Pig Launcher

Reduction
WBS Nombre de tarea Duration Inicio Final (Texto2) Start February 2024 March 2024
(Texto1) (Texto2) 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28
0 Pig Launcher Reduction Project 17 days dia -9 dia 38.5 Feb 9 '24
1 Welder qualification 5.5 days dia 11 dia 26 Feb 29 '24
1.1 Consumables Procurement 5.5 days dia 11 dia 26 Feb 29 '24
1.2 Welder Qualification 1 day dia 23 dia 25 Mar 12 '24
2 Reception of Pig Launcher 16 days dia -9 dia 7 Feb 9 '24
2.1 Platform design 4 days dia -9 dia -5 Feb 9 '24
2.2 Procurement of materials 4 days dia -5 dia -1 Feb 13 '24
2.3 Platform Manufacturing 5 days dia -1 dia 4 Feb 17 '24
2.4 Tests 3 days dia 4 dia 7 Feb 22 '24
3 Installation of template to fix spool 2 days dia 7 dia 9 Feb 25 '24
4 Pig Launcher 4.5 days dia 11 dia 24 Feb 29 '24
4.1 Pig Launcher Disembark 1 day dia 11 dia 12.5 Feb 29 '24
4.2 Pick up Pig Launcher 1 day dia 15 dia 17 Mar 4 '24
4.3 Crop the reduction(16x12” sch. 140) by cutting1disc
day dia 18 dia 19 Mar 7 '24
4.4 Reducer Delivery in Modec Warehouse 1 day dia 19 dia 20 Mar 8 '24
4.5 Pick up Reducer 2 days dia 22 dia 24 Mar 11 '24
5 Bevel machining 4 days dia 19 dia 23 Mar 8 '24
6 MPI on the bevels 0.5 days dia 23 dia 23.5 Mar 12 '24
7 Fitted the new reduction 16”x12” sch. 40 and 0.5 days dia 23.5 dia 24 Mar 12 '24
tack welding
8 Preheat by ceramic heater. 0.5 days dia 24 dia 24.5 Mar 13 '24
9 Welding application 3 days dia 24.5 dia 27.5 Mar 13 '24
10 Post welding process 10 days dia 27.5 dia 37.5 Mar 16 '24
10.1 MPI and RT inspection of the 12" Ø and 16" Ø 1 day dia 27.5 dia 28.5 Mar 16 '24
joints
10.2 PWHT Process 1 day dia 28.5 dia 29.5 Mar 17 '24
10.3 MPI/RT inspection of the 12" Ø and 16" Ø joints
1 day dia 29.5 dia 30.5 Mar 18 '24
10.4 Hydrostatic test 2 days dia 30.5 dia 32.5 Mar 19 '24
10.5 RT inspection of the 12" Ø and 16" Ø joints 1 day dia 32.5 dia 33.5 Mar 21 '24
10.6 Corrosion protection 4 days dia 33.5 dia 37.5 Mar 22 '24
11 Delivery of PIG LAUNCHER to MODEC's dock 1 day dia 37.5 dia 38.5 Mar 26 '24

This plan consider just laboral Tarea Resumen Resumen del proyecto