WI-NG-6460-002-090 Work Instruction For ACSE - ABTS - ToP Scheme Check & FT Rev00

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

NATIONAL GRID

Title: Index Number: Revision Number: Page Number:


WI-NG-6460-002-090 00 1 of 5
Prepared By: Orig. Issue Date:
2015-07-01
Revision Date:
Tarek Mohammad Ahmad
Technical Support & Coordination Division
Reviewed By:

ACSE / ABTS / TOP Muhammad Al-Buhairi, Division Manager


Technical Support & Coordination Division, CSD
Scheme Check and Validated By:

Function Test
Emad Abdullah Bawajih, Division Manager
Standards and Procedures Division, AQPD, Technical Services
Recommended By:
-----

Concurred By:
-----

Approved By:

Mutlaq N. Al-Otaibi, Department Manager


Commissioning Services Department, Technical Services

1.0 INTRODUCTION

Proper commissioning of ACSE / ABTS / TOP Scheme and Function check is an


important issue to prove that new ACSE / ABTS / TOP panels have been properly
shipped and correctly installed. This work instruction highlights the necessary steps
related to proper commissioning of new ACSE / ABTS / TOP panels in HV and EHV
substations.

All ACSE / ABTS / TOP panels must be tested in the factory before delivery to the
site and must be tested by commissioning contractor at site after installation for
processing to begin in the on-site Commissioning and testing phase. Commissioning
tests at site is done to prove that:

 No ACSE / ABTS / TOP panel was subjected to any damage during


transportation.
 Each ACSE / ABTS / TOP panel has been installed correctly.
 Each equipment in ACSE / ABTS / TOP panel is working in coordination with
other equipment, as specified.
 All equipment in ACSE / ABTS / TOP panels are safe for putting into service.
 The ACSE / ABTS / TOP Scheme and Function check is completely correct and
all equipment work as per checked scheme
Archiving System Website: http://AMAS
TP-NG-6250-001-007
NATIONAL GRID

Title: Index Number:


WI-NG-6460-002-090
ACSE / ABTS / TOP Scheme Check and Page Number:
2 of 6
Function Test

This Work Instruction has reference to Procedure PR-NG-6460-002 “Project


Commissioning”.

2.0 RESPONSIBLITIES
- Anyone working in testing location during commission stage must follow the safety
requirements as per SEC rules and CSD employees are responsible for applying
safety rules in all places which they working in.
- Project site engineer is responsible for committing the contractor to prepare
testing and commissioning places to be done in proper climate conditions as per
Company policies, procedures and accepted temperatures the relays, devices and
test equipment can be tested or operated within it.
- Any of CSD staff is responsible for testing activities according to approved
specification and design and he shall not start any test for any ACSE / ABTS /
TOP Scheme and Function check until providing the following:

o Approved test forms.


o Signed test formats of all activities which must be completed before ACSE / ABTS
/ TOP Scheme and Function check Factory Tests certificates.
o Updated Approved final settings.
o All relays must be configured.
o Relay manual.
o Approved schematic drawings.
o Protection requirement.
o Test equipment valid calibration certificates.
o Approved Contractor organization chart.
o Contractor staff approved qualification certificates.

- Its responsibility of the commissioning contractors to provide all testing ACSE /


ABTS / TOP Scheme and Function check with its valid calibration certificates that
will maybe require applying the testing / commissioning procedure in proper
manner.
- Its responsibility of the CSD Engineer/Technician to check and witness all
activities required for ACSE / ABTS / TOP Scheme and Function check following
all of this work instruction.
- CSD Engineer/Technician is responsible for recording status of any test for
ACSE / ABTS / TOP Scheme and Function check in its check list and test form as
Archiving System Website: http://AMAS
TP-NG-6250-001-007
NATIONAL GRID

Title: Index Number:


WI-NG-6460-002-090
ACSE / ABTS / TOP Scheme Check and Page Number:
3 of 6
Function Test

per the following work instruction.


- Each check list and test form shall be signed by CSD engineer/technician and
testing contractor engineer.

3.0 Work Instruction of ACSE / ABTS / TOP Scheme check and Function Test

Auto Changeover Switching Equipment - Automated Bus Transfer Scheme - Trip on


Parallel Scheme

3.1 Visual Inspection

Item Description Remarks


1. General Visual Inspection. WI-NG-6460-002-056

3.2 Electrical tests

Item Description Remarks


1. WI-NG-6460-002-083
General Function Tests.
WI-NG-6460-002-085
2. Study the different schemes for automatic closing of the
standby or the parallel running Transformer incomer
Breakers or Bus section in case of tripping of any
transformer available in the Schematic diagram.
3. Study test format compared with schematic drawing and
protection requirement.
4. Check status of all related circuit breakers, devises,
equipments and protective relays for each simulation case.
5. Check 4 out of 5 interlocking scheme is achieved while DC
loss of PLC device.
6. Simulate operation cases one by one according to test
format and record results. (Check the Schemes by tripping
of the different transformers one by one and changeover of
the switchgears are according to the Scheme.)
Check the blocking of Changeover for the Blocking
Conditions of Auto Changeover of Switchgears.
Check the Scheme opening of Bus Couplers or Incomers
Archiving System Website: http://AMAS
TP-NG-6250-001-007
NATIONAL GRID

Title: Index Number:


WI-NG-6460-002-090
ACSE / ABTS / TOP Scheme Check and Page Number:
4 of 6
Function Test

in case of energization of tripped Transformer.


7. Check LEDs, display messages and alarm annunciations
for each simulation case.
8. Check all cases and conditions at ACSE/ABTS ON and
ACSE/ABTS OFF positions.
And check all cases and conditions at TOP ON and TOP
OFF positions.
9. Check all cases and conditions at control mode and ECC
mode and segregation between each other.
10. Measure all time settings in PLC configuration.
11. Check panel indication for:
ACSE/ABTS ready
ACSE/ABTS close command failed
TOP scheme selected

Archiving System Website: http://AMAS


TP-NG-6250-001-007
NATIONAL GRID

Title: Index Number:


WI-NG-6460-002-090
ACSE / ABTS / TOP Scheme Check and Page Number:
5 of 6
Function Test

4.0 REFERENCES

Index Number /
Title
Reference Number
PR-NG-6460-002 Project Commissioning Procedure
WI-NG-6460-002-056 Work Instructions of Protection relays general mechanical checks
& visual inspection
WI-NG-6460-002-083 Work Instructions of General Panel Scheme and Function Check
WI-NG-6460-002-085 Work Instructions of Relay and Control Panels Scheme and
Function Check
5.0 REVISION HISTORY

Version Date Brief Description of Change / Annual Review


00 2015-07-01 First issue.

Archiving System Website: http://AMAS


TP-NG-6250-001-007
NATIONAL GRID

Title: Index Number:


WI-NG-6460-002-090
ACSE / ABTS / TOP Scheme Check and Page Number:
6 of 6
Function Test

This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications therein found not conformance with the document shall be declared invalid.
For clarification and verification on this document, contact the following:

Engr. Tarek Mohammad Ahmad


Technical Support and Coordination Division
Commissioning Services Department
Technical Services Business Unit
Extension No. 77469 Email: 69608@ngrid.sa

Archiving System Website: http://AMAS


TP-NG-6250-001-007