Professional Documents
Culture Documents
Final PlanSche
Final PlanSche
1.5:
0.8
e 12
$9000
Confronting
® Forcing
Withdrawal
Smoothing
Question 6 0/1 point
Suppose you are a senior project manager on an industrial project. So far, you have spent $26,410 to conduct the reconnaissance and survey of the site,
prepare preliminary plans and drawings, and run Monte Carlo simulations. You are preparing to meet with senior management and your sponsor, but you
discover that there are new industrial bylaws that will cause you to spend an additional estimated $15,000 to revise your plans and drawings. You contact the
senior management and the sponsor of the project and trigger a change request. The change is approved by CCB and you adjust the cost performance
baseline. What variable represents the $26,410 in an Earned Value calculation?
® PV
BAC
AC
When the project is completed we will have spent 89 percent more than planned
© Under budget
-mpp
.mpt
XPV
® XER
Question 10 1/1 point
Kelsey and James are two persons who deal with the scope changes on a software project at Western University. Whenever, a change
request is triggered by a stakeholder, they immediately and efficiently process that request through Perform Integrated Change Control
Process and get the decisions made from the CCB. Neil and Kevin are also on the team but they are bothered at the least unless their
involvement is badly needed. It looks that this arrangement is working fine. What stage of team development, this scenario
demonstrates?
Storming
® | Performing
Forming
Norming
© $68,079.60
$47,277.50
$68,733
$0.72
Track progress
Analyze workloads
Confronting
| Forcing
Compromising
Smoothing
Question 14 0/1 point
Two of your project team members approach you with a conflict that they are having with each other over the technical approach to their work. One of the two people is
very aggressive and tries to get you to decide quickly. The other team member is quiet and seems less willing to talk about the issue. The conflict is starting to cause delays,
and you need to reach a decision quickly. What's the BEST approach to solving this conflict?
Tell the team members that they need to work this out quickly, because otherwise the project could face delays.
Tell the team members that they should take it to the technical functional manager.
© Storming
Performing
Norming
Forming
® Storming
Performing
Norming
Forming
Storming
Performing
© Forming
Norming
Question 18 1/1 point
As project manager, you scheduled a status update ing. During the ing, a problem developed, and the group di d it. The day after the meeting, Kevin
approached you and expressed his concern that the problem was not truly resolved. After thinking about it, he felt that his concerns were still valid and should be
addressed. What conflict resolution method was likely used at the status meeting?
® Smoothing
Forcing
Withdrawal
Collaboration
Confronting
Forcing
® Compromising
Smoothing
-$870
®) $870
89
113