Professional Documents
Culture Documents
Compex Engineering Problem-F.Karim
Compex Engineering Problem-F.Karim
Compex Engineering Problem-F.Karim
TECHNOLOGY PESHAWAR
Department of Civil Engineering
TRANSPORTATION ENGINEEIRNG - II
Batch - 2020
Semester: 7th Last Date of Submission: March 5, 2024
Examination: Complex Engineering Problem Total Marks: 8
Course Learning Objective: 3 Learning Level: 5
Name of Student: ID:
Prepare Marshall Mix Design for asphalt mix confirming the following gradation:
Sieve Size 1 inch ¾ inch 3/8 inch #4 #8 #50 #200 pan
% Passing 100 90-100 56-70 35-50 23-35 5-12 2-8 -
Objective:
The main objective of this CEP is to guide the students about the Marshall Mix
Design to choose the best compatible amount of aggregates and bitumen for Hot Mix
Asphalt.
Activities:
Main activities of the problem are:-
Aggregate sample collection from Malakand quarry of KP
Carrying out Mix design Calculations
Laboratory analysis of the sample
Proposing final aggregate blend and optimum bitumen content
Submission of the final report