Professional Documents
Culture Documents
60-8013 - Check List For Regeneration Gas Heater RFQ
60-8013 - Check List For Regeneration Gas Heater RFQ
PROJECT:
REQUISITION NUMBER: 0XXX-MI20-60PO-8013
CHECKED BY - PACKAGE ENGINEER:
VERIFIED BY - LEAD ENGINEER:
1.1 Whether Document numbering is as per Document Control procedure (0003-MI20-00P1-0100 or project specific
document numbering procedure, if any).
1.3 Whether all the latest applicable COMPANY and INDUSTRY standards have been provided as Reference.
Special Attention to project specific standards, if any.
1.4 Whether the design life of the equipment has been specified as per project specific requirements.
1.5 Whether Hazardous area requirement is specified as per the latest hazardous area drawings.
1.6 Whether Cable entries checked against Project requirements. (Refer Note (i) )
1.7 Whether the IP rating of all component have been specified as per Project requirement.
1.8 Whether Spares have been specified as per Project Spare requirement philosophy.
1.9 Whether make of all components have been specified as per Project approved vendor list
1.10 Whether the documentation requirement is correctly reflected in SDDR .(Include the NR-13 dossier index and NR-13
relevant documentation for Brazil Projects)
1.11 Whether the welding, coating & painting requirements has been specified as per project specific requirements.
1.12 Whether all lesson learnt have been incorporated from previous projects. Please check in MIMS -> Report -> Feedback
Log
2.2.5 Watt density of each heater element shall be proposed by Vendor. As per UOP requirement, for regeneration gas
heater design watt density should be no more than 3.88 W/cm sq. (Refer Note (vi) )
2.2.6 Heater shall be designed for continuous/intermittent etc operation as per requirement provided by Process.
(If intermittent, no flow condition has to be considered)
1 Of 3
CHECK LIST FOR ELECTRIC HEATERS
PROJECT:
REQUISITION NUMBER: 0XXX-MI20-60PO-8013
CHECKED BY - PACKAGE ENGINEER:
VERIFIED BY - LEAD ENGINEER:
2.2.7 As a minimum, the heater shall be provided with two duplex thermocouples for each bundle, one for flange and one for
terminal box. Necessary transmitters shall also be installed in an instrument junction box near the heater terminal box.
2.3.3 Whether the incoming and the heater voltage have been clearly specified including the variations allowed as per
applicable standards.
2.3.4 The short circuit capability requirement of the incoming and outgoing ACBs/MCCBs shall be clearly specified
as per project requirements. If panel directly powered from transformer, short circuit shall be calculated and informed
to vendor at the time of bid.
2.3.5 The incomer and outgoing breaker rating shall be clearly specified based on the upstream transformer and heater
rating respectively.
2.3.6 If ACBs are used as incomer, they shall be withdrawable time for maintenance and ACB trolley shall be included
in Vendor scope of supply.
2.3.7 Insulating Monitoring device shall be considered for panels directly powered from transformers.
2.3.8 Power transfer facility shall be considered for panels directly powered from transformers including necessary
electrical and mechanical interlock.
2.3.9 Necessary control, monitoring, indications, switched, trips etc shall be considered on the control panel based on
project requirements. All wiring inside panel shall be LSHF(Low smoke Halogen free)
2.3.10 When multiple stages being used, shall be checked whether all stages are thyristor controlled or some are thyristor
controlled & some contactor controlled. Where contactor controlled circuits are used, load sequencing shall be
included.
2.3.11 All relays inside control panel used for emergency shutdown shall be SIL 2 certified
3 MATERIAL
3.1 SHELL : It shall be dependent on maximum design temperature and process operation requirements. Typically
CARBON STEEL is allowed upto 400 deg C. STAINLESS STEEL may also be used if there are any
start-up pressurization issues. Shall be closely coordinated with Process/Mechanical.
3.4 BAFFLES: INCOLOY 800 for Regeneration Gas heater to have the same material as element to avoid differential
thermal expansion at high temperatures. STAINLESS STEEL for smaller heaters
3.5 TIE ROD : INCOLOY 800 for Regeneration Gas heater to have the same material as element to avoid differential
thermal expansion at high temperatures. STAINLESS STEEL for smaller heaters.
4 ACCESSORIES
4.3 TRANSMITTERS
4.3.1 Check the requirement in P&ID.
4.3.2 All pressure/temperature transmitters shall be considered as SIL 2 certified
4.3.3 Transmitter shall utilize standard 4-20mA protocol, using HART technology
5 TEST/CERTIFICATION REQUIREMENT
5.7 WELDING REQUIREMENT FOR SEAL WELDED ELEMENTS (As per Quality Standards)
6.3 INSTRUMENTATION
6.3.1 Temperature transmitters shall be included for all temperature sensors installed in heater. Temperature transmitter and
temperature sensor specification are clearly mentined in the requisition specification.
6.3.2 Pressure transmitter shall be included for pressure sensor installed in terminal box. Pressure transmitter specification is
clearly mentioned in the requisition specification.
6.3.3 Instrumentation Junction box shall be EExe certified, IP 66, suitable for hazardous area, SS316L, epoxy coated.
6.3.4 To be checked whether heater is controlled by Gas dehydration package LCP or FCS
6.3.5 Interface signals shall be decided as per P&ID diagram
6.4 STRUCTURAL
6.4.1 Weight & COG of heater shall be asked in company template
6.4.2 Detailed information on installation interface shall be asked to be indicated on GA
NOTES:
(i) The estimated cable entry size for heater side shall be informed to Bidders at bidding stage to get acceptance on the Ex "d" terminal box.
(ii) Number of stages are typically informed by Process. However, in case of LV heater, if the kW rating exceeds the maximum capability of the largest
MCCB used in the LV SWBD, the heater shall be electrically split into required number of stages.
(iii) If parallel heaters are being used, it shall be ensured that flowmeters/manual control valves are provided on individual heater piping to ensure uniform
flow distribution.
(iv) The heater shall be rated for base + spare capacity requirement. Spare electric elements shall be considered only as replacement in case of
failure of any running elements.
(v) Bite Coupling is not allowed as per UOP specification due to possibility of leakage. However, if welding is being used, cladding shall be done on the
non process end to avoid differential thermal expansion issued due to welding of dissimilar materials. (Since element is usually Incoloy 800 and
flange is Carbon steel)
(vi) This point is critical since changing the watt density has direct impact on the number of elements and shell size.
(vii) The regeneration gas heater for PETROBRAS projects shall comply with all the UOP requirements as specified in various points.
3 Of 3