Professional Documents
Culture Documents
EHS Requirements For Contracting Works
EHS Requirements For Contracting Works
Date: Time:
Project Title: Location:
Contractor/ Company Name: Representative:
General
The contractor undertakes university principles on “workplace and environmental
protection” place the highest priority on protecting the life and health of employees and
are aimed at preventing physical and psychological injury to persons while at work.
The contractor has examined the work site to identify any hazards and prepare risk
assessment/ job hazard analysis.
During Acutely Hazardous Situations, work shall be immediately suspended and the
hazard promptly eliminated. Work may not commence until all unsafe conditions have
been eliminated.
The contractors should provide AUC HSE Office at least a week before the work with a
list of all equipment / vehicles which will be used by his employees to perform the
contract terms.
Crane Operation, Hoisting and Pulling Tasks
Before using a mobile crane, the contractor must present the inspection certificate for
the crane as well as proof of qualification to perform crane and backstop work.
Cranes, Hoist, Forklift, Loader…...etc operated only by trained and authorized persons.
It is not permissible to use lifting tackle or load-bearing equipment that does not have a
load-capacity notice and visible and valid inspection sticker.
Persons in hoist able personnel lifting devices must be secured against falling by using
PPE.
1
Scaffolding and Ladders Work
The contractor shall be use an approval and acceptable scaffolding.
Any time scaffolding is not available for use -- in particular while being assembled,
disassembled or modified - the scaffolding shall be labeled at all access points and stairs
with “No Entrance”
All portable ladders used by contractor’s personnel must be in good working conditions
and equipped with ladder safety feet.
Electro-Technical Work
Equipment and supplies brought in by the contractor must be safe and tested and
comply with applicable statutory requirements.
The electrician-in-charge or the AUC may stipulate additional requirements and has
decision-making authority in all electro-technical matters. Instructions of the electrician-
in-charge relating to electrical safety shall be adhered to by all employees.
Hot Works
If hot work must be performed, a (supplement to work permit) must be obtained from
the HSE dept. and appropriate safety measures must be taken.
All conditions and limitations mentioned in the permit must be strictly followed by the
contractor’s personnel.
When performing welding work over gratings or on open platforms, fire-resistant covers
must be placed on the areas below where welding is being done. Flammable materials
shall be removed or properly covered (e.g. fire-control tarp).
The contractor shall secure all compressed gas cylinders to stationary object in an
upright position during use and storage.
2
Confined Spaces
When performing work in containers or confined spaces, special attention should be
given to the safety of personnel who are performing such work. Access authorization
with gas Test/analysis is required.
When performing work in containers and confined spaces and when working with
breathing apparatus, at least one watcher must be stationed outside the hazard zone.
The particular safety features of tools and equipment used in containers and confined
spaces shall be checked every time before work.
Excavation Works
The contractor shall obtain all underground utilities drawings to determine potential
interference in the vicinity of the excavation.
The excavation must be barricaded and these barricades should be equipped with
flashers to warn during night.
Chemical Materials
HSE should capture the chemicals inventory of the contractor.
Determine who has the authority to approve certain chemicals and what is allowed on
site.
Does contractor know Emergency Response Plans, Spill Response and hazardous waste
plans based on their site and inventory?
Contractor shall not dispose of any materials into AUC storm and / or sanitary sewers.
Transports
Drivers should be instructed prior to accessing the work site by vehicle.
Deliveries shall take place only during regular daytime work hours.
Routes used within the university and the sites shall be kept clear.
Contractor shall not park equipment / vehicles front of any fire hydrants and access
doors of buildings so as to cause congestion.
3
If reverse is necessary for operational reasons, it must be performed in such manner so
that it poses no hazard to people or things.
Contractors shall ensure that leftover materials, construction waste, rubbish, packaging,
etc. is promptly removed from their areas.
Unless otherwise agreed by contract, rules on waste logistics and disposal that apply to
the specific site facility or the site shall be applied.
Tools and Equipment
Tools and equipment shall be put away and stored securely after use.
All tools and equipment shall be turned off or otherwise rendered safe immediately at
the end of the work day as well as during break periods.
Personal Protective Equipment (PPE)
The contractor shall provide his employees with sufficient protective equipment and
clothing on the basis of the protective measures stipulated in the risk assessment.
Persons who lack PPE that accords with the regulations applicable to the university or
construction site (such as a safety helmet/safety shoes/safety goggles/etc.) may not
access the university and construction sites.
Safety Signs
All safety warning signs posted at different AUC locations (for example: No Smoking)
must be observed and obeyed by contractor’s personnel.
The contractor shall provide and install signs, barriers, etc. around work areas involved
overhead work. These items shall indicate overhead work and specify necessary caution
to be exercised in the area.
4
Emergency Cases
In case of any accident or injury to any of the contractor’s employees during his work in
AUC locations, the injured person may be provided with first aid medical treatment by
AUC clinic. Any further treatment required will have to be provided by the contractor.
Contractor should immediately report any accident occurred to AUC Safety Office (ext.:
4170/ 0226154170).
In case of fire in the area where the contractor is working, he should inform control
room immediately on telephone # 4170 or break the glass of any manual call points to
activate the sirens.
In case of emergencies, contractor’s employees must not move to the area where
emergency exists. If the emergency is in the areas where the contractor is working, he
should ensure that his employees move out of the critical area immediately to the
nearest designated point and none of his equipment is left obstructing access to the
area.