.
20.6.3.2 Position
The maximum permitted deviation of the stone column centre from the centre point shown on
the setting out drawings shall be 75mm in any direction.
20.6.4 Personnel
The Contractor shall employ only personnel experienced in the construction of Stone Columns
for this part of the Works.
S20 - 21
20.6.6 Load Tests on Preliminary Stone Columns
20.6.6.1 Plate Load Test on Preliminary Stone Column
Before installation of the stone columns as a whole commences, the Contractor will be directed
to install one or more preliminary stone columns at positions to be determined by the S.O. He
shall install these stone columns as soon as practicable to the depth as required. Loading of a
stone column shall not commence until seven (7) days have elapsed after completion of its
installation.
20.6.9 Vibroflot
The vibroflot (poker vibrator) shall be sufficiently powerful to ensure:
The vibroflot shall be equipped with automatic systems for continuous record of power output
and depth of penetration.
S20 - 22
20.6.10 Obstructions
In the event of obstructions preventing the penetration of the vibroflot lot the Contractor shall
inform the S.O. for his instructions.
Power consumption shall form a basis for determining the adequacy of compaction of stone
columns.
The minimum power consumption at each level shall not be less than that approved by the S.O.
from the preliminary stone column installation. The Contractor shall install additional stone
columns at his own cost in the event that the required power consumption has not been
achieved throughout the length of the stone columns.
(a) Unless otherwise specified, penetration of the vibroflot to the required depth shall be
with air and/or vibrations. On reaching the required depth, the vibroflot shall be lifted
and lowered at least once over the full depth from commencement level to the required
depth;
(i) Compaction with the vibroflot kept at that depth for not less than 3 minutes
while stones are fed in. Any arching of the stones between the vibroflot and the
sides of the hole shall be overcome by raising and lowering of the vibroflot over
a distance of approximately 0.5m;
(ii) Without further input of stone, the vibroflot lot shall be raised in steps of not
more than 25cm over a time interval of not less than l min/step or over such time
intervals as may be necessary to achieve the required power consumption
determined by the S.O. from installation of the preliminary stone column;
(iii) Input of stones shall be resumed and the procedures given in sub- clauses (a) and
(b) above shall be repeated.
(c) At a depth of approximately 1.0m below the final level, compaction shall be carried out
by repeated vertical movements of the vibroflot lot until the -required power
consumption determined by the S.O. from installation of the preliminary stone column
is achieved;
(d) Where shown on the Drawings, "Bottom-Feed Vibrators" shall be used where stones are
fed into that depth at which compaction is being carried out by means of gravel supply
tube with air pressure to prevent ingress of water or soil into the gravel supply tube.
Penetration of the vibrator shall be by jacking with air flushing.
S20 - 23
20.6.12 Materials
20.6.12.1 Stones
Stones used for forming stone columns shall consist of hard, durable inert material with
particle size distribution falling within the grading envelope given in Table 20.8. The stones
shall also be free of unsuitable material defined in the relevant clauses of the Earthworks
Specifications. When the stones are subjected to five (5) cycles of the sodium sulphate
soundness test (ASTM C88- 76, "Soundness of Aggregates by use of sodium sulphate or
magnesium sulphate" 1976) the weighted average loss shall not exceed 10 per cent.
% Passing by Weight
BS 410 Test Sieve (mm)
Nominal Size of Singled-sized stone – 37.5mm
75.0 -
63.0 100
37.5 85 - 100
20.0 0 - 20
14.0 -
10.0 0-5
5.0 -
2.36 -
Prior to the commencement of the Works, the Contractor shall submit for approval samples of
the stone backfill aggregate from each proposed source of supply.
Throughout the period of the Works, when directed by the S.O., the Contractor shall be
required to substantiate that the output from the approved sources of stone consistently
conforms to the requirements of the Specifications and any conditions stipulated during the
initial approval.
On completion of the stone columns, the Contractor shall deliver to the S.O. a drawing
recording the final depths of all Stone Columns relative to Ordinance of Datum.
S20 - 24
20.6.14 Disposal of Arising
The Contractor shall ensure that the arising from the stone column installation cause minimum
contamination of the working surface. The Contractor shall remove the arising.
Surface depressions and/or contamination shall be made good by the Contractor with the
specified material before he commence the Works over the treated area.
The Contractor shall construct the foundation for the kentledge and any crib-work, beams or
other supporting structure in such a manner that there shall not be differential settlement,
bending or deflection of an amount that constitutes a safety hazard or impairs the efficiency of
the operation. The kentledge shall be adequately bonded, tied, or otherwise held together to
prevent it falling apart, or becoming unstable through deflection of the supports. The weight of
kentledge shall be greater than the maximum test load and if the weight is estimated from the
density and volume of the constituent materials, an adequate factor of safety against error shall
be allowed. The maximum test load or test pressure as read on the gauge in use shall be
displayed and all operators shall be made aware of this limit.
In all cases the Contractor shall ensure that when the hydraulic jack and load measuring device
are mounted on the bearing plate the whole system will be stable up to the maximum load to be
applied.
The hydraulic jack, pump, hoses, pipes, couplings and other apparatus to be operated under
hydraulic pressure shall be capable of withstanding a test pressure of 1.5 times the maximum
working pressure without leakage.
S20 - 25
20.6.15.4 Equipment for Loading and Load Measurements
(a) Equipment for Applying Load
The equipment used for applying load shall consist of a hydraulic ram or jack having a
capacity at least equal to the required maximum load, and a hand or power driven pump
with a pressure gauge included in the hydraulic system. The ram shall be placed on the
bearing plate so as to transfer an axial load to the bearing plate. The complete system
shall be capable of transferring the maximum load required for the purpose of the tests.
The load from the reaction system shall be transferred axially to the hydraulic ram or
jack.
20.6.15.5 Method of Measuring the Movement of the Bearing and the Surrounding Ground
Surface
In the plate load tests on stone columns, movements of the bearing plate and the surrounding
ground surface shall be measured by at least four (4) dial gauges mounted directly onto the
bearing plate and four (4) dial gauges disposed outside the plate and on the ground surface at a
distance from the centre of the plate equal to 1.5 times the width of the plate.
The dial gauges shall be capable of measuring settlement to an accuracy of 0.05mm and must
be supported by a reference frame independent of the kentledge.
Levels shall be taken of the reference frame against external datum at the end of each load
increment to check movement of the reference frame.
20.6.15.7 Locations
The bearing plate shall be located directly over the stone columns.
Throughout the test period all load or settlement measuring equipment shall be
S20 - 26
protected from the weather.
Construction equipment and persons who are not involved in the testing process shall be
kept at a sufficient distance from the test site to avoid disturbance of the measurement
apparatus.
The S.O. shall be given not less than 24 hours‟ notice of intention to commence the test.
(d) Records
During the progress of the test, the testing equipment and all records of the test shall be
available as required for inspection by the S.O or his representative.
(e) Supervision
The Contractor shall provide an experienced Supervisor to be present full time during
the duration of the tests to ensure that the loading sequence and method of taking
settlement readings are strictly followed and that the true load is maintained at all times.
Tests shall be carried out only in the presence of the S.O. or his representative.
A minimum period of 2 hours shall intervene between the applications of each increment
except that no increment is added until a settlement of less than 0.lmm is observed for 20
minutes under the previously applied increment.
At a load level to be specified by the S.O., the applied load shall remain on the bearing plate
for a minimum period of 24 hours and time-settlement readings taken in regular intervals as for
the load increments.
Unloading shall be carried out in four (4) equal stages and time-settlement readings taken. At
least sixty (60) minutes intervals shall be allowed between the unloading decrements.
One unload-reload cycle shall be carried out at each load level to be specified by the S.O.
S20 - 27
20.7 TERRAMESH WALL
20.7.1 Materials Specification
20.7.1.1 Introduction
The specification below applies to Terramesh units and to the materials from which these are
manufactured.
For simplicity the word “Terramesh” is used. This may be changed for or have the words
“Terramesh System” added singularly or in combination as appropriate. Unless specifically
stated otherwise.
20.7.1.2 Definitions
Terramesh is defined as PVC coated heavily galvanized steel wire mesh box-shaped basket
with a section of the mesh extending into the soil to act as soil reinforcement into the backfill
soil. The basket is filled on site with clean-hard stones.
The selvedges of the Terramesh are the thicker perimeter and edge wires to which the wire
mesh is securely tied to withstand sudden or gradual stress from any direction.
The diaphragms are the internal wire mesh partitions which divide the Terramesh box into
approximately equal sized cells.
Lacing and bracing wire is the wire used to assemble and join the Terramesh units.
Connecting wires are the internal wires used to prevent the Terramesh from bulging during
filling.
All material supplied must be accompanied by a manufacturing certificate from the factory for
quality control and quality management purposes. The supplier and material shall comply with
the following criteria in order to supply the material:-
(a) Factory shall have certification ISO 9001/2 for quality control and management.
(b) Past experience in supplying material for wall more than 9m height.
(c) Shall comply with BBA certificate for expectancy life of material up to 120 years.
(d) The front face box and the soil reinforcement tail shall be made from one continues
mesh panel.
(e) The mesh twists are oriented vertically on the gabion face and perpendicular to the front
face in the reinforcement panel.
S20 - 28
(b) Wire Diameter
Wire diameters and relevant tolerances shall be in accordance with the following table:
The adhesion of the zinc coating to the wire shall be such that when the wire is wrapped six
times around a four wire diameter size mandrel it shall not flake or crack to such an extent that
any zinc can be removed.
The coating shall be 0.50mm average thickness with a tolerance of ± 0.05mm, and nowhere
shall be less than 0.40mm thickness.
S20 - 29
(v) Elongation
Shall not be less than 200% and not greater than 280% in accordance with ASTM D
412-92.
Testing for deterioration shall be as described below. Variation of the initial characteristics
may be allowed, as specified hereunder, when the specimen is submitted to the following tests:
(iv) Brittleness temperature: cold bend less than -30°C test method BS2782-104A; cold flex
less than +15°C in accordance with BS2782-151A(84).
After the above tests have been performed, the PVC coating shall exhibit the following
properties:
(i) Appearance
The vinyl coating shall not crack, blister or split and shall not show any marked change
in colour.
(v) Elongation
Shall not show change higher than 25% of its initial value.
S20 - 30
20.7.1.5 Wire Mesh
Wire mesh shall be mechanically pre-fabricated to become a uniform hexagonal woven mesh
wherein the joints are formed by twisting each pair of wires through three half-turns
(commonly known as double twist), in such a manner that unraveling is prevented.
The tightness of the twisted joints shall be such that a force of not less than 1.7 kN is required
when pulling on one wire to separate it from the other wire, provided each wire is prevented
from turning under the applied forces, and the wire is all in the same plane.
The mesh tensile strength, in soil, is to be equal to or greater than 47 kN/m. All wire used in
Terramesh units shall be PVC coated.
Mesh X ( mm ) Y ( mm ) Tolerance %
8 82 122 +5%
20.7.1.6 Selvedges
The cut edges of all mesh used in the construction of Terramesh System, except the bottom
edges of diaphragms and the end of the soil reinforcing tail shall be tightly selvedged with a
wire having a diameter of at least 3.40 mm.
S20 - 31
The side selvedge of all and any mesh panels shall be woven integrally with the main mesh as
described in the above clause 1.5 with a selvedge wire of at least 3.40 mm in diameter.
Where the selvedge is not woven integrally with the mesh but has to be fastened to the cut
ends of the mesh, it must be attached by mechanically binding the cut ends of the mesh two
and half turns around the selvedge wire or by other approved method, provided that the force
of not less than 8.5 kN applied in the same plane as the mesh, at a point on the selvedge of a
mesh sample one metre long, is required to separate it from the mesh.
The rear and side panels of the box gabion section of the Terramesh unit shall be formed by a
continuous panel connected to the main panel, along the bottom of the rear panel, either by a
spiral wire through the mesh openings or by being mechanically placed with four connecting
rings.
The lacing and bracing wire shall be made from Heavily Galvanized Wire, coated with PVC
and have a core diameter of 2.20 mm.
All Terramesh dimensions shall be within a tolerance limit of 5% of the required size.
No rock shall exceed 250mm and at least 85% by weight of the stone shall have a size equal to
or larger than 100mm. No rock shall pass through the mesh.
Ideally, the backfill shall be granular, free draining and have the following specification,
unless otherwise approved by the S.O:
S20 - 32
(a) not more than 15% by mass of total material to be finer than 75 micron sieve opening
(b) at least 90% by mass of total material to be finer than the 100 mm sieve opening
Cohesive frictional fill as described in the Specification of Highway Works – Classes 7C and
7D, is permitted provided it is in accordance with the design and internal drainage system is
included.
The soil should not exhibit any deterioration in these characteristics with time.
20.7.2 Assembly and Erection Specification for Terramesh System Unit Reinforced Walls
20.7.2.1 Scope
This part of the specification details the requirements from the assembly stage through to the
final wiring of the completed Terramesh® units.
The contractor shall provide to the S.O, for his approval, full details and specifications of the
Terramesh he proposes to use in this contract. Only those products so approved by the S.O
shall be allowed to be incorporated in the works.
20.7.2.2 Preparation
The site shall be surveyed, cleared, trimmed level and the ground compacted accordingly.
Prior to assembly, the Terramesh units shall be opened out flat on the ground and stretched to
remove all kinks and bends.
The Terramesh units shall be assembled individually by raising the front panel (with lid), the
hinged rear panel, and the two ends vertical ensuring that all creases are in the correct position
and that tops of all four sides are even. The diaphragm panel should be located in a vertical
plane centrally within the facing box.
The four corner edges of the facing box shall be laced first followed by the edges of the
internal diaphragm to the sides.
In all cases, lacing shall commence by twisting the end of the lacing wire tightly around the
selvedge/s. It shall then pass round the two edges being joined using alternate single and
double loops at 100mm intervals and be securely tied off at the bottom. The ends of all lacing
wires shall be turned to the inside of the box on completion of each lacing operation. Each
loop shall be pulled tight to prevent the joint opening during filling.
20.7.2.3 Erection
Only assembled boxes, or groups of boxes, shall be positioned in the structure. The side, or
end, from which work is to proceed, shall be secured either to the completed work, or by rods
or stakes driven into the ground at the corner. These stakes must be secure and be high enough
to reach at least to the top of the gabion box.
Further gabion boxes shall be positioned in the structure as required, each being securely laced
to the preceding one along all common corners and diaphragms using the lacing technique
described above.
S20 - 33
20.7.2.4 Geotextile
Non-woven geotextile, as specified in the contract Drawings and approved by the S.O, shall be
placed vertically at the back of each gabion box section of the Terramesh units, and extend
backwards into the fill at least 0.5m parallel to the mesh of homogenous lower panel and also
0.5m below the panel directly above the unit, to prevent migration of fines.
20.7.2.5 Stretching
Final stretching of the gabion boxes shall be carried out using a pull-lift of at least one tonne
capacity, firmly secured to the free end of the assembled gabion boxes.
Whilst under tension, the gabion box section of the Terramesh units shall be securely laced
along all edges (top, bottom and sides) and at diaphragm points, to all adjacent boxes.
20.7.2.6 Filling
Filling shall be carried out whilst gabion boxes are under tension.
The front face and all other faces which will be exposed in the completed structure shall be
“hand packed” with the stones placed so as to produce a neat face free from excessive bulges,
depressions and voids.
Internal bracing wires shall be provided on the exposed faces at the rate of 4/cu.m at 330mm
centres to prevent distortion of the units during filling and in the completed structure. These
bracing wires shall be wrapped around two of the mesh wires and extend from front to back.
Additional bracing wires shall be provided on exposed ends at a rate of 4/sq.m of face.
Mechanical filling equipment may be used with the approval of the S.O, providing adequate
precautions are taken to protect the PVC coating from abrasion during filling operations.
Tension on the gabion boxes shall be released only when fully laced and sufficiently full to
prevent the mesh from slackening.
All gabions shall be overfilled by 25mm using flat stone to allow for minor settlement and to
provide a level surface for subsequent layers.
The select backfill shall be compacted in lifts not exceeding 250-300 mm to 90% of maximum
density as determined by Test 12 of BS1377, unless otherwise specified on the Drawings or
specified by the S.O.
Care shall be taken to ensure heavy compaction equipment does not come into contact with the
mesh panels or within 1.0 m of the front face. Tracked construction equipment shall not be
operated directly upon the mesh reinforcement. A minimum fill thickness of 150mm is
required prior to operation of tracked vehicles over the mesh.
During construction, the surface of fill should be kept horizontal. A slight sloping surface
shall be maintained to facilitate drainage of surface water run-off.
Compaction adjacent to the front edge should be done using hand operated rollers or plate
compactors.
S20 - 34
20.8 GABION RETAINING WALL
- Specification for Gabion Retaining Wall, please refer to Section 3: Drainage - Clause 3.6.
The external stability of the reinforced soil retaining wall has been catered for.
The Contractor shall provide the type of facing specified in the Drawings and design the
reinforcing elements, the facings, fasteners and connections between adjacent facing units, and
between the facings and the reinforcing elements, and joint fillers all in accordance with the
requirements of the Specifications and in conformity with the lines, levels and details given in
the Drawings or as amended by the S.O.
In this Specification various required attributes, properties, design methods, materials and other
parameters are defined for the three systems defined below. Should the Contractor propose a
different system to those defined he must submit full details of the design methods, materials
specifications, construction methods and all other matters relevant to the system together with
copies of all applicable Codes of Practice, Design Manuals, Specifications and other relevant
documents at the time of tendering.
20.9.2 Definitions
"Reinforced Soil" means any part of the Permanent Works comprising a mass of bulky
material of fragmented form having tensile reinforcing elements embedded in the mass so that
the elements interact with the material to stabilise it and includes any facing which may be
necessary for such part of the Permanent Works.
"Deadman Anchor Wall" means a reinforced soil comprising the mass of fill which is
reinforced with galvanized steel bars tied to multiple deadman anchor blocks at the rear and
connected to concrete facings by means of some mechanical connection. The name Deadman
Anchor Wall is not a registered trademarks.
"Reinforced Earth Wall" means a reinforced soil comprising the mass of fill which is
reinforced with tensile elements which is galvanised metal strip which is attached to concrete
facing by means of some mechanical connection. The name itself is a registered trademark.
A `Wall' of reinforced soil comprises the mass of fill which is reinforced with tensile elements
and the facing which is attached to the elements.
20.9.3 Dimensions
The lengths, heights and widths of the Reinforced Soil Retaining Wall shall be as shown in the
Drawings.
S20 - 35
(iii) BS8006: British Standard 8006: Code of Practice for Strengthened/Reinforced Soilsand
Other Fills;
(iv) AS 1204 : Australian Standard 1204 : Structural steels ordinary weldable grades -
Metric Unit;
(vi) "Reinforced Earth Retaining Walls and Bridge Abutments of Embankments" Technical
Memorandum (Bridges) BE 3/78. Department of Transport, United Kingdom;
(vii) "Reinforced Earth Structures Recommendations - Rules of the Art" French Ministry of
Transport, August 1980 hereinafter referred to in its abbreviated form RESRRA. FMOT
(1980);
(viii) "Design and Construction Guidelines. Reinforced Soil Structures. U.S. Dept. of
Transportation. Federal Highway Administration". (Hereinafter referred to in its
abbreviated form as U.S. Dept. TFHA).
The recommendations of the Codes and memorandum shall be followed in so far as they are
applicable to the design and construction of the wall and its foundation. However, should there
be any discrepancies between the abovementioned Codes of Practice and this Specification,
then the latter shall take precedence.
All British or other Standards and Codes of Practice, etc. shall be deemed to be the editions
current at the time of Tender. Current editions may have the same numbering system as
previous editions or renumbered. Should the Contractor wish to propose compliance with
Standards or Codes of Practice different from those stipulated in the Specification then such
alternative standards of Codes of Practice shall only be considered by the S.O. if in the opinion
of the S.O. they are equivalent or superior to the Standards or Codes of Practice stipulated in
the Specification.
20.9.5 Materials
The following are criteria to be adopted with respect to materials in the Contractor's design of
components.
Reinforcing elements shall be galvanised steel bars individually attached to deadman anchor
blocks.
20.9.5.2 Facings
The facings shall consist of precast rigid concrete panels not less than 150mm thick.
20.9.5.3 Fasteners
(a) Deadman Anchor Walls and Reinforced Earth Walls
Fasteners for connections between adjacent facing units and between the facing and the
reinforcing elements shall take the form of dowels, rods, hexagon head screws or bolts of
galvanized steel alloys.
S20 - 36
20.9.5.4 Facing Unit Joint Filler Material
Fillers shall be durable, resistant to the effects of air pollution, insulation and water which may
be contaminated.
Bedding material shall consist of durable gasket material such as resin bonded cork strip. The
selection of the bedding material will depend upon the structural behaviour of the facing
assumed in the design of the wall.
Sealing material for filling joints other than bedding joints may consist of either polyethylene
foam or polyurethane foam strip.
20.9.5.5 Fill
Fill in the wall shall be wholly granular fill as specified in Clause 20.6.8.2
The Contractor shall design the reinforcing elements in accordance with the requirements of
the Specifications.
In the event that the S.O. alters the lengths of reinforcement and/or configurations of the
slopes, the Contractor shall redesign the reinforcing elements in accordance with the
requirements of the Specifications. The tendered rates shall allow for any change in quantities
as a result of redesign.
The lengths given are the minimum required for the design of the reinforcing elements. The
Contractor shall verify that the lengths given are satisfactory for the sound performance of his
wall system, and shall design for increased stresses and lengths if necessary.
(i) The lateral active soil pressure acting on the facing element shall be computed from the
vertical pressure assuming a Ko condition (Ko = 1-Sin);
(ii) The tension force in the tendon shall be computed from the active soil pressure in (i)
above acting over the tributary surface area of the facing for the tendon;
(iii) The deadman shall be located at a horizontal distance of not less than H/5 beyond the
Rankine failure plane inclined at (p/4 + f/2) to the horizontal emanating from the toes,
where H is the length of the wall as defined on the Drawings;
(iv) Pull out capacity of the deadman shall be estimated assuming the cohesion to be absent.
The friction angle shall correspond to the material over which the failure planes shall
develop. The Factor of Safety against pull out capacity shall be not less than 2.0.
S20 - 37
(d) Particular Requirements for Reinforced Earth Walls
The vertical spacing of the strips shall not be more than 750mm.
The Local Equilibrium Method described in Section 2.4.2 of the RESRRA.FMOT (1980) shall
be used in the design.
The design shall satisfy the requirements of Section 2.4.4.2.1 of the RESRRA.FMOT (1980).
For ribbed reinforcing strips (Highly Adherent (H.A.) reinforcements) the soil-reinforcement
friction coefficient (referred to as f* in RESRRA.FMOT (1980)) shall be as described in
Section 2.3.3.1 of RESRRA.FMOT (1980) with the exception that the coefficient fo* shall not
exceed 1.5;
For smooth reinforcing strips, the soil-reinforcement friction coefficient (f*) shall be equal to
0.40 as given in Section 2.3.3.2 of RESRRA.FMOT (1980).
(a) Facing
Loads for which the facing shall be designed shall be as follows:
(i) The horizontal soil pressures and the corresponding reinforcing element tensile
reactions;
(iii) Vertical shear forces derived from relative movement between the facing and the fill
and possible additional tensile reactions in the elements;
Facings shall consist of rigid panels, each of area not exceeding 2.5 sq.m. and which are able
to move vertically relative to one another either by overlapping or by compressing a filler
placed in the horizontal joints between the units.
(b) Connections between Facing And The Reinforcing Elements for Deadman Anchor
and Reinforced Earth Walls
(i) Connections shall be designed to transfer the forces described in 20.8.6.2.1 and may be
either rigid or sliding. The latter type of connection may include the use of dowels, rods
or guide rods with tee-shaped bolts or strips. No bolt, screw, dowel or rod shall be less
than 12mm nominal diameter;
(ii) Stresses. Calculated values of stresses in bolts, screws, dowels and rods shall be based
on the cross sectional area derived from the nominal diameter of the component except
that the axial tensile stress in a bolt or a screw, and the shear stress in a screw shall be
based on the cross sectional area derived from the root diameter of the thread;
a. Bolts and screws shall be so proportioned that the sum of calculated axial and
shear stresses to their respective permissible values does not exceed 1.4;
b. For combined bending, axial and shear stresses the design shall comply with the
requirements of BS 5950 Clause 14 except Clause 14d and Table 1. In no case
shall the equivalent stress exceed 0.7 times the yield or 0.2% proof stress of the
material.
S20 - 38
(iv) Holes for fasteners in metallic sheet and strip :-
a. Diameter
The design shall be based on the holes diameter being 2mm greater than the
nominal diameter of the fastener;
b. Pitch
The distance between centres of holes shall be not less than 2.5 times the
nominal diameter of the fastener;
c. Edge Distance
The distance from the centre of the hole to the edge of the sheet or strip shall be
not less than 1.5 times the nominal diameter of the fastener. Where edges are
sheared or hand flame cut the edge distance shall be increased by 5mm.
No bolt, screw, dowel or rod shall be less than 12mm nominal diameter.
S20 - 39
20.9.7.2 Reinforced Earth Walls
(a) Galvanized Carbon Steel Strips
Steel reinforcement and tie strips shall comply generally with AS 1204 and shall be either:
(i) Plain flats cut from continuously hot dipped galvanised sheet of minimum yield stress
300 MPa; OR
(ii) Plain or ribbed flats in accordance with the composition and property requirements of
AS 1204 Grade 250.
Reinforcement shall be cut to length and holed in the specified locations. Reinforcement shall
be inspected to ensure that it is free from defects that may impair its strength or durability.
The non-structural sacrificial thickness to be allowed for on each surface exposed to corrosion
shall be 0.75mm.
(a) It shall not contain chalk, unburnt colliery shale, pulverised fuel ash or unsuitable
material as defined in Section 2: Earthworks;
(b) The coefficient of uniformity shall be not less than 5 unless otherwise agreed by the
S.O.;
(c) The chemical and electrical properties of the fill shall be suitable for the reinforcing
elements. The requirements are given in Section 20.9.8.4;
Grading Limits
B.S. Sieve Size Percentage by Mass Passing
125 mm 100
90 mm 85 – 100
10 mm 25 – 100
600 microns 10 - 65
63 microns 0 - 10
S20 - 40
(b) Fill for Reinforced Earth Walls
(i) For ribbed reinforcing strip (Highly Adherent Reinforcement (H.A.)), the angle of
internal friction of a saturated specimen of the fill measured under conditions of rapid
shearing must be equal to or greater than 250;
(ii) For smooth reinforcing strip, the angle of friction earth/reinforcing strip measured under
the same conditions must be equal to or greater than 220;
(c) Sulphides
Where the origin of the material raises the possibilities of the presence of sulphides, the
concentration of the sulphide shall be checked and shall not exceed 300 mg/kg for structure
outside water and 100 mg/kg for structures in soft water.
The resistivity of the material shall be greater than the following limits:
S20 - 41
(b) Black hexagon bolts, screws and nuts shall comply with BS 4190 and shall be hot dip
galvanized in accordance with the requirements of BS 729. The strength grade
designation of bolts and screws shall be not less than 4.6 and of nuts not less than 4.0;
(c) Plain washers shall be of either Form A or Form E to BS 4320 and shall be made of
cold rolled carbon steel strip CS4 complying with BS 1449:Part 1 hot dip galvanized in
accordance with BS 729;
(d) Dowels and rods shall be made from one of the following :-
(i) Steel bar complying with BS 4449 hot dip galvanized in accordance with the
requirements of BS 729;
(ii) Steel of grade 50B complying with BS 4360 hot dip galvanized in accordance
with the requirements of BS 729;
(iii) Stainless steel complying with BS 970: Part 4 except that the 0.2% proof stress
of the bolt shall be not less than 450 N/mm2 and the tensile stress shall be not
less than 700 N/mm2.
Permissible stresses for bolts and screws up to 40mm stock size are given in Table 20.16.
Those for dowels and rods are given in Table 20.17.
Carbon Steel
(galvanized) BS 4360: 355 195 215 117 367
Grade 50B
S20 - 42
20.9.10 Facings
The concrete shall have a 28 days characteristic cube strength (fcu) of 30 MPa and cement
content of not less than 350 kg/m3 using Normal Portland Cement. Admixtures shall not be
used without the approval of the S.O.
Tie strips, connecting dowels, PVC tubes and lifting ferrules shall be cast in place to
dimensions which shall have been submitted by the Contractor to, and approved by the S.O.
Panels shall be cast on a flat area using the standard moulds properly assembled to form a
grout tight face at the joints. Concrete shall be placed and compacted to eliminate voids or
blemishes. Units shall be cured for a minimum of 28 days.
(b) the difference between the lengths of the diagonals shall not exceed 10 mm
Vertical Joint fillers shall consist of polyurethane foam or polyethylene foam strips.
20.9.13 Construction
20.9.13.1 Fill
Fill shall follow closely behind the wall facing erection. At each level of reinforcement,
backfill shall be roughly levelled before placing and/or bolting reinforcement elements. The
maximum thickness of each fill layer depending on reinforcement spacing shall be 0.3m or
lesser amount as required to meet the compacted density as specified below notwithstanding
the requirements of the Specifications for compaction (Earthwork Section of the
Specification).
The top 500mm of backfill of finished embankments shall be compacted to a density of not
less than 95% of the maximum dry density, as determined by the BS1377 Compaction Test
(4.5kg rammer method), over the full width of the embankment. Layers below this shall be
compacted to a density of not less than 90% of the maximum dry density.
During backfill placement trucks and heavy vehicles shall be kept back at least 2m from the
face of the wall.
S20 - 43
The deposition, spreading, levelling and compaction of the fill shall be carried out generally in
a direction parallel to the facing and shall be executed in stages to alternate with the placing
and fixing of the reinforcing elements and the facing.
Care shall be taken to ensure that the reinforcing elements and facing are not damaged or
displaced during deposition, spreading, levelling and compaction of the fill. The programme
of filling shall be arranged so that no machines or vehicles run on the reinforcing elements.
The fill within 2m of the face of the wall and anchor blocks shall be compacted using one of
the following:
(a) Vibro-tamper;
(c) Vibrating roller having a mass per metre width of not more than 1,300kg and a total
mass of not more than 1,000kg.
Prior to the commencement of compaction the Contractor shall submit for the approval of the
S.O. the compaction plant proposed for use. The Contractor shall determine by site visits and
laboratory testing the density/moisture relationship of the material and the optimum field
moisture content to give the maximum dry density for the proposed compaction method.
The methods of compaction determined from the site trials giving results which satisfy the
Contract will be accepted by the S.O. and the Contractor shall follow the same methods for the
rest of the compaction works. The Contractor may not depart from the accepted method unless
further trials are carried out.
The rear of the wall shall be adequately supported either by temporary shoring or by phasing
the work in order to ensure that the facing of the reinforced soil and the granular fill behind the
wall can be raised together.
(b) Stored flat and clearly marked to identify items having different lengths and cross
sectional dimensions;
The reinforcing elements shall be placed on compacted fill and looped between an outer fixing
bar and the panel connection. Reinforcing elements shall be pulled taut before commencement
of deposition and compaction of the subsequent layer of fill. All cut ends of the reinforcing
elements shall be sealed with approved sealant.
S20 - 44
20.9.13.4 Tolerances
The general tolerances applied to the finished wall shall be as follows:
(a) Local variations measured by a 4.5m straight edge shall not exceed 25 mm for
reinforced soil retaining wall
Method of test for fill material shall comply with the requirements for testing soils in BS 1377.
(ii) Three samples shall be tested, each sample occupying the full depth of the shear
box and shall be compacted to (92% ± 2%) of the maximum dry density which
shall be determined in accordance with BS 1377 Compaction Test (4.5 kg
rammer method).
(iii) The normal stress shall be equal to the maximum vertical pressure in the fill,
obtained from the design calculations, and shall be applied to the sample which
shall be sheared within one hour of compaction. The rate of shearing shall be not
greater than l.2 mm/minute.
(iv) The peak shear stress, corresponding with a particular normal stress, shall be
obtained from the measurement of the maximum shear value.
(v) The residual shear stress, corresponding to a particular normal stress shall be
obtained from the measurement of the residual shear value.
(vi) The tangent of the effective angle of internal friction of a sample is given by the
ratio of the peak shear stress to the corresponding normal stress. The average of
the three angles so obtained from the three samples shall be reported as the peak
effective angle of internal friction of the fill.
(vii) The tangent of the residual effective angle of internal friction of a sample is
given by the ratio of the residual shear stress (at Constant Volume Condition) to
the corresponding normal stress. The average of the three angles so obtained
from the three samples shall be reported as the residual angle of internal friction
of the fill. Shear stress and normal stress shall be plotted on the vertical and
normal stress shall be plotted on the vertical and horizontal axis respectively.
(b) Procedure for testing the coefficient of friction between the fill and strip reinforcing
elements shall be as for Clause 24.14.2 (a) above except that:
(i) Reinforcing element material shall be cut to fit the interior
plan shape of the shear box. It shall be fixed so that the top face of the material is
flush with the top edge of the lower half of the box and aligned, so that shearing
occurs in a direction parallel to the longitudinal axis of a reinforcing element.
The fill sample shall occupy the top half of the box.
S20 - 45
(ii) For each sample, the ratio of the peak shear stress and the residual shear stress to
the corresponding normal stress shall be recorded. The mean of the six ratios so
obtained from the three samples shall be reported as the peak coefficient of
friction and the residual coefficient of friction between the till and the
reinforcing elements respectively.
20.9.14.3 Testing of Chloride Content (Reinforced Earth and Deadman Anchor Walls)
Testing of chloride content of the fill shall be carried out in accordance with the requirements
of Clauses 2722 or Specification for Road and Bridge Works, Department of Transport UK,
1976 for fine aggregate except that each test sample referred to in sub-clause 6 of that
Specification shall consist of approximately 1000g of the dry sample.
(a) The row of electrodes shall be orientated in a different direction at each location within
the area of the proposed excavation;
(b) The spacing of adjacent electrodes in each row shall be not less than 1.5m and this
spacing shall be increased by increments of approximately 2m, for successive tests. The
maximum spacing shall be equal to the depth to which material is to be excavated;
(c) The fill resistivity for a particular rest shall be obtained from the expression:
f = 200 x a R
20.9.14.5 Testing of Redox Potential (Reinforced Earth and Deadman Anchor Walls)
(a) The redox potential of fill shall be determined at the site of the cutting or of the
proposed borrow pit or the stockpiles by measuring the potential of a platinum electrode
with respect to a saturated calomel reference electrode.
(b) Apparatus
(i) One platinum probe of an approved robust design having two separate platinum
electrodes embedded in the nose-piece;
S20 - 46
(iii) One pH/millivoltmeter complete with circuit wiring;
(iv) Three plastic bottles, wide mouthed, screw topped, 500 ml capacity, one
containing 70% alcohol, two containing distilled water;
(v) One rubber stopper having a hole to suit the platinum probe and of outside
diameter to fit the plastic bottles above;
(vii) Saturated solution of potassium chloride in screw topped plastic bottle of 500 ml
capacity;
(ix) One plastic bottle, wide mouthed, 250ml fitted rubber stopper having a hole to
suit the reference probe.
(c) Storage
The calomel reference probe shall be cleaned, filled with a saturated solution of
potassium chloride and stored so that the porous plug is immersed in distilled water.
(e) Method
For each test:
(i) Excavate a hole, not less than 1m square in plan, down to the required depth;
(ii) A sample shall be taken from the base of the excavation for determining pH
value of the fill;
(iii) The probes shall be located 300 mm apart and pushed into contact with the fill at
the base of the excavation;
(iv) The electrical circuit shall be completed, connecting one of the electrodes of the
platinum probe and the reference probe to the position and negative terminals of
the millivoltmeter respectively. If no reading can be obtained the leads shall be
reversed; the subsequent readings being treated as negative values;
(v) Each platinum electrode shall be included in the circuit separately; readings
being recorded immediately after the platinum probe have been rotated through
one revolution under firm hand pressure. The two electrode readings shall be
discarded when they differ by more than 10mV and the electrodes shall be
cleaned;
(f) The mean of two acceptable readings shall be obtained from the expression:
E = Ep + 250 + 60 (pH - 7)
S20 - 47
20.9.15 Galvanization Tests for Reinforcing Elements (Reinforced and Deadman Anchor Walls)
Galvanization tests to be carried out in accordance to BS 729 Part 1:1971 includes the
following:
(a) Stripping Test to determine the weight of coating given in Appendix A, BS 729.
The coating weight shall comply with the minimum values quoted in Table 1, BS 728.
(b) Copper Sulphate (Preece) Dip Test for the uniformity of coating given in Appendix B,
BS 729.
The coating shall withstand four one-minute dips in the standard copper sulphate
solution without the formation of an adherent red spot of metallic copper upon the base
metal.
The Contractor shall measure accurately the applied tensile loads and the corresponding
deflection of the strip.
The Contractor shall submit test details for the approval of the S.O.
20.10.2 Materials
Stone for rubble masonry shall consist of field stone or rough uneven quarry stone. The stone
shall be dense, resistant to the action of air and water and suitable in all other respects for the
purpose intended.
The stones shall, in general, have their largest faces parallel. The maximum thickness of the
stone shall in no case exceed the thickness of the wall or portion of the structure into which it
is being built. The median size of the stone shall be not less than 200 mm, unless otherwise
indicated in the Drawings.
Mortar shall be composed of one part of cement and two parts of sand by dry loose volume and
sufficient water to make mortar that can be easily handled and trowelled. Re-tempering of
mortar that has been mixed for period of 30 minutes or longer shall not be permitted.
Stone located at external faces of walls shall be all of similar sizes with the average dimension
of the exposed face of each stone not less than 200 mm for mortared stone masonry retaining
walls. All points on the external faces of walls shall be in their designated positions within a
S20 - 48
tolerance of minus 0 plus 150 mm measured outside the limits of the walls. Exposed stone
faces shall be free of surplus mortar with all mortared joints neatly finish.
At the time of positioning and mortaring, all stones shall be cleaned of all soil or material
which would otherwise reduce the bond between the stone faces and the mortar. Mortared
stone walls shall be constructed in vertical lifts of approximately uniform thickness across the
width of the wall. A blanket of mortar shall be placed in stages over each lift so that when
stones in the succeeding lift are placed, all gaps between the lifts are completely filled with
mortar. As stones are placed, or on completion of each lift, mortar shall be worked into place in
the gaps between adjacent stones so that at least 75 per cent of the volume of each void formed
between adjacent stone is filled with mortar.
20.11.3 Materials
20.11.3.1 Polyvinyl Chloride (PVC) Pipes Technical Properties
The horizontal drain shall be of Polyvinyl Chloride (PVC) pipe of in accordance with the
specification of MS 628: Part 1, 2 and 3. Classification of PVC pipe shall meet or exceed the
minimum values specified in the Drawings.
The slotted perimeter of the pipe shall be positioned at the top to allow inflow of underground
water into the pipe and the uncut section of the pipe shall be laid at the bottom to drain the
water out from the hole.
S20 - 49
(b) Physical Property Requirement – The physical properties in term of mass per unit area
shall comply or exceed the minimum values specified in the Drawings.
(c) Filtration Requirement – Equivalent opening size of the filter cloth shall be two or three
times greater than the D85 size of the surrounding soil or as specified in the Drawings.
(d) Permeability Requirement – The permeability of the filter cloth shall be greater than ten
times the permeability of the soil to be drained or as specified in the Drawings.
Consignment Certificate – For the purpose of ascertaining that each consignment of PVC pipe
and filter cloth supplied to site is of the approved type and quality from the same manufacturer
and batch as indicated, the contractor must furnish with every consignment, an original
consignment certificate from the manufacturer giving the following information:
S20 - 50
20.11.5.3 Storage at Site
The contractor shall ensure that the PVC pipe and filter cloth is properly stored in a covered
area at the worksite. If no covered area is available, the PVC pipe and filter cloth may be
stored on raised platform and covered with a waterproof canvas.
The contractor is solely responsible for the good condition of the PVC pipe and filter cloth
stored at the worksite and in the event of damages or deteriorations of the PVC pipe and filter
cloth due to improper storage, he shall be liable to replace the affected materials at his own
cost when directed to do so by the S.O.
20.11.6 Installation
The location of the drains shall not vary by more than 6 inches (152.4mm) from the locations
indicated on the Drawings or as directed by the S.O.
Drains that are out of their proper location by more than 6 inches (152.4mm) or drains that are
damages in construction, or drains that are improperly completed shall be rejected by the S.O,
and no compensation will be allowed for any materials furnished or for any work performed
on such drains.
The contractor shall provide the S.O. with suitable means of making a linear determination of
the quantity of drain material used.
20.11.6.1 Drilling
The contractor shall deploy suitable drilling equipment plus skilled operator and supervisor
that have adequate capacity and experience to produce the drill hole according to the size,
length and accuracy as shown in the Drawings and as specified in this specification.
The position of each horizontal drain shall be marked and pegged clearly on the ground/slope
before the commencement of drilling works. If necessary, survey equipment shall be used to
locate the position of horizontal drains.
The temporary drilling platform shall be erected firmly on the ground/slope, such that no
excessive movements or sway occurs during drilling. The drain holes shall be drilled at an
inclined angle into the ground/slope. The minimum angle of inclination shall be at least 2.5
degrees upwards.
Dry rotary drill, auger or down-the-hole hammer shall be used. Suitable drill bit slightly larger
that PVC pipe shall also be used. In ground likely to collapse, the drilled shaft shall be
protected by suitable temporary casing. Drill holes shall be flushed clean on completion of
drilling and the opening protected or sealed to prevent the entry of any foreign matter.
Drilling for the whole design length of horizontal drain shall be carried out uninterrupted and
completed with necessary hole cleansing within one hour. To ensure effective cleansing of the
drill holes, an additional drilled length of about 0.3m to the design length shall be provided so
that cleansing of cutting and debris towards the bottom of the drill holes by the compressed air
through the drill rods can be effectively and eventually carried out. All drill rods shall be
properly jointed without leakage.
S20 - 51
20.11.6.3 Horizontal Drain beside Soil Nail/Ground Anchor/Rock Bolt
In the area where horizontal drains are to be installed together with soil nail/ground
anchor/rock bolts, the installation of soil nail/ground anchors/rock bolts shall be completed
first before the commencement of horizontal drains.
20.11.7 Submittals
The contractor shall keep records for each horizontal drain installation and shall submit one
signed copy to the S.O. not later that noon of the next working day after the horizontal drains
have been installed. The record for each horizontal drain shall include horizontal drain
reference number, date/time of manufacturer and completion of drilling and inserting of pipe,
names of supervisor and operators, plus the necessary drilling details. Drilling records shall
include:-
This specification is intended to be a step by step sequential ordering of all the operations
entailed in the manufacture, drilling, installation, grouting and stressing of the soil nail and
construction of gunite.
S20 - 52
BS 4483 BRC mesh and reinforcing fabric
(d) Method of working acceptance test and suitability test of slope reinforcement e.g. soil
nails
Agreement by the S.O. with the proposed method of construction shall not relieve the
Contractor's obligation under the Contract.
The Contractor shall provide test certificates for the steel members and grout material relevant
to the construction and slope stabilization.
All procedures necessary to safeguard the works and workmen, except for any emergency
measures that may have to be taken by the Contractor to ensure safety, shall be subject to prior
approval to the S.O., but such approval shall not relieve the Contractor of any of his
responsibilities.
This specification is intended to be a step by step sequential ordering of all the operations
entailed in the manufacture, installation, grouting and stressing of the soil nail.
20.12.6 Reinforcement
The effective reinforcement for a soil nail comprises of one number yield steel bar produced by
local mill conforming the relevant standard. All outer bars are to be cleaned and free from
rust. Steel bars shall come in full length of 12.0 m. Centralizers shall be provided at specified
interval. When splicing of steel bar is required, it shall be in general accordance to the S.O.'s
Specification. When welding is required, only low hydrogen welding electrode shall be used
conforming to E7018.
Full length of reinforcement complete with centralizers shall be inserted into the drill hole
immediately after drill hole is flushed clean. The protruding end of the re-bar shall be threaded
to receive the bearing plate assembly and in specified length.
S20 - 53
20.12.7 Slope Trimming
Localized uneven slope profile shall be trimmed with "cangkul" where necessary. To prevent
excessive disturbance to the existing slope, large-scale slope trimming is prohibited.
20.12.9 Drilling
100 mm diameter nominal (or as shown on the Drawings) of drill holes are to be drilled at the
correct locations with rotary augering machine to the required design length. Drilling shall be
of dry method rotary. Temporary steel casing is to be used when necessary where the drill hole
is likely to collapse. Rotary percussion drilling shall be used when boulder is encountered.
Drill holes are to be flushed as clean as possible during drilling with air.
20.12.10 Grouting
Grouting shall be carried out without unnecessary delay. The grout is to be mixed for
approximately two minutes in a high speed mixer and then pumped into the drill hole by tremie
method though either a PVC or steel pipe inserted into the bottom of the drill hole until it is
full.
Grouting is to be continued until neat cement grout flows out from the drill hole. The pumping
of grout shall be continued while the tremie pipe is withdrawn to prevent formation of cavities
in the grout. If temporary casing is used, the casing shall be removed by either jacking or
rotating immediately after grouting is completed. During and after removal of casing, the
grout column is to be topped up where necessary. Unless otherwise specified, the grout mix
shall consist of w/c ratio of 0.5 by weight. The characteristic strength of the grout at 28 days
shall be 25 N/sq. mm.
S20 - 54
20.13 GUNITING
20.13.1 General
(a) The Contractor as instructed shall carry out guniting of specified thick including
provision of materials, dowels, reinforcing fabric or BRC and concrete spacer on the
slope surface as shown in the Drawings.
20.13.2 Materials
(a) The cement for gunite shall conform to the requirements of BS 12. All aggregates shall
be cleaned, hard, strong, durable and free from clay, organic or other impurities.
(b) The fine aggregate for gunite shall be cleaned, natural, sharp fresh-water river sand free
from clay and any other impurities and well graded from 5mm sieve down to No. 100
BS sieve.
(c) The coarse aggregate for gunite shall comply with BS 882, 1201 and 1193-1200.
(d) Reinforcing fabric or BRC mesh shall be hard-drawn steel wire reinforcing fabric with a
wire diameter of 4.0mm and pitch of 200mm in each direction complying with the
requirements of BS 4483:1983.
(e) Admixtures as approved by the S.O. shall be added in accordance with manufacturer‟s
recommendation.
(f) Dowels of length and size specified in the Drawings shall be of deformed high yield
steel complying with BS 4449 requirements.
20.13.3 Proportioning
(a) The gunite shall have a minimum cement content of 330 kgs. per cubic meter as
discharged from the nozzle, a minimum water-cement ratio of 0.4 by mass, and shall
have a minimum compressive strength of 30 MPa at 28 days when tested by means of
100mm diameter cores taken from in-place gunite or from test panels. The cores shall
be prepared and tested for compressive strength in accordance to BS 1881, Part
120:1983.
(b) The relative proportions of fine aggregate, coarse aggregate, cement and the moisture
content of the ingredient when mixed shall be proposed by Contractor and to submit for
approval by the S.O. The fine and coarse aggregates shall be thoroughly mixed in an
approved mixer and fed with the cement at the correct rate to achieve the required
proportions and shall enter the gunite machine in such a way as to achieve proper
mixing.
(c) Mixed dry aggregates and cement which are not placed within 30 minutes after mixing
shall be discarded. Payment will not be made for such discarded materials.
S20 - 55
(b) The Contractor shall prepare test panel in the presence of the S.O. for each mix
proportion to be used. The test panels shall be made by applying at least 150mm in
thickness of gunite to a hardboard panel approximately 800mm square. The gunite shall
be applied to the panels in the same manner, using material including reinforcing fabrics
where applicable, equipment and pressures that will be used in the works and shall be
cured in accordance with Section 9: Concrete. The panels shall be submitted to the S.O.
for examination and for test in sufficient time to obtain and test the cores.
(c) No gunite shall be applied to the works until the quality of workmanship and the
compressive strength of the gunite as determined from the test panels meets the
specified requirements.
(d) The Contractor shall employ only skilled nozzlemen and before being permitted to
perform any production application of gunite, each nozzleman shall demonstrate to the
S.O. his ability to apply gunite to the required standard, including the required water-
cement ratio.
(e) Air and water shall be provided in sufficient volume and under such pressure as may be
necessary for the best operating conditions. In applying the gunite, the discharge nozzle
shall be held so that the stream of the material shall impinge as nearly as possible at the
optimum angle to the surface for minimum rebound, and the velocity of discharge from
the nozzle, the distance of the nozzle from the surface and the amount of water used in
the mix and shall be regulated so as to produce a coating with a minimum rebound of
the material and no sagging. Obstructions such as service lines shall be removed to
enable direct application of gunite to the surfaces. Rebound material shall not be used
again shall be removed from the work and disposed off by the Contractor as part of the
work.
(f) During the application of gunite, the Contractor shall provide adequate ventilation
facilities and take such other measures as are necessary for the safety of his workman,
including provision of face protection for nozzlemen.
20.13.5 Preparation
(a) The location where gunite is to be used will be as shown in Drawings.
(b) Wherever gunite is required the Contractor shall clean and prepare the surfaces to
receive the coating. Loose or shattered rock, rock debris, loose concrete soil or other
loose material shall be removed from the surfaces. Material in clay seams shall be cut
back to a depth as directed to provide a key. After the loose material has been removed,
the surface shall be washed where required with a strong air-water jet or by other
approved means.
(c) The reinforcing fabric or BRC mesh shall be set on slope surface using cement-sand
spacer block and shall not touch the ground surface. The fabric or BRC mesh shall be
fixed to the ground using dowels spaced at both directions at distance as shown in the
Drawings.
(d) Dowels shall be fixed to the ground using cement grout. The drill holes for the dowels
shall not less than 50mm diameter. The grout with dowels in it shall gain a sufficient
strength before application of gunite.
20.13.6 Application
(a) Gunite shall only be applied in the presence of the S.O. and shall be built up in
successive layers, each layer generally not exceeding 50mm in thickness, such that
sagging and bleeding does not occur. Care shall be taken to ensure that cavities
resulting from cutting back to clay seams, as described in sub-clauses (5) of this Clause
are completely backfilled with gunite. Where reinforcing fabric support is used, the
mortar shall cover the fabric to a depth of at least 30mm.
S20 - 56
(b) All rebound and other loose material shall be removed by air jets or other suitable
means from the surface of each layer as work proceeds.
(c) During the application of gunite, any water flowing over or seeping through the surface
to which the gunite is to be applied, shall be diverted by the use of panning, pipes, felt
strips or other approved means. Where directed, formed holes or pipe outlets shall be
provided in the coating to relieve water pressure on the coating.
(d) Gunite shall be not be applied to an area until all blasting within 50 M of the area has
been completed, unless otherwise approved or directed by the S.O.
20.13.7 Curing
All gunite shall be cured with water and shall be cured continuously for at least 7 days
immediately following placement. Natural curing may be allowed if atmospheric conditions
surrounding the gunite are satisfactorily, such as when the relative humidity is at or above 85
percent.
20.14.2 Materials
20.14.2.1 Stone
Stone shall be clean rough quarry stone, or pit or river cobbles, or a mixture of any of these
materials, and shall be essentially free from dust, clay, vegetative matter and other deleterious
materials. Individual pieces of stone shall be approximately cubical or spherical. The
maximum thickness of the stone shall in no case exceed the thickness of the wall or portion of
the structure into which it is being built. The size of the stone shall be > 100 mm and <
200mm, unless otherwise indicated in the Drawings. The stone shall be hard, tough, durable
and dense, resistant to the action of air and water, and suitable in all respects for the purpose
intended.
S20 - 57
The ingredients for mortar shall be measured in proper gauge boxes and mixed on a clean-
boarded platform or in an approved mechanical batch mixer.
All mortar shall be used within 30 minutes of mixing and no reworking of mortar shall be
permitted thereafter.
Construction of mortared stone pitching shall commence at the lowest part of each structure or
section of a structure and continue progressively upward. Long structures of slope surface
protection shall be constructed in section of practicable length, to the satisfaction of the S.O.
The surface against which the work is to be placed shall be moistened with clean water little in
advance of construction, and covered with a layer of cement mortar about 50 mm thick. Stones
shall then be firmly set by hand into the mortar, densely packed against adjacent stones and
built up to form a stone structure of more or less uniform thickness which shall nowhere be
less than 300 mm (measured perpendicularly to the surface covered). All the while that stones
are being placed, all voids in the structure shall be packed solidly with mortar and stone spalls;
however the surfaces of stones in the exposed faces and edges shall not be covered with
mortar. The exposed surfaces and edges of the structure shall be constructed such that they
have as large a proportion as practicable composed of stone faces. Weep holes shall be
provided as shown on the Drawings or as directed by the S.O.
Mortar which has been mixed for more than 30 minutes shall not be used in the works. Nor
shall mortar be laid against the supporting surface more than 2 minutes before pitching stone
and building up the structure to full thickness is commenced on any section of the work, as the
construction advances.
The work shall be carried out and finished all to the satisfaction of the S.O.
20.15 GEOCELL
20.15.1 Scope
This specification covers the general and technical requirements for the supply and installation
of Cellular Retention System as described herein. All materials used and the works shall meet
the requirements of this specification and details shown on the contract drawings.
20.15.3 Setting-Out
The Contractor shall be responsible for the true and proper setting-out of the areas to which the
Cellular Retention System is to be placed and for the correctness of the lines, widths, levels
and slopes as shown on the contract drawings.
S20 - 58
20.15.4 Locally Produced Products
The Cellular Retention System to be used in this contract shall be fully of Malaysian
origin unless otherwise approved by the designer. The Cellular Retention System shall be
produced by local factory with ISO certification and equipped with testing laborato ry,
where sampling and testing can be readily carried out.
The Contractor is solely responsible for the good condition of the Cellular Retention System
stored at the worksite and in the event of damages or deteriorations of the Cellular Retention
System due to improper storage, he shall be liable to replace the affected materials at his own
cost when directed to do so by the S.O.
20.15.6 Testing
20.15.6.1 General
Prior to the procurement of materials, the contractor shall provide a sample and the
Manufacturer's Independent Test Report (ITR), showing full compliance of the proposed
Cellular Retention System to all the above-specified property values corresponding to their
respective test methods, for the approval of the S.O.
All tests shall be carried out in accordance with the codes of Practices and Standards as
provided within this specification, unless otherwise approved by the S.O. The independent test
report and tests shall be prepared and carried out at reputable institution or laboratory such as
SIRIM, IKRAM, UTM, UKM, UPM, UM or other accredited independent laboratories
approved by the S.O.
Routine sample testing, when required and specified, shall be carried out at factory or at
independent laboratory witnessed by the S.O.'s representative. The Contractor shall submit test
report showing compliance of the specification by independent testing authority or laboratory
such as listed above or an accredited laboratory approved by the S.O.
S20 - 59
indicated, the contractor must furnish with every consignment, an original Consignment
Certificate from the Manufacturer giving the following information:-
The structure provides lateral confinement of the infill materials. The enhanced system works
on the principle of friction between the infill materials and the cell walls as well as the lateral
confinement forces generated by the applied load thus minimising deformation and
subsequently improving the stability of the overall structure. The newly filled structure acts to
redistribute the load, sustain the erosive forces to protect the underlying soil layers and
reinforce the fill materials. When the Cellular Retention System is applied with suitable infill
materials, it offers cost-effective solutions to the following applications:
S20 - 60
Table 20.18b: General Properties of Cellular Retention System
Type
Property Units
K4 K6 K8
Cell Height, H mm 100 150 200
Minimum Cell Seam Peel
N 1450 2140 2850
Strength
Dimension: Expended Piece
Width m 2.2 2.4 2.8
Length m 3.05, 6.1 or as specified
Dimension: Expended Cell
Width mm 203 203 203
Length mm 244 244 244
Area mm2 248 248 248
20.15.8 Installation
20.15.8.1 General
Installation of Cellular Retention System shall be carried out by qualified and experienced
workers under the supervision of a qualified engineer.
(a) Well graded aggregates with maximum size not exceeding 50mm
The infill materials shall be well compacted within the cells, in accordance with the
requirements of the Works Specification and the Manufacturer's instructions as shown on the
contract drawing.
S20 - 61
with mortar, removing soft material and backfilling with concrete and providing adequate
drainage measures. Typical details of these items are shown in the Drawings.
(b) No blasting is permitted for the works under this Clause unless approved by the S.O.
(c) If, in the S.O.'s opinion, the rock stabilization works are required solely as a result of the
Contractor's standard of workmanship (for example poorly aligned pre-split drill holes) the
Contractor shall bear the cost of such stabilization measures as are required by the S.O.
(d) The S.O. will inform the Contractor of the extent and nature of rock stabilization work
required for any slope, or portion of slope, within two weeks of access being provided to
that slope or portion of slope. The S.O. will also inform the Contractor which of these
items, if any, he considers to be necessary as a result of the Contractor's standard of
workmanship.
(b) Where the slope stabilization details include the removal of rock or other materials the S.O.
may wish to carry out an additional inspection of the area of the slope from which rock or
other materials has been removed. If required by the S.O., the Contractor shall re-erect or
repairs the access to allow the additional inspection to take place.
(c) The Contractor shall make due allowance in his programming for the time required to erect
and maintain access to rock slopes.
(b) Such removal shall be carried out carefully so as to prevent boulders, rock fragments or
other materials from falling down the slope. Removal shall also be carried out in such a
manner as to prevent damage to other parts of the ground surface, slope drainage channels
or pipes, road surfaces, fencing and any other temporary or permanent works.
(b) Where ordered by the S.O., the Contractor shall remove all vegetation from joints and the
joints shall be sealed with a 1:2 cement/sand mortar.
(b) Before sprayed concrete is used, the Contractor shall submit his mix design for approval
and shall demonstrate the process that he will use by spraying trial panels to establish the
S20 - 62
suitability of the plant, the materials and the operators to be used. The trial panels should
consist of two types:
(i) A trial panel of 40mm thick spray not less than 3000mm x 3000mm located within
the Site as directed by the S.O.
(ii) A 1000mm x 1000mm x 100mm thick test panel sprayed at the same time and
cured in accordance with Sub-clause 9(ix).
Cores cut from trial panels shall be used to determine the density that can be achieved and
the tolerance within which the density can be maintained. Tests shall be made to determine
the average percentage of rebound for concrete of various thicknesses. The results of the
rebound tests shall be used in calculations of the cement content of the applied concrete.
The Contractor shall provide two copies of the copies of the results of all tests to the S.O.
Once the trial panels have been approved, the Contractor shall not alter the mix or means of
application without the S.O.'s written consent.
(c) Sprayed concrete shall be applied in layers not exceeding 40mm thick. The Contractor shall
put forward his proposals for achieving the required thickness to the S.O. for approval.
(d) All materials used shall comply with and shall be stored tested and used in accordance with
the provisions of the relevant Clauses in the Specification. The Contractor shall ensure that
a sufficient supply of material of uniform quality corresponding to the samples submitted is
available.
(e) The moisture content of the mix before use shall not exceed 10%, the remaining water
being added at the instant of application. The air and water supply, the rate of application
and all other factors affecting the quality of the work shall be adjusted by the operator so as
to produce dense concrete with no sloughing. No mix shall be used more than two hours
after any water has been added to it. Rebound material shall not be reused and, when so
required by the S.O., shall be removed within 8 hours of spraying.
(f) The rock slope or any previously sprayed concrete surface shall be cleaned down with an
air jet before being sprayed with concrete. Surplus water shall be removed by air jet and if
any water is flowing from or across the rock or existing sprayed concrete and is liable to
reduce the adhesion of the concrete it shall be diverted by the pipes, hoses or other
approved means before spraying starts. Where ordered or approved by the S.O., weep holes
shall be formed, or pipes and hoses built in to relieve water pressure behind the concrete
and to divert the water from the face.
(g) 50mm diameter weepholes shall be formed with PVC pipes at 1.2 metre centres in each
direction or otherwise as directed by the S.O.
(h) A record shall be kept of the quantities of all material used at each slope and shall be
submitted daily to the S.O.
(i) Immediately after application and for 3 days thereafter, sprayed concrete shall be protected
from the effects of weather, either
(i) after thorough wetting, by completely covering with approved waterproof paper or
plastic membrane maintained in contact with the concrete; or
(ii) by completely covering the concrete with layer of hessian, sacking, canvas or
similar absorbent material kept constantly wet.
(iii) The strength of the applied concrete shall be determined by crushing 100mm
diameter cores cut from 100mm thick test panels sprayed at the same time and
cured in the same manner as the in-situ concrete. Moulds for unreinforced test
panels shall be 1000mm x 1000mm x 250mm thick rigidly fixed alongside the
works to the approval of the S.O. One test panels shall be sprayed per 500m² or
more frequently as the S.O. may direct.
S20 - 63
Six cores shall be cut from each panel, three of which shall be crushed at 7 days and
three at 28 days. Cores shall not be taken within 125mm of the edges of the panel.
Prior to crushing the density of each core shall be measured. The minimum
equivalent cube strength of the core shall be:
at 7 days - 10 MPa;
at 28 days - 20 MPa.
(j) In addition to provision of test panels, complete areas of sprayed concrete shall be tested
from time to time by sounding them with a wooden mallet. Hollow sounding areas shall be
removed and resprayed or, at the discretion of the S.O. a second layer of sprayed concrete
shall be added. Any such remedial work shall not be measured for payment.
(b) This protective screen shall be a chain-linked steel net type and shall not be subject to
unravelling when individual links are broken.
(i) Chain Link Mesh: plastic coated, galvanised mild steel to BS 1722 Part 10, wire
core: 3.55mm diameter. Wire overall 4.75mm diameter, mesh: 50mm aperture, roll
width 2400mm, colour dark green, 14C 39 to BS 4800.
(ii) Line Wire : plastic coated galvanised mild steel to BS 4102, core diameter 3.55mm
diameter, wire overall 4.75mm diameter, colour dark green, 14C 39 to BS 4800.
(iii) Dowel bars of 25mm diameter mild steel to BS 4449 of generally 2000mm length
galvanised to BS 729 or equivalent.
(v) Steel Fixings: Eyebolt strains, ring nut fixings, bulldog clamps, anchor plates, etc all
to be galvanised to BS 729.
(c) The protective screen shall generally be fixed onto the final rock face in the following
manner as directed by the S.O.
(i) Drill 50mm diameter holes in the rock along the top of the rock face at 1000mm
centres and 1500mm depth.
(ii) Dowel Bars to be installed, with approved resin or cementitions grout approved by
the S.O., such that 500mm of the dowel projects above the rock surface.
(iii) Chain Link Mesh netting to be hung vertically in 2400mm wide strips to cover the
face with 300mm overlaps between adjacent strips.
(iv) Galvanised steel wire rope is to be threaded through the top mesh and secured to the
projecting dowel bars.
(v) Bottom and sides edges of chain link mesh to be secured by threading 16mm dia.
galvanised steel wire rope through the mesh and fixed to rock bolts by bulldog
clamps and anchor plates.
S20 - 64
(vi) Vertical joints in the chain link mesh are to be secured by threading line wire down
through the overlap, the line wires being clamped at the top to dowel bars and
tensioned by means of an eyebolt strainer at the bottom fixed to a rock bolt.
(vii) Rock bolts as directed by the S.O. to be used to tie down bottom, side edges and
general areas. Vertical lap jointing line wires are to pass under the anchor plates.
20.16.7.2 Materials
20.16.7.2.1 Rock Bolt Bars
(a) Rock bolt bars shall be straight shaft, deformed, solid, continuous thread bar, new, and
undamaged. Rock anchor steel shall be protected from dirt, rust and deleterious
substances.
(b) Rock bolt bars shall be ASTM A722 Grade 150 steel, galvanized. The diameter of
the rock bolt as specified in the Drawings. All exposed parts of the rock anchor, shall
be galvanized in accordance with ASTM A123/ASTM A153.
(b) Surface Bearing Plates. Surface bearing plates shall be fabricated from A36 steel
and shall have a minimum size of 7” (177.8mm) x 7.5” (190.5mm) x 1.75” (44.45mm).
(c) Beveled Washers, Flat Washers and Wedges. Beveled washers, hardened flat
washers, and wedges for the anchorage shall be designed to preclude premature
failure of the pre-stressing steel due to notch or pinching effects.
(d) Heavy 2H Hex Nuts. Heavy 2H hex nuts shall be constructed for threaded
engagement with the outer end of the rock bolt bar. The nut should be heavy duty
type with round head, conforming to ASTM A-325. Anchor nuts shall develop an
ultimate strength not less than 100 per cent of the guaranteed ultimate strength (GUTS) of
the bar and conform to ASTM A436.
(e) Centralizer. Centralizers are required and shall be fabricated from Schedule 40
PVC, or other material not detrimental to the steel rock bolt bar (wood shall not be
used) and shall be capable of being securely attached to the bar. The centralizers shall be
sized to meet the tolerance requirements for the grout cover defined in sub-section
20.16.7.3.2.
(f) Coupler Protection. The coupler and any exposed bar section next to it shall be
covered with a corrosion proof compound or wax impregnated cloth tape. The coupler
area shall be covered by a smooth plastic tube complying with the requirements set forth
in section 2.5, overlapping the adjacent sheathed bar by at least 1 inch (25.4mm). The two
joints shall be sealed each by a coated heat shrink sleeve of at least 6 inches (152.4mm)
length, or approved equal. The corrosion proof compound shall completely fill the
space inside the cover tube.
S20 - 65
20.16.7.2.3 Cement Grout.
(a) Rock bolt grout shall be non-shrink neat cement with a maximum water to cement
ratio of 0.45 by weight.
(b) Water for mixing grout shall be potable and free from substances which might be
deleterious or corrosive to concrete or steel.
(c) Grout strength accelerators shall not be used. Admixtures which control bleed and
retard set may be used. Admixtures shall be mixed and placed in accordance
with the manufacturer‟s recommendations.
(d) The cement grout mix shall provide a minimum compressive strength of 3000 psi at
the time of stressing.
(e) Appropriate measures shall be taken to preclude freezing of the grout prior to its
reaching design strength.
(f) Cement shall conform to AASHTO M 85/ASTM C 150, Type I, II, or III Portland
cement.
20.16.7.2.4 Sheathing
Sheathing used over the rock bolt bar in the unbonded (free stressing ) zone shall be made
of material with the following properties: resistant to chemical attack from aggressive
environments, grout or corrosion inhibiting compounds; resistant to aging by ultraviolet light;
non-detrimental to the rock bolt bar and capable of withstanding abrasion, impact and
bending during handling and installation. The minimum wall thickness for the sheathing
shall be 0.060 inch (1.524mm) for polyethylene or polypropylene, 0.040 inch (1.016mm) for
PVC tubing and 0.20 inch (5.08mm) for steel tubing or pipe. The sheathing shall permit the
unobstructed elongation of the unbonded length during stressing.
(b) The minimum hole diameter shall be selected such that a minimum of 1.25 inches
(31.75mm) of grout cover is provided around the rock bolt bar within the anchor zone.
(c) The bonded length and associated hole diameter shall be large enough to provide a
capacity of at least 1.33 times the design load or as directed by the S.O.
(e) Centralizers shall have a maximum spacing of 7 feet (2.13m) and the lowest
centralizer shall be located 3 feet (1m) or less from the end of the rock bolt bar.
(f) The deviation of the drilled hole entry angle from the specified inclination and
direction shall be no more than 3 degrees.
S20 - 66
20.16.7.3.3 Drilling
Rotary percussion equipment shall be used to drill the holes. The drill hole diameter shall
conform to the requirements of this special provision. As a minimum, the drill hole shall
extend 12 inches (304.8mm) below the design depth of the rock bolt bar. In down bolting
situations, the drill holes shall extend 16 inches (406.4mm) beyond the length of the rock
bolt bar. Care shall be taken to insure an accurate and straight hole. Drilled holes shall be
cleaned of all drill cuttings, sludge and debris before the rock bolt bar is inserted into the hole.
20.16.7.3.4 Installation
(a) As a minimum, the bottom of the rock bolt bar shall be positioned 12 inches
(304.8mm) above the bottom of the drilled hole. In down bolting situations, the bottom
of the rock bolt bar shall be positioned 16 inches (406.4mm) above the bottom of the
drilled hole.
(b) The threaded outer end of the rock bolt bar shall extend the minimum length beyond the
anchorage that will be capable of accepting the proof test and lift off equipment. The
anchorage nut shall be tightened using an approved post tensioning hydraulic jack,
which permits tightening of the nut during tensioning.
(c) All equipment used for placing shall be such that it will not damage the rock bolt or
its accessories.
(d) Chipping out the rock or building a pad may be required to provide a level surface
for the bearing plate. Pads must be constructed of materials that will withstand the
applied lock offload without loss of strength over the life of the rock bolt. The
design, method of construction and materials used for the pad must be submitted to
the S.O. for approval.
(e) The contractor shall keep and provide a borehole log for each borehole drilled for rock
anchors. The log shall include, but not limited to the following: hole location, hole
diameter, hole length, angle from horizontal, date/time of drilling, drilling equipment
used, encountered subsurface conditions (groundwater, joints, voids, soil/weak rock,
etc.), and name of driller. The borehole logs shall be submitted to the S.O. on a daily
basis.
(f) All damage to the galvanized surfaces, and threaded portions of all fittings and
fasteners and cut ends of bolts after assembly, shall be repaired by thoroughly wire
brushing the damaged area and painting it with two to four coats or to a thickness
equivalent to the surrounding galvanizing, of an approved organic zinc-rich repair
paint containing 92 per cent (min) zinc by weight.
20.16.7.3.5 Grouting
(a) Grouting of the annular space around the rock bolt shall be accomplished by pressure
grouting with a grout pump, providing a minimum of 90 psi capacity. Mixers and
pumps shall have adequate capacity and hoses shall be sized to allow continuous
grouting of an individual bolt within one hour or less.
(b) All grout pipes, tubes and fittings shall be clean and free from dirt particles, grease,
hardened grout, or other contamination before grouting is commenced for any bolt. All
surplus water and diluted grout shall be flushed or blown from all lines before
commencing injections. The grout line shall be attached to the grout injection tube with
suitable fittings such that leakage is entirely prevented.
(c) The grout shall be injected at a pressure, which is sufficient to overcome hydrostatic
head. The pressure, which is used, shall be approved by the S.O. Dewatering or pre-
grouting may be required for proper grouting of the rock bolt in groundwater or poor
rock conditions.
(d) Bolts in upward inclination shall use a sealing grout to seal the opening around the bolt
prior to grouting through a short tube, which extends through the sealing grout. Such
S20 - 67
bolts shall be considered grouted when there is a full return of grout through a vent hole
within the sealing grout.
(e) The anchor bond length shall be grouted by injecting grout at the lowest point in the
anchor.
(b) The testing equipment shall include at a minimum one dial gauge, a dial gauge support,
and a jack with pressure gauge. The equipment shall be capable of stressing the rock
bolt to the maximum specified test load within the rated capacity. The pump shall be
capable of applying each load increment in less than 60 seconds. The equipment shall
permit the rock bolt to be stressed in increments so that the load can be raised or
lowered in accordance with the test specifications, and allow the bolt to be lift-off tested
to confirm the lock-off load. Stressing equipment shall have been calibrated by an
independent test laboratory within an accuracy of ±2% within 60 days prior to use.
Rock anchor testing will not be allowed until approval of the calibration report by the
S.O. The calibration certificate and graph shall be available on site at all times. The
production gauge shall have graduations not larger than 100 psi. The equipment that has
been calibrated shall be used which permit the measurement of total movement at every
load increment to be read to the nearest 0.001 inch (0.0254mm). The dial gauge shall
have sufficient travel to record the total rock bolt movement at the maximum test load
without the need to reset at an interim point.
(c) Testing Equipment Setup. Prior to setting the dial gauge, the alignment load shall be
accurately placed on the rock bolt. The alignment load shall be determined by the S.O.
as per cent of the design load. The dial gauge shall bear on the pulling head of the jack
and the stems shall be in alignment with the rock bolt direction. The dial gauge shall be
supported on an independent fixed frame, such as a tripod, which will not move as a
result of stressing or other construction activities during the test.
(d) Testing Schedule. Proof tests shall be performed by incrementally loading the rock
bolt to 133 per cent of the design load (DL). The rock bolt movement at each load
shall be measured and recorded by the S.O. At load increments other than the
maximum test load, the load shall be held long enough to obtain a stable reading.
Incremental loading for proof tests shall be in accordance with the following schedule:
AL
0.25DL
0.50DL
0.75DL
1.00DL
1.20DL
1.33DL
AL
Lock-off
Lift- off Reading
All load increments shall be maintained within 5 per cent of the intended load.
Depending on performance, either 10 minute or 60 minute creep tests shall be
performed at the maximum test load (1.33 DL). The creep period shall start as soon
as the maximum test load is applied and rock bolt movement shall be measured and
recorded at 1, 2, 3, 4, 5, 6, and 10 minutes. Where the rock bolt movement between 1
and 10 minutes exceeds 0.040 inch (1.016mm), the maximum test load shall be
maintained an additional 50 minutes and movements shall be recorded at 20, 30, 40, 50,
S20 - 68
and 60 minutes. Total creep movement must not exceed 0.080 inch (2.032mm) between the
6 and 60 minute readings.
(e) Proof Test Acceptance Criteria. Proof tests shall be considered acceptable when all
of the following criteria are met:
(i) A total creep movement of less than. 0.04 inch (1.016mm) is observed between the
1 and 10 minute readings or a total creep movement of less than 0.08 inch
(2.032mm) is observed between the 6 and 60 minute readings.
(ii) The creep rate is constant or decreasing throughout the creep test load hold
period.
(iii) The total movement at the maximum test load exceeds 80 per cent of the
theoretical elastic elongation of the rock bolt unbonded length.
(iv) A pull out failure does not occur at the maximum test load. Pull out failure is
defined as the load at which attempts to increase the test load simply result in
continued pull out movement of the rock bolt. The pull out failure load shall be
recorded as part of the test data.
(f) Lock Off Procedures. After completion and acceptance of the proof test, the rock
bolt shall be locked off at the design load or at a load as directed by the S.O. After
transferring the load to the anchorage and prior to removing the jack, a lift-off test
shall be conducted to confirm the magnitude of the load in the rock bolt. This load
shall be determined by reapplying the load to the rock bolt to lift off the anchor nut
without turning the anchor nut. The lift-off load shall be within 5 per cent the design
lock off load. If these criteria are not met, the rock bolt load shall be adjusted
accordingly and the initial lift-off reading repeated.
20.16.7.3.7 Submittals
Submit a rock bolt installation plan, for approval, that includes the Contractor‟s
qualifications, details the rock anchor type, couplings, face plate and nut, drilling operation, the
proposed rope access methods if applicable and safety plan, the assembly of the bolt with
its accessories, the method of bolt installation including grout mixes, testing procedures,
and the method for providing a level surface for the bearing plate ten days prior to
commencement of work. Submit manufacture‟s certificates of compliance for the
following: rock bolt thread bar, complete rock bolt head assembly including nuts, wedges,
washers, plates, covers and trumpet, smooth sheathing, centralizers, corrosion inhibitor
compound, and grout design with admixtures.
S20 - 69
Figure 20.3: Pre-stressed Corrosion Protected Grouted Rock Bolt
20.16.8.2 Materials
20.16.8.2.1 Rock Dowel Bars
(a) Rock dowel bars shall be straight shaft, deformed, solid, continuous thread bar, new,
and undamaged.
(b) Rock dowel bars shall be galvanized ASTM A722 Grade 150 steel. The minimum
diameter as shown on the Drawings and/or as directed by the S.O.
(b) Surface Bearing Plates. Surface bearing plates shall be fabricated from A36 steel and
shall have a minimum size of 7” (177.8mm) x 7.5” (190.5mm) x 1.25” (31.75mm).
S20 - 70
(c) Beveled Washers, Flat Washers and Wedges. Beveled washers, hardened flat
washers, and wedges for the anchorage shall be designed to preclude premature failure
of the steel due to notch or pinching effects.
(d) Heavy 2H Hex Nuts. Heavy 2H hex nuts shall be constructed for threaded engagement
with the outer end of the rock dowel bar. The nut should be heavy-duty type with round
head, conforming to ASTM A-325.
(e) Centralizer. Centralizers are required and shall be fabricated from Schedule 40 PVC,
or other material not detrimental to the steel rock dowel bar (wood shall not be used)
and shall be capable of being securely attached to the bar. The centralizers shall be sized
to meet the tolerance requirements for the grout cover defined in section 20.16.8.3.2.
(f) Coupler Protection. The coupler and any exposed bar section next to it shall be
covered with a corrosion proof compound or wax impregnated cloth tape. The coupler
area shall be covered by a smooth plastic tube complying with the requirements set
forth in section 2.5, overlapping the adjacent sheathed bar by at least 1 inch (25.4mm).
The two joints shall be sealed each by a coated heat shrink sleeve of at least 6 inches
(152.4mm) length, or approved equal. The corrosion proof compound shall completely
fill the space inside the cover tube.
(b) Water for mixing grout shall be potable and free from substances which might be
deleterious or corrosive to concrete or steel.
(c) Grout strength accelerators shall not be used. Admixtures which control bleed and
retard set may be used. Admixtures shall be mixed and placed in accordance with the
manufacturer‟s recommendations.
(d) The cement grout mix shall provide a minimum compressive strength of 3000 psi.
(e) Appropriate measures shall be taken to preclude freezing of the grout prior to its
reaching design strength.
(f) Cement shall conform to AASHTO M 85/ASTM C 150, Type I, II, or III Portland
cement.
(c) Centralizers shall have a maximum spacing of 10 feet (3.05m) and the lowest
centralizer shall be located 5 feet (1.52m) or less from the end of the rock dowel bar.
S20 - 71
(d) All damage to the galvanized surfaces, and threaded portions of all fittings and fasteners
and cut ends of bolts after assembly, shall be repaired by thoroughly wire brushing the
damaged area and painting it with two to four coats or to a thickness equivalent to the
surrounding galvanizing, of an approved organic zinc-rich repair paint containing 92 per
cent (min) zinc by weight.
(e) The deviation of the drilled hole entry angle from the specified inclination and direction
shall be no more than 3 degrees.
20.16.8.3.3 Drilling
Rotary percussion equipment shall be used to drill the holes. The drill hole diameter shall
conform to the requirements of this special provision. As a minimum, the drill hole shall
extend 12 inches (304.8mm) below the design depth of the rock dowel bar. In down bolting
situations, the drill holes shall extend 16 inches (406.4mm) beyond the length of the rock
dowel bar. Care shall be taken to insure an accurate and straight hole. Drilled holes shall be
cleaned of all drill cuttings, sludge and debris before the rock dowel bar is inserted into the
hole.
20.16.8.3.5 Installation
(a) As a minimum, the bottom of the rock dowel bar shall be positioned 12 inches
(304.8mm) above the bottom of the drilled hole. In down bolting situations, the bottom
of the rock bolt bar shall be positioned 16 inches (406.4mm) above the bottom of the
drilled hole.
(b) All equipment used for placing shall be such that it will not damage the rock dowel or
its accessories.
(c) Chipping out the rock may be required to provide a level surface for the bearing plate.
All voids behind the bearing plate shall be completely filled with cement grout. Cement
grout shall be used to provide a smooth surface for the bearing plate.
(d) All damage to the galvanized surfaces, and threaded portions of all fittings and fasteners
and cut ends of bolts after assembly, shall be repaired by thoroughly wire brushing the
damaged area and painting it with two to four coats or to a thickness equivalent to the
surrounding galvanizing, of an approved organic zinc-rich repair paint containing 92 per
cent (min) zinc by weight.
20.16.8.3.6 Grouting
(a) Grouting of the annular space around the rock dowel shall be accomplished by pressure
grouting with a grout pump, providing a minimum of 90 psi capacity. Mixers and
pumps shall have adequate capacity and hoses shall be sized to allow continuous
grouting of an individual dowel within one hour or less.
(b) All grout pipes, tubes and fittings shall be clean and free from dirt particles, grease,
hardened grout, or other contamination before grouting is commenced for any rock
dowel. All surplus water and diluted grout shall be flushed or blown from all lines
before commencing injections. The grout line shall be attached to the grout injection
tube with suitable fittings such that leakage is entirely prevented.
S20 - 72
(c) The grout shall be injected at a pressure, which is sufficient to overcome hydrostatic
head. The pressure, which is used, shall be approved by the S.O. Dewatering or pre-
grouting may be required for proper grouting of the rock dowel in groundwater or poor
rock conditions.
(d) Rock dowels in upward inclination shall use a sealing grout to seal the opening around
the dowel prior to grouting through a short tube, which extends through the sealing
grout. Such rock dowels shall be considered grouted when there is a full return of grout
through a vent hole within the sealing grout.
(e) The rock dowel shall be grouted by injecting grout at the lowest point in the rock dowel
bar.
20.16.8.3.7 Submittals
Submit a rock dowel installation plan, for approval, that includes the Contractor‟s
qualifications, proposed construction sequence and schedule, proposed rope access methods if
applicable and safety plan, proposed drilling methods and equipment, the assembly of the rock
dowel with its accessories, proposed mix design for the grouting, the method of rock dowel
installation, and the method for providing a level surface for the bearing plate. The installation
plan shall be submitted ten days prior to commencement of work in accordance with 105.02.
Submit manufacture‟s certificates of compliance for the following: Rock dowel thread bar,
complete rock dowel head assembly including nuts, wedges, washers, plates, covers,
centralizers and grout design with admixtures.
1. Settlement Of Subsoil
Settlement of subsoil due to fill is to be measured by means of settlement plates. Settlement plates are
positioned before the fill is laid.
The settlements plates shall be placed at locations indicated on the drawing. They shall be located in
areas that are least affected by construction vehicles and plant. They shall be properly protected with a
wooden barricade, 1m high and labelled with visible reference numbers. Heavy compaction plant shall
not approach within 1.5m of projecting instruments.
Damaged instruments shall be replaced or repaired by the Contractor at his own expense within seven
days.
3. Frequency of Measurement
S20 - 73
The frequency or the interval of measurement is dependent on the rate of settlement of subsoil. Close
intervals, are used during and shortly after fill has been laid. The intervals are increased with increase
in the duration of lapse time. The following can be used as a guide:
a) During filling
Installation of precise instrument involves the supply and installation of the installation at positions as
indicated by the S.O./Engineer.
The temporary bench marks will be installed at the nearby stable structure or remote from the
reclamation area and marked on an end bearing pile or similar structure.
b) Settlement Plates
The precise level settlement measurements shall be referenced to the temporary bench marks.
The measuring instruments shall be a precise level, capable of allowing readings to be read to
0.1 mm.
5. Plotting
S20 - 74