Professional Documents
Culture Documents
Schedule Optimization Brochure
Schedule Optimization Brochure
The table to the right shows the three Business Plan (FEL-1) Conceptual Plan (FEL-2) FEED (FEL-3)
stages of FEP, cost/schedule deliverables,
expected outcome, and decision gates ± 50% estimate ± 30% estimate ± 10% definitive estimate
at each stage. FEL presents an excellent Level I master schedule Level II milestone schedule Level III project schedule
opportunity to apply robust planning
early in a project’s life cycle, when the Project initiation into business plan Basis of design Tender documents
ability to influence changes in design is Gate 1: Approved for business plan Gate 2: Design basis approved Gate 3: AFE
relatively high and the cost to make those
changes is relatively low. It typically applies 4. Business Plan Level I Master Schedule (FEL-1)
to industries with highly capital-intensive
projects with long life cycles. The business plan stage is often referred to as the project initiation stage. Major activities include
conducting a business case, preliminary conceptual studies, scope definition, stakeholders’
The following sections recommend sched- identification, and benchmarking against similar internal or external projects. A business plan
ule quality checks at each stage of FEP. project schedule reflects the business plan milestones usually in bar chart format. It is developed
It is encouraged that schedule reviewers be mainly based on a brief scope of work and historical data including preliminary durations
included as part of gate reviews and score benchmarked against similar projects. The graphic below is an example of a business plan schedule
each phase relative to schedule quality for a large process plant project.
and schedule optimization with a grading
scale that includes “pass,” “fail,” or “needs The following quality checks identify the minimum quality measures to include with a Level I
improvement” on the project schedule. project master and business plan schedule:
If there are any failed items, the schedule
should not be accepted until all concerns, 1. Brief scope of work or project scoping document
errors, or problems have been corrected, 2. List of key interfaces within the project or with other projects
cleared, or considered. 3. Initial project charter
4. Schedule data used as benchmarks from similar projects
Major activities during conceptual engineering quality measures to include and consider for
include preparing the basis of design, perform- the Level II project milestone schedule:
ing a project feasibility study, issuing a prelimi-
nary Project Execution Plan (PEP), developing 1. The basis and assumptions used to prepare
the Work Breakdown Structure (WBS), con- the Level II project milestone schedule
ducting value improvement practices includ- 2. Complete “Design Basis” documents
ing project and schedule risks, validating all 3. Updated project charter
viable alternatives, and identifying long-lead 4. Project Execution Plan (PEP) including
procurement items. Major deliverables during list of key interfaces
this phase include a design basis package, pre- 5. Updated contracting strategy
liminary PEP, WBS, Level II project milestone
schedule, Schedule Risk Analysis (SRA) report, 6. Updated project risk management or
and ±30% budget estimate. risk register
7. Schedule Risk Assessment (SRA) report
During FEL-2, a detailed project milestone showing schedule confidence level
schedule is developed to plan and control 8. Updated constructability review report
the detailed activities required to produce
all FEL-2 deliverables and ensure they meet 9. Preliminary P&ID and other drawings,
milestone deadlines. The FEL-2 project plot plans, and diagrams
milestone schedule should be a Critical 10. Procurement duration(s) based upon
Path Method (CPM) schedule. Interactive actual vendor quotations
planning sessions are typically held during the 11. Process and utility sized equipment list
development to determine activity durations 12. Sized electrical equipment
and logic to ensure stakeholders alignment. 13. Bulk construction quantities
Schedule development is usually based on
14. Procurement strategy and material
activities defined in discipline man-hour We can help you provide
procurement plan
estimates. The above bar chart is an example
FEL-2 schedule of engineering deliverables for 15. Memorandum of understanding transparency and accountability
process flow diagrams (PFDs) and utility flow for execution
diagrams (UFDs), as well as preliminary piping 16. Commissioning, start-up, and for all project stakeholders.
and instrumentation diagrams (P&IDs). shutdown requirements
17. Change log documenting project changes
The ultimate objective is to prepare a well-
since start of FEL-2
developed FEL-2 target schedule that provides
a tool to measure the schedule/performance. 18. Benchmarking study or report
The following list provides the minimum 19. Value assurance reports
Front-End Schedule Optimization Services
6. FEED Plan Level III Project The Level III Project Summary Schedule (PSS)
Summary Schedule (FEL-3) is a CPM-based schedule using information
from FEL-2. The PSS is a fully resource-
The FEL-3 stage is project pre-planning, loaded schedule, and the activities for each
usually referred to as FEED. It focuses phase are logically linked to produce a project’s
on technical project requirements with a overall duration and resource requirements.
definitive cost estimate of ±10% accuracy. The Level III PSS establishes the baseline for
All required FEED documents should project durations and represents the basis for
be complete, such that the contracting project approval and total AFE funding. This
strategy is final, bidding and award of schedule is used for generating project baseline
the project execution are complete or progress “S” curves. The Level III PSS is an
in final stages, long-lead equipment actual deliverable of FEL-3 and is rigorously
vendors are selected or finalized, and reviewed at 60% development during
all known potential risks are identified. the schedule optimization workshop(s).
It also includes special studies such as A key deliverable is the Schedule Basis and
environmental studies and the hazard and Assumptions Memorandum that provides a
operability study (HAZOP), Electrical detailed explanation of how the Level III PSS
Transient Analyzer Program (ETAP), has been prepared.
energy optimization report, interface The Level III PSS will also include a quality
management, etc. Major deliverables The FEL-3 stage also includes schedule assessment using the guidelines established
include the final tender documents, optimization workshops that will achieve by the United States Defense Contract
Level III Project Summary Schedule alignment by all project stakeholders on Management Agency (DCMA). The DCMA
(PSS), and detailed PEP. The FEED the overall schedule, establish priorities, 14-point CPM schedule assessment check
package as a deliverable of FEL-3 is understand manpower requirements, identify is a helpful best-practice guide to assess the
usually of sufficient detail to prepare a the basis for schedule activity durations, quality of a CPM schedule’s technical aspects,
±10% accuracy estimate used to secure finalize the contracting and procurement which include the following:
authorization for permanent funding strategies, identify internal and external
expenditure (AFE). FEED provides the constraints, etc. The following checklist 1. Missing logic checks
baseline from which all subsequently identifies the minimum document quality 2. Negative lag (leads) checks
considered scope changes are measured. assessments that should be included with a 3. Excessive positive lag checks
Level III PSS submittal:
4. Logic type checks (i.e., FS, SS, FF,
1. Level III PSS with supporting Schedule and SF)
Basis and Assumptions Memorandum 5. Hard constraint checks
2. Final project charter, final PEP, and final 6. High (total) float checks
contracting strategy 7. Negative float checks
3. Updated project risk management 8. Long duration checks
We can help you avoid, document and risk register
9. Invalid date checks
4. Final constructability review report
minimize, or resolve disputes 10. Resource loading checks
5. Updated SRA report clearly showing
11. Late activity checks
during the entire project life cycle. schedule confidence level
12. Critical path test
6. Process, utility, and electrical sized
equipment lists 13. Critical Path Length Index (CPLI) check
7. Vendor quotations on long-lead 14. Baseline Execution Index (BEI) check
equipment delivery times
7. Project Advisory Services
8. Quantities and man-hours by discipline
for engineering and construction Long International and CORE’s project ad-
9. Updated procurement plan and visory services assist with the implementation
of project monitoring techniques to maintain
commissioning and start-up
cost, schedule, and quality objectives; provide
requirements
transparency and accountability for all project
10. Benchmarking report and final agreed- stakeholders; and avoid, minimize, or resolve
upon value assurance reports disputes during the entire project life cycle, in-
11. Critical milestones issue for-bid package cluding the important front-end design phase.
Long International, Inc. • 10098 Whistling Elk Drive • Littleton, Colorado 80127-6109 U.S.A. • Telephone: (303) 972-2443 • long-intl.com