Professional Documents
Culture Documents
Chapter 3 G1
Chapter 3 G1
CONSTRUCTION
PRE- PLANNING
3-1 PLANNING
▪ Planning is a n art, a nd art of
planning exist only among human
beings .
1 . O W N E R S O F T H E C O M PA N Y. w h e n w e
plan to achieve a profit by operating at the
m i n i m u m c a p a c i t y, u t i l i z i n g t h e a v a i l a b l e
resources.
2 . E M P L O Y E E S . We p l a n t o c r e a t e o r m a i n t a i n
jobs.
3.1 PLANNING
FOUR DIMENSIONS:
1. Planning is a philosophy.
2. Planning is integration .
3. Planning is a process.
4. Planning is a collection of
procedures .
3-2 THE PROJECT MANAGER
a. Job offices
b. Storage sheds
c. Workshops
d. Roadway, etc.
c. Bank house for workers and facilities.
The layout of these
structures should be
planned carefully, in The job should be
anticipation of its removal adequate, but not
during the excavation of excessively staffed, to
the permanent works more ensure efficient execution
particularly, the storage of the work. Large
and its contents which construction needs
might cause competent foremen. The
disorganization and delays. contractor must be
selective in sending men
of proven ability and
qualification to start the
work even if they are
replaced later by selected
personnel engaged locally.
The construction site should
be maintained in strict and
in an orderly routine
because it has a
psychological effect on the
staff and workers, which
promote conscientious
service. Remember that the
owner would like to see the
actual work getting under
way in its fullest operation
and orderliness.
● In carrying out the construction work, idle time and
unnecessary cost should be avoided. Time saving
devices such as telephone, loudspeakers, signal
posts, traffic control sign board location and other
economy measures should be installed
immediately upon commencement of the work.
Before the work get started, it should be first
established from which the buildings may be
demarcated on the ground.
The excavator with his equipment
should start cleaning, stripping and
digging operations. Material deliveries
should also start as soon as possible
and a labor force started the
excavation for the foundation work,
etc. If all these operations get under
way without undue delay, the job will
have a healthy aspect, high morale and
satisfaction of all concerned from the
owner to the contractor and down to
the lowly laborers.
The contractor should procure sufficient copies of
the plan and specification to distribute among his
supervisory staff. This will thoroughly acquaint
them with the details of the job. Likewise, the sub-
contractors and consultant should be furnished
with the plans and specifications so that, there is no
excuse for mistake and delay on this account.
PRELIMINARIES IN ORGANIZING A CONSTRUCTION JOB
Building Execution of
Permit must major
beSecure activities
1. Planning
A use of labor, materials and time. The organization of the work is the
responsibility of the contractor under the direction of the supervising
Architect or Engineer.
D Each has their own duties to perform in the interest of their employer
- the owner. Most of their respective duties and responsibilities were
stipulated and defined in the contract, and all will be better exercised
if each one appreciates the duty and responsibility of the other.
ORGANIZATION OF WORK
The Engineer or Architect on behalf of the owner is also
responsible for the following duties:
1. As representative of the owner
a. Act as interpreter of the plan
b. As guardian and arbiter between the owner and contractor.
2. Maintain site records and documents like:
a. Layout plans
b. Contract documents
c. Time and progress chart
d. Work diary
ARCHITECT e. Contractor’s order book
f. Records of tests
g. Progress report
h. Measurement book, etc.
ORGANIZATION OF WORK
The contractor is generally responsible to the owner for the following
duties:
1. Providing and making access roads with due regards to the
convenience of construction.
2. Erection of site office in a central position to facilitate checking of all
site activities
3. Erection of store shed of adequate capacity to ensure,
a. Protection of materials against damage
b. Protection of materials against deterioration
c. Prevent materials from wastage and pilfering
1. Construction of temporary quarters and ancillaries for labor with due
regard to site of works, amenities and hygienic conditions
2. Appointment of supervisory staff processing technical knowledge
CONTRACTOR and capable of controlling the work and labor.
3. Early arrangement for construction equipment, i.e.
a. Scaffolding d. Ladders
b. Formworks e. Tools
c. Instruments and machinery with necessary screw, fuel and parts etc.
PLANNING AND PROGRESS CHART
The most important part of the works organization are:
1. The preparation of a comprehensive time and progress chart for the execution of the work.
2. The periodic revision of the chart as circumstances demand, and the regular comparison of
progress chart made with the program.
The project manager is required to prepare an approved time and progress chart, which is
generally part of the main contract documents:
1. The time and progress that must show an analysis of the chief elements and types of
construction involved in the project.
2. The scheduled dates of commencement and completions of every stage of the main
contract and of sub-contracts.
Without proper program, the construction work can be disorderly managed. The time and
progress charts serves as the coordination and control of all the work under the different
subdivisions of the contract. With this time and progress chart it is easy to pinpoint where the
delay has occurred, and who is responsible for the delay.
Likewise, because of a clear definition of the dates, all parties concerned have to assume their
tasks making much easier for the contractor to finish the job on time.
Besides of being the standard requirement, the chart, automatically shows and offer the
following information:
1. The sequence of operations
2. The target time and date for their completion
3. The rate of which they must be carried out
4. The owner’s staff and the contractor's staff should be familiar with the information given in
the chart and should constantly strive to carry out the work according to the projected rate
of accomplishment.
5. If some operations are to be done by sub-contractors, they should be notified in advance
and given a clear understanding of what exactly is expected from them.
6. The chart also tends to prevent changes in design and layout with consequent delays and
increased in cost. it also provides essential information regarding labor, materials and plant
requirements.
MAINTAINING TIME AND PROGRESS CHART
The making of time and progress chart is a matter of trial and error. It requires
consideration of alternative methods ang the effect of each event, resulting in an orderly
arrangement of event and an ultimate savings of time and cost.
The chart is divided into many horizontal spaces as are required for the major operations
of the job. The vertical columns provide space for:
The target dates for buying materials should be worked back from the starting date and time
allowance for the operations requiring shop drawings and fabrication. The progress is shown in green
color for on time, and red for behind schedule.
The ideal chart shows the progress line green throughout the contract period. On large project, a
separate chart is provided showing a date of delivery and a date of using up of all principal
materials and laborers of each category employed on the main contract and of the sub-contracts.
The time and progress charts we kept up to date so that when the Owner or the Engineer visit the site,
they could see a true comparison between the actual progress against the scheduled program.
Within the first week of each month, the contractor shall forward to the engineer or architect a
progress report showing particulars of the work done in workshop and on the site, also giving the
present position, the rate of progress, estimated time of completion and hold-ups for the delay if any.
e those in-charge of the work to see the effect of the contingency. It will be on subsequent operations
and to make the necessary adjustments to bring the program back into line.
3-9 PLANNING AND SCHEDULING WITH GANTT CHART
▪ Gantt chart is a tool used for planning and scheduling simple projects.
▪ To prepare the chart, the project manager has to identify the major
activities that would be required. Estimates for each activity are made
and the sequence was determined. Once completed, the chart indicates
which activities were to occur including their planned duration, and
when they were to occur.
3-10 MATERIAL SUPPLY
2. Quantities required
4. Unit price
5. Amount
◦ The purchasing clerk of the contractor must have experience in identifying
the variety of materials and supplies in general demand for construction work
including the trade names, the quality and the local practices that govern the
prices.
3-11 FINANCIAL AND BUDGETING
1. The static or fixed budget - this type of budget depends upon the ability to
predict income with at least a reasonable degree of accuracy.
- A fixed sum of money is allocated for expenditures with
a fixed budget of operations for a specified period.
2. The variable or flexible budget – this type of budget recognizes the unreliability
of income prediction and make provisions in advance for variations in
construction expenditures in accordance with variation in income.
- Variable budget is constructed in anticipation of variables
income. It provides advance for orderly change in the volume of construction and
expenditures.
▪ Fixed Cost - is one that is constant in total amount for a given period.