ML-01 Work Procedure For Row Survey

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Tolani Projects Private Ltd.

WORK PROCEDURE No.:


BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

PROJECT LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt. Ltd
Document Title PROCEDURE FOR ROW SURVEY

WORK PROCEDURE
FOR
ROW SURVEY
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
TPPL : Tolani Projects Pvt Ltd.
BPCL : Bharat Petroleum Corporation Limited
VCS : VCS QUALITY SERVICES PVT. LTD.
WP : WORK PROCEDURE
ML : MAINLINE

ISSUED FOR REVIEW

PURPOSE OF ISSUE PREPARED REVIEWED


REV DATE APPROVED BY
BY BY

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 1 of 6
Tolani Projects Private Ltd.
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


PROJECT
INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd..
Document Title PROCEDURE FOR ROW SURVEY

INDEX

1.0 SCOPE

2.0 REFERENCE

3.0 ABBREVIATIONS

4.0 RESPONSIBILITIES

5.0 METHODOLOGY

6.0 HEALTH, SAFETY&ENVIRONMENT

7.0 APPENDICES/FORMATS

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 2 of 6
Tolani Projects Private Ltd.
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


PROJECT
INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd..
Document Title PROCEDURE FOR ROW SURVEY
1.0 SCOPE
This document is intended to outline the procedure for carrying out pipeline centerline alignment survey for
the corridor in which the above pipelines are to be installed. The objectives of the pipeline route alignment
survey are as follows:

a. To collect information about the existing facilities, identify crossings and other details along pipeline
corridor.
b. To create individual drawings for proposed crossings.

2.0 REFERENCES
Following document shall in part or in totality form the reference document:

1. VCS Specification WOR/S/05/21/01 BPCL/VCS standard Technical


Specification Mainline Construction
(Onshore)
2. OISD STD 141 OISD Standard for Design &
Construction Requirements of
Hydrocarbon Pipeline
3. ASME B 31.8 ASME Standard for Design and
Construction of Gas Transmission &
Distribution Systems
4. Alignment sheet
3.0 BBREVIATIONS
AFC - Approved for Construction
ROU - Right of Use
ROW - Right of Way
IP - Intermediate Point
TP - Turning Point
TBM - Temporary Bench Mark

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 3 of 6
Tolani Projects Private Ltd.
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


PROJECT
INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd..
Document Title PROCEDURE FOR ROW SURVEY

4.0 RESPONSIBILITIES
Project Manager - Shall report to Head Office Project coordinator,
Client & PMC.
- Shall be responsible for control, supervision and
direction for implementation and execution of
construction plans using calibrated measuring and
test equipment’s.

Surveyor - Shall report to Project Manager.


- Preparation of schedule addressing specific issues
and characteristics of each spread.
- Generates reports and records data .
-
Checks and verifies the activity

HSE Officer - Reports to Site Project Manager.


- Manages the implementation of all safety
requirements during operations.
5.0 METHODOLOGY
5.1 EQUIPMENT
• Theodolite (Dumpy)
• Auto Level
• Total Station/DGPS
• 30 Mtrs Measuring Tape -steel
• Ranging Rod
• 5 Mtrs Staff-steel

5.2 PRE-CONSTRUCTION SURVEY

As a part of pre-construction survey to be carried out prior to start of the construction activities, based on
the Approved for Construction (AFC) Alignment Sheet issued by PJPL / VCS to the Contractor, the
pipeline trench center line, the extent of the ROU shall be identified and marked using the following

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 4 of 6
Tolani Projects Private Ltd.
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


PROJECT
INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd..
Document Title PROCEDURE FOR ROW SURVEY
method:
6.2.1 The Intermediate Points (IPs) and Turning points (TPs) shown in the AFC alignment sheet shall be
physically located and marked using theodolite and ranging rod.
6.2.2 Wooden pegs shall be fixed at turning points and at 100 Mtrs. on either side of ROW.
6.2.3 Center line of pipeline shall be demarcated by stacking of wooden pegs at an interval of maximum
100 Mtrs for straight-line sections and maximum 10 Mtrs for horizontal bends and turning points.
6.2.4 Markers in the form of wooden pegs shall be placed on the reference line be at a distance of max 100 Mtrs
for straight line section maximum 10 Mtrs for horizontal bend.

5.3 STAKING OF PIPELINE ROUTE


In addition, the Contractor shall stake wooden pegs at a regular interval of 100 meters minimum duly
marked for easy identification with name of pipeline, progressive pipeline chainage with yellow paint on
base color of red. The staking shall be on the edge of ROU.
The markers are also to be installed at every turning point, and on both sides of all road, river, rail and canal
crossing etc.

5.4 BENCH MARKS


Benchmarks have been installed by PJPL designated survey agency agency as part of route alignment
survey. Using such bench marks, temporary bench marks shall be established at every 5 Kms preferably on
some permanent structure in close vicinity to the pipeline ROU. The bench mark should be painted and
marked for easy identification as in the case of marker stone.

6.0 HEALTH, SAFETY & ENVIRONMENT


The approved procedure for health, safety and environment shall be followed during execution.

1 PPE is a must in this activity.


2 All Measuring & Test Equipment used must be well maintained.
The control of Health, Safety and Environment hazards shall be governed by documents viz. First Aid
Practices, Environment Control Procedure and Occupational Health and safety practices.

7.0 APPENDICES / FORMATS

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 5 of 6
Tolani Projects Private Ltd.
WORK PROCEDURE No.:
BPCL-VCS-TPPL-PJPL-299-ML-01
PROCEDURE FOR ROW SURVEY

LAYING OF ATF PIPELINEFROM BPCL PIYALA TERMINAL TO JEWAR


PROJECT
INTERNATIONAL AIRPORT (14” x 32 Km approx.)
OWNER Bharat Petroleum Corporation Limited
EPMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd..
Document Title PROCEDURE FOR ROW SURVEY
Inspection and Test Plan BPCL-VCS-TPPL-PJPL-299-ML-01/ITP-01 Rev-01

Inspection Report BPCL-VCS-TPPL-PJPL-299-ML-01/IR-01 Rev-01

DOCUMENT NO. REV. SHT.


PROCEDURE FOR ROW SURVEY
BPCL-VCS-TPPL-PJPL-299-ML-01 00 6 of 6
INSPECTION REPORT ROUTE SURVEY
DOC NO:- BPCL-VCS-TPPL-PJPL-299-ML-02/IR-01

PROJECT
LAYING OF ATF PIPELINE FROM BPCL PIYALA TERMINAL TO JEWAR
INTERNATIONAL AIRPORT (14” x 32 Kms)
OWNER Bharat Petroleum Corporation Limited.
PMC VCS QUALITY SERVICES PVT. LTD.
CONTRACTOR Tolani Projects Pvt Ltd.
From: Report No.:
To: Date:
Section: Alignment Sheet No.:

Chainage
Sr.No. Section Length Terrain Remarks
From To

Turning Point Details with Chainage and Bearing / Deflection Angle

Sr.No. TP/IP Chainage TP/IP No. Bearing / Deflection Angle Remarks

Details of Structure/ Monuments In / Across ROW such as Pipeline, HT Line etc. & Restricted ROW
Name of Structure Chainage Details

PROGRESS
PREVIOUS TODAY CUMULATATIVE

For TPPL For VCS/BPCL

Sign: Sign:
Name: Name:

Date: Date: