Professional Documents
Culture Documents
Method Statement and Risk Assessment - Quarry Mining-R1
Method Statement and Risk Assessment - Quarry Mining-R1
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Method Statement
&
Risk Assessment
For
Project Name: New Rail Installation on Saqr Port Berth #5, Rak Rock LLC, RAK
Location of the Quarry mining
Works: P.O. Box 9593, Ras Al Khaimah, UAE
Title: METHOD STATEMENT OF CRANE RAIL SYSTEM
INSTALLATION AND RISK ASSESSMENT
Scope of works The task involves the installation and commissioning of a crane rail
system and includes the following work:
Page 1 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
TABLE OF CONTENTS
CH NO SR CONTENT PAGE
NO NO
1 PROJECT DESCRIPTION AND PHASING
1.1 Purpose 3
1.2 Scope 3
1.3 References 3
1.4 Definitions and abbreviations 4
1.5 Manpower 4
1.6 Plant and Equipment 4
1.7 Materials 4
1.8 Duration of work 5
1.9 Responsibilities 5
1.10 Project Team 6
3 RAIL CONSTRUCTION 9
8 CERTIFICATIONS 42
Page 2 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
1. PROJECT DESCRIPTION
1.1 Purpose
This work method statement is being submitted in connection with the requirement of project work
“NEW RAIL INSTALLATION ON SAQR PORT BERTH #5 by Quarry Mining
1.2 Scope
The scope of work to be executed under this Contract includes the installation of three rail lines
261m (quay) , 237m (middle rail) and 186m (land side) crane rail system, design, installation, and
commissioning crane rail system at Berth 5.
1.5 Manpower:
Site Engineer
Supervisor
Technicians and fitters
Welders
Surveyor
1.7 Materials:
Page 4 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
1.9 Responsibilities:
The primary responsibility of carrying out all the activities mentioned in this procedure rests
with the site- in-charge unless mentioned otherwise.
Project Manager: Overall execution and administration of the project as per contract
requirements, specifications and the PQP. Liaise with the Head (Quality & HSE) for
preparation and updating of PQP. Directly control the Site Engineers and Supervisors. He is
responsible to ensure that all the correct procedures are followed and all necessary permits
for the work are obtained in advance.
Site Engineer: Assess manpower, equipment or other resources required to ensure timely
completion of the project. Monitor availability of all materials as per schedule. Inform the
Project Manager for any non-availability of materials to take proper action. Carry out Ensure
that the drawings and documents are up to date and the latest drawing is available and is being
utilized in the project site works. Filled-up the check-sheet and submit the necessary IR to the
QA/QC function when the work is ready for inspection.
Page 5 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 6 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
All personnel accessing their site will wear the mandatory PPE. All workmen and staff shall
wear the mandatory and job specific Personnel Protective Equipments. Pre-task briefing
shall be conducted on every day before starting the work. Experienced and HSE inducted
workmen shall be deployed for the work
Page 7 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
2.4 Housekeeping
The equipment/tools/materials required for the work shall be stored /stacked
in such a manner so as to give a safe working atmosphere to the workforce at site.
All workplace areas shall be maintained clear of debris, waste and other rubbish, which shall
be disposed of in segregated containers for disposal. An adequate number of containers
marked appropriate labels for storage and disposal of waste materials shall be strategically
placed throughout the construction areas at all time.
Any spillages, such as oil or grease shall be immediately cleaned up, by absorption in inert
sand or other suitable materials. The materials for the particular work shall be stored at site
so that no obstructions to the work or access to the workforce.
Debris, waste oil containers etc shall be stacked and placed in a barricaded location away
from the work areas and access routes. Adequate fire precautions shall be in place. Before
leaving the site, it shall be ensured by the responsible person that the site area is cleaned and no
obstruction is encountered for next day work.
Page 8 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
3. RAIL CONSTRUCTION
The rail construction for landside, seaside & Middle rail is shown below. The rail construction will be in
a concrete recess. The width of the recess is about 400mm and the depth is about 150mm.
Page 9 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
4. Anchors: The crane rail construction will be anchored by the anchors of size M20x250mm and at the
same regular distance of 600mm
5. Cementitious grout: cementitious grout will be used to fill the void between concrete foundation and
soleplate
B) Middle rail
Page 10 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
9. Anchors: The crane rail construction will be anchored by the anchors of size M20x250mm and at the
same regular distance of 600mm
10. Cementitious grout: cementitious grout will be used to fill the void between concrete foundation and
soleplate.
Page 11 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
The installation works will be done in two phases. The first phase is 161m on the quayside and 186m on
the landside. The second phase will be 1 x 237m (middle rail).
Although the construction of the sea and land side is different as the middle rail construction, the
installation and sequence of working for both construction is similar
To ensure the quality of the works, safety, and planning the following site conditions are essential:
- The working location is free and no other activities take place at the same moment and place. This means
Berth 5 will be free during the complete first phase of the rail works and so on.
- Prior to each phase, BemoMMP will receive survey reports from the existing beams, both quay and
landside. The survey reports will show the dimensions of the existing concrete recesses (depth and
width), the depth related to the rail height reference, individual straightness, and center-to-center
alignment between both existing recesses.
- Reference points and offsets are marked on both the quay and land beam from the first day of the
installation of each phase.
Planning
Page 12 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 13 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
4.4 Welding
The rail joints will be welded according to the puddle arc welding methodology, applied welding standard
ISO-NEN-EN 3834-4.
Puddle arc welding is a welding process in which electrodes are used to obtain lengths without disruptions.
The complete welding process is done by hand. The working sequence for the puddle arc welding process
will be as follows:
- Aligning rail joint in height and direction by using steel wedges. A copper plate will be under the rail
joint
- Pre-heating rail ends by using heaters, supplied by oxygen and propane
- Welding feet from the rail joint by using electrodes. Earthing cable, welding machine and torch are
the most common equipment and tools for this activity. A power aggregate will take care of the
required power supply of 400V-32A.
- Welding body and head from the rail joint by using electrodes. Earthing cable, welding machine and
torch and copper blocks are the most common equipment and tools for this activity. A power
aggregate will take care of the required power supply of 400V-32A
- Removing copper blocks and steel wedges. To ensure both the quality and safety the welding works
will be carried out outside defining exclusion zone
- Re- profiling crane rail by means of using an electrical driven grinding machine after the cooling
down period from the weld
- After completion of all the welding works, a visual inspection will be carried out to check the quality of
the welding.
- .
Page 14 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 15 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 16 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
BemoMMP will use both a levelling instrument, total station instrument and alignment tools to perform the
alignment works.
The alignment works can only be carried out by the availability of reference points. The reference points
will be provided from the first day of the installation.
Next to the reference points the client will also take care of a survey report from the existing concrete recess
prior to the works. The survey reports will show the dimensions of the concrete recesses (depth and width),
the depth related to the rail height reference, individual straightness and centre-to-centre alignment between
both recesses at each three meters
Page 17 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 18 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Mix the cementitious grout with hand and Grout the soleplates according to the product specification.
The grout must flow under the soleplates from one side of the construction. This is to prevent air holes under
the soleplates.
Page 19 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 20 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
5. WELDING
Page 21 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 22 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 23 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 24 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 25 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 26 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
The project performance reporting will be accomplished through established status meetings,
reports, and internal project tracking systems. The following are a list of mechanisms used
that provide performance reporting:
1. Daily Progress report (Standard)
2. Daily progress report (Graphical)
3. Weekly Status Meeting
4. Monthly Client Meeting (or as necessary)
5. Project Manager Monthly Status Report
The quality assurance shall be ensured for workmanship, equipments and materials conformance
to the applicable standards and requirements at every stage of the construction. This shall be
monitored by quality control personnel or designated substitute on the site during the operation.
All inspections and tests shall be conducted in accordance with written test procedures as
detailed in the Project Quality Plan and Inspection and Test Plan approved by the Employer.
Applicable documents with latest version such as Inspection & Test Plan, Method Statements
shall be readily available and used by inspection and test personnel at the time of inspection as
referring documents.
Page 27 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
7. Risk analysis
Working without risks is not possible. Awareness and taking measurements will reduce the probability
and/or effects from the risks. This part of the method statement gives an overview of the appearing risks and
the specific (possible) measurements to take during the crane rail installation works.
The outlined risks can be divided into two themes; the risks which may impact the quality of the works (so-
called Q- risks) and the risks which may have an impact on the well-being/safety from the workers or the
environment (so called HSE- risks).
The risks will be discussed on the first day of the installation works.
Table 2: Q- risks
# Activity Potential danger Measurements
1 Welding and Bad rail performance at - Performance of welding works with
grinding works the welds experienced workers
- Facilitation of exclusion zones
- Free working area, no other activities
- Quality is more important than quantity
- Performance of welding works outside the
concrete recess (as much as possible)
- Following the welding procedure ISO-
NEN-EN 3834-4 from aligning, pre-
heating, welding and grinding
- Ensure all welding and grinding
equipment and tools are approved
- Protection of welding and grinding works
from wet and windy conditions
- Visual inspection of all the welds
-
2 Alignment Crane rail cannot be - Client provides survey report from casted
works aligned within the quay and landside beam to BemoMMP
tolerance range due to prior to the start of the works
location of concrete - Facilitation of reference points and offsets
recess by client at the start from the rail works
- Performance of alignment works with
experienced workers or close coordination
by experienced supervisors
- Check on reference points by BemoMMP
at the start from the works (only possible by
availability references)
- Free working area, no other activities
Page 28 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 32 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 34 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
Page 35 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
Page 36 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
Page 37 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
Page 38 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
5.1 Use lifting appliance
wherever possible.
5.2 Personnel to be aware of
manual handling
techniques prior to lifting
operations undertaken Site manager
Cuts, bruises & 5.3 Never exceed capacity,
Manual Plan the lift.
5 strains, traps, 3 4 12 5.4 Try to use mechanical aids 3 1 3
handling management,
personal injuries wherever possible.
site and safety
5.5 Observe weights and
management.
centre-of-gravity as
indicated or make an
assessment prior to
undertaking a manual lift.
Page 39 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
Page 40 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Risk Acceptance
criteria
Risk rating = Severity (S) x Probability (P) S P RR If RR > 6 then work will not commence S P RR
7.1 Movement to be along
approved routes only.
7.2 Use experienced staff to
operate machinery.
7.3 Use correct PPE and
comply with site rules.
7.4 Obey site speed limits and
Crushing or impact site traffic demarcation
measures and signs.
injuries or injuries to 7.5 Ensure all parts of the
Site Traffic others Serious vehicle operate correctly. Site manager
and Injuries, Damage to 7.6 Vehicle movements to be
management,
7 4 2 8 supervised and ‘Banked’
and safety
4 1 4
movement plant and equipment, when reversing.
7.7 Be aware of overhead management.
of vehicles Infringement of
supply hazards – detailed
safety distances, loss information to be supplied
of control. at site induction.
7.8 Follow site specific safety
instructions at all times.
7.9 Ensure pedestrian
walkways are clearly signed
and demarked from
transport routes
Page 41 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
8. CERTIFICATIONS
Page 42 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 43 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 44 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 45 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 46 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE
METHOD STATEMENT Rev: 00
AND
Doc No: QM/MSRA/2/24
RISK ASSESSMENT
Page 47 of 47
BEMO MMP RAIL SYSTEM LLC
Office 115, Adel Ahmed Al Wahedi Building, Al Marar, Deira, PO 235548, Dubai, UAE