SECTION C : VALVES

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
SHIP’S SIDE OVERBOARD & SEA VALVES
Hot Work No Staging Yes Job Code C.1
Gas Freeing No Heavy Lift No

Ventilation No Access Removal Yes Steel Kgs


Cleaning Yes Lighting Yes Class Yes

Confliction with other jobs Completed

C.1 The valves listed below are to be opened up for examination, seats and discs ground
together, internals scraped clean and coated with “Apexior”) and repacked glands
where applicable.

On completion of all works the valves are to be surveyed by Class and owners
representative.

The valves to be replaced with new jointing and closed in the presence of the vessel’s
Chief engineer and /or owners’ representative.

During flooding of the dry dock, flooding is to be suspended one (1) foot before the
vessel leaves the blocks and all overhauled sea valves opened to the satisfaction of the
Chief engineer, on verification of valve operation flooding can be recommenced.

Costs to include materials and all necessary access/side works.

3 meters staging tower costs to be included for port & starboard midships draft valves in
No 3 ballast wing tanks.

Butterfly valves over 300mm diameter to be inspected using cherry picker from the dock
side without dismantling. Butterfly valves under 200 mm diameter to be dismantled for
inspection.

DESCRIPTION SIZE SITE TYPE PRICE

DRY - DOCK SPECIFICATIONS 2018


E/R Low Suction 550 x 10K ER S.L
E/R High Suction 550 x 10K ER B/Fly
E/R Low Suction Vent 25 x 10K ER S.L
E/R High Suction Vent 25 x 10K ER S.L
ER High sea chest steam blow valves 2x (25x10k) ER S.L
ER Low sea chest steam blow valves 2x (25x10k) ER S.L
GS/Fire Pump O/B 200 x 10K ER S.L
IG Scrubber O/B 300 x 10K ER B/Fly
Auxiliary Condenser O/B 400 x 10K ER B/Fly
Atmospheric Cond O/B 300 x 10K ER B/Fly
HT/LT Cooler O/B 200 x 10K ER B/Fly
Evaporator Eductor O/B 150 x 10K ER B/Fly
Bilge OWS O/B 60 x 10K ER Gate
Auxiliary Boiler Blowdown O/B 40 x 16K ER S.L
Composite Boiler Blowdown O/B 40 x 16K ER S.L
Aft Hydraulic CW O/B 50 x 10K ER S.L
Emergency Fire Pump Suction 200 x 5K SG S.L
Aft Draught Gauge 50 x 10K ER Gate
Storm Valve for Waste/Galley x 2 100 x 5K ER Storm
Storm Valve for Waste/Galley x 2 100 x 5K ER Storm
Ballast pump susction 700 x 10K PR B/Fly
Ballast Sea Chest Vent 65 x 10K PR B/Fly
Ballast Sea Chest Blow Valve 25 x 10K PR S.L
Cargo pump suction (Portside OCIMF press 550 x 10K PR B/Fly
test)
Cargo pump suction air vent 65 x 10K PR S.L
Cargo pump suction blow valve 25 x 10K PR S.L
Ballast O/B port (remove for access + 550 x 10K PR N.R
spool)
Ballast O/B Stbd (renew the SS bolts) 550 x 10K PR B/Fly
Deck seal O/B 50 x 10K PR B/Fly
Midship Draught Gauge x 2 50 x 10K BT Gate-(staging
3m)
Forward Draugth Gauge 50 x 10K FP Gate
Forward Hydraulic CW O/B x 2 40 x 10K Fclse S.L
Forward Eductor O/B 65 x 10K Fclse S.L
After Peak Tank V/V 150 x 5K APT B/Fly double

DRY - DOCK SPECIFICATIONS 2018


flanged
F.W.G Ejector Suction x 2 125 x 5K PR B/Fly double
flanged
F.W.G Ejector Discharge x 2 125 x 5K PR Globe V/V
F.W.G Ejector By Pass 125 x 5K PR B/Fly Wafer
Main Cooling SW Suction 300 x 5K PR B/Fly double
flanged
Main Cooling SW Discharge 300 x 5K PR Globe angle
V/V
Main C.O.P.T Cond. Suction 400 x 5K PR B/Fly double
flanged
Main C.O.P.T Cond. Discharge 400 x 5K PR Globe angle
V/V
C.O.P.T Cond Suction 450 x 5K PR B/Fly double
flanged
C.O.P.T Cond Discharge 450 x 5K PR Globe angle
V/V
C.O.P.T Cond Em’cy bilge suction 450 x 5K PR Globe angle
V/V
Sea Chest Intermediate 550 x 5K Sea B/Fly Wafer
Chest

INTERNAL VALVES
DESCRIPTION SIZE SITE TYPE PRICE
Low suction intermediate 550 x 10K ER B/Fly
High suction intermediate 550 x 10K ER B/Fly
Condenser SW pump Suction x 2 400 x 10K ER B/Fly
Main SW cooling pump suction 400 x 10K ER B/Fly
Main SW cooling pump discharge 400 x 10K ER NR
Evaporator Eductor Suction 300 x 10K ER B/Fly
GS /Fire pumps No 1 Suction x 2 200 x 5K ER Globe angle
GS /Fire pumps No 1 Suction x 1 150 x 5K ER Globe angle
GS /Fire pumps No 1 Discharge x 2 200 x 10K ER Globe angle

DRY - DOCK SPECIFICATIONS 2018


GS /Fire pumps No 1 Discharge x 1 200 x 10K ER Globe angle
GS /Fire pumps No 1 Discharge x 1 150 x 10K ER Globe angle
GS /Fire pumps No 2 Suction x 2 200 x 5K ER Globe angle
GS /Fire pumps No 2 Suction x 1 150 x 5K ER Globe angle
GS /Fire pumps No 2 Discharge x 3 200 x 10K ER Globe angle
GS /Fire pumps No 2 Discharge x 1 200 x 10K ER Globe angle

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
OVERBOARD VALVE STUB PIPES
Hot Work No Staging No Job Code C.2
Gas Freeing No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs Completed

C.2 UTI Thickness gauging to be carried out on following ships side stub pipes:

1 Port & starboard main sea suction


2 Eng. Room High suction
3 Ballast pump suction
4 Inert gas scrubber overboard
5 Sewage overboard x 2
6 Bilge/OWS overboard
7 Boiler blow down x 3 (P&S Aux boiler & Composite boiler)
8 Deck seal overboard.
9 Fire & GS overboard
10 Galley waste storm valve fwd
11 Atmospheric Condenser/LT Cooler overboard
12 HT Cooler overboard
13 Aft hydraulic power pack
14 COPT/Ejector overboard
15 FW Evaporator overboard
16 Port & Stbd Storm overboard
17 Steam injection valves for seachest box port and stbd

Allow for up to 5 points per stub.

UTI to be contacted from Owner’s representative firm and handed over to Owner’s
representative on completion – any stubs to be renewed will be advised. Quote minimum
price for UT reading per additional site and number of included readings.

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
ER INBOARD VALVES
Hot Work No Staging No Job Code C.3
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs Completed

C.3 Standard prices to be given for opening & closing the following various sizes & types
of valves as per C.1.

DETAILS (MAKERS/TYPE/SIZE)
Valve Size/Type

Low sea water suction intermediate 5k/550A butterfly

High sea water suction intermediate 5k/550A butterfly

Main sea water pump suction 5k/400A butterfly (anti corrosion flange fitted)

COPT/Main sea water pump suction 5k/400A butterfly (anti corrosion flange fitted)

COPT sea water pump suction 5k/450A butterfly (anti corrosion flange fitted)

Fresh water ejector sea water suction 5k/125A butterfly (2)

Fresh water ejector sea water discharge 5k/125A Globe (2)

Fresh water ejector sea water by pass 5k/125A butterfly wafer

Fire/GS pumps suction 5k/200A SL (4)

Fire/GS pumps suction 5k/150A SL (2)

Fire/GS pumps discharge 10k/200A Globe angle (5)

Fire/GS pumps discharge 10K/200A Globe (2)

Fire/GS pumps discharge 10K/150A Globe angle

DRY - DOCK SPECIFICATIONS 2018


IG Scrubber tower supply pump suction 5k/150A butterfly

IG deck seal pump suctions 5k/50A Globe SD

IG deck seal pump discharge 5k/50A Globe SD

Main sea water pump discharge 5k/300A Globe SDNR

COPT/Main sea water pump discharge 5k/400A Globe SDNR

COPT sea water pump discharge 5k/400A Globe SDNR

IG Scrubber tower supply pump discharge 5k/200A Globe SDNR

O.W.S sea water suction 5k/50A Globe SDNR

L.T. cooler inlet/outlet/bye-pass 5k/250A B/fly. (8)

HT Cooler inlet/outlet/bye-pass 5k/200A B/fly. (2)

Emergency fire pump foot valve 10k/125A Globe NR

Bilge Emergency Suction SDNR NB300

Total 44 Valves

UNDER NO CIRCUMSTANCES IS BURNING AND/OR HEATING EQUIPMENT TO BE USED WHEN


REMOVING ANY OF THE VALVE FLANGE NUTS AND BOLTS.

VALVES HAVE VULCANISED INTERIOR

DRY DOCK REPAIR SPECIFICATIONS


STEAM VALVES OVERHAUL

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging No Job Code C.4
Gas Freeing Required No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs Completed

C.4 JOB SCOPE:

1. Valves to be opened for examination and machining as necessary. Allow for


machining all valve lids and seats. After machining, valves to be lapped.
2. Valve gland studs to be renewed, each valve 2 pc M16 x 100mm.
3. Allow for renewal of packing and jointing with yard supply approved packing and
jointing.
4. Before refitting, valves to be hydraulically tested to satisfaction of C/E in yard
workshop.

FOLLOWING VALVES TO REMOVE < DISMANTLE AND OVERHAUL:

 16 kg/cm2 Range / reducing station and IG Steam dump IN/OUT/Bypass valves (6


Off)

6 off Globe valves 125 NB. To be removed to workshop for full overhaul

 6 kg/cm2 Range inlet and Outlet and Bypass valves (3 off)

3 off Globe valves 50 NB. To be removed to workshop for full overhaul

 10 kg/cm2. Steam valves for FO heaters (6 Off)

NB 25mm Globe Valves (Bronze)

 16 kg/cm2 Cargo steam master and warming through valves (2 off)

1 SL Globe valve 250 NB, 1 SL Globe valve 15 mm NB

 Cargo Pump Valves 20k 125/250A globe valves (4 off)

Cargo pump steam inlet valves, 3 off. 20k/125A globe type.

Cargo pump master steam inlet valve, 1 off. 20k/250A globe type.

DRY - DOCK SPECIFICATIONS 2018


Reducing: 16Kg to 6Kg 20K 50 Globe valve (2)

Reducing: 16Kg to 6Kg 20K 50 By pass Globe valve.

DRY DOCK REPAIR SPECIFICATIONS


PUMP ROOM BALLAST VALVES

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging No Job Code C.5
Gas Freeing Required No Heavy Lift Yes
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class Yes
Confliction with other jobs Completed

C.5 Ballast valves:


 BA 023 (NB 650) Main ballast suction valve
 BA 024 (NB 650) Main ballast suction valve
 BA 025 (NB 500) Ballast System Valve
 BA 026 (NB 500) Ballast System Valve
 BA 027 (NB 500) Ballast System Valve
 BA 028 (NB 500) Ballast System Valve
 BA 029 (NB 650) Sea chest return valve
 BA 030 (NB 650) Sea chest suction valve
 BA 033 (NB450) Ballast System Valve
 BA 034 (NB450) Ballast System Valve
 BA 035 (NB 650) Main ballast O/B
 BA 037 (NB 200) Ballast System Valve
 BA 038 (NB 150) Ballast System Valve

Above valves are to be removed for overhaul.

Allow for the following repairs to “Hanil Hydraulic” butterfly valves generally:

 Valve Butterflies to be set up in a milling machine for dressing up.


 Butterflies to be built up with welding where corroded and ground back to fit.
 SS guide pins and nuts to make on account of missing/broken parts.
 Butterfly valves to strip down in the workshop and fit new Owners supplied rubber
linings.

DRY - DOCK SPECIFICATIONS 2018


 Allow to build up the bridge pieces with weld before machining to standard as well as
welding up the spindle end pockets. Allow for grit blast or hydro blast internals of the
valve body and re coating with epoxy.

DRY DOCK REPAIR SPECIFICATIONS


PUMP ROOM BALLAST AND COT SYSTEM NON RETURN VALVES

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging No Job Code C.6
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class Yes
Confliction with other jobs Completed

C.6 Cargo / Ballast / Eductor: Non Return valves pump-room

Contractor to quote tariff rate for overhaul of following non-return valves:


Item No 1: Three (3) Cargo pump non-return valves
Cargo Pump N.R valves x three (3)
Valve bore 450mm 600mm
Flange: JIS16K

Item No 2: Ballast pump discharge N.R valves x Two (2)


Valve bore 450mm
Flanges: JIS16K

Item No 3: Ballast Eductor


Valve Bore 200mm
Flanges: JIS10K

Item No 4: Cargo stripping eductor x two (2)


Valve bore 250mm
Flanges: JIS16K

Item No 5: Water ballast overboard discharge


Valve bore 650mm
Flanges: JIS5K

DRY - DOCK SPECIFICATIONS 2018


Work-Scope:
a) Removal of the discharge N.R flap valve from associated pipe work Standard JIS
pressure rated flanges x two (2).

b) Cleaning of valve, transportation to shore and inspection by nominated member of


ship’s staff.

c) Allow for welding of 3 x 50mm diameter x 5mm deep pits. Surface grinding and mech.
Preparation ST2.

d) Coating of valve with two coats (2 x 150 microns) of owner supplied paint. Allow for
0.5m2 coating repair.

e) Reassembly of valve complete and refit on board complete with gaskets, nuts and
bolts.

f) Leak test after reassembly to be witnessed by nominated member of ship’s staff.

g) Transportation / reinstallation on board.

Cargo valve casing coating: Coal tar epoxy coating.


Ballast pump valve casing: Pure epoxy.
Contractor to supply all nuts, bolts and pressure rated oil resistant asbestos free gaskets
as per flange standard requirements.
All transportation and Cranage to be included within quotes.

BERNHARD SCHULTE SHIPMANAGEMENT CYPRUS LTD

CARGO TANK VALVE OVERHAULS

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging 5 m3 Job Code C.7
Gas Freeing Required No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting Yes Class
Confliction with other jobs Completed

C.7 Cargo System Valves in Cargo tanks to be overhauled.


Allow to remove:
8 x 500 NB Butterfly Valve Fill / Suc from COT 1 To COT 8

8 x 200 NB Butterfly Valve Fill / Suc from COT 1 To COT 8


4 x 500 NB Butterfly Valve Group Iso into COT 3
2 x 300 NB Butterfly valves Fill / Suc from Slop Port

1x 500 NB Butterfly valves Gravity Tranf

Total 23 Valves

Valves to be landed to shore workshop and stripped down for inspection. All parts to be
cleaned.
Allow removing and replacing valve rubber seat with new spare (owners supply).

On completion of overhaul, each valve to be blanked and pressure tested to rated


pressure (16 Bar).

Valves to be fitted back with all new gaskets and nuts/bolts as required.

Spares to be supply by owner.

DRY DOCK REPAIR SPECIFICATIONS


WATER BALLAST TANK VALVES OVERHAULS

DRY - DOCK SPECIFICATIONS 2018


Hot Work Staging 5m3 Job Code C.8
Gas Freeing Required Heavy Lift
Ventilation Access Removal Yes Steel Kgs
Cleaning Yes Lighting Yes Class
Confliction with other jobs Completed

C.8 Ballast System Valves in WB tanks to be overhauled.

Allow to remove:
11 x 300 NB Butterfly Valve Fill / Suc FPT to WBT 5
10 x 150 NB Butterfly Valve Fill / Suct. From WBT 1 to WBT 5.

Total 21 Valve

Valves to be landed to shore workshop and stripped down for inspection.

Allow to remove and replace valve rubber seat with new spare (owners supply).

On completion of overhaul, each valve to be blanked and pressure tested to rated


pressure (5 Bar).

Valves to be fitted back with all new gaskets and nuts/bolts as required.

DRY DOCK REPAIR SPECIFICATIONS


PUMP ROOM CARGO VALVES
Hot Work No Staging 5 m3 Job Code C.9

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting Yes Class
Confliction with other jobs Completed

C.9 Cargo System Valves in Pump Room to be overhauled.


Allow to remove the following valves:
 3 x 450 NB Butterfly Valve from COP’s discharge (OP 224, OP 225, OP226)
 1 x 450 NB Butterfly Valve from oily water main iso (OP 273)
 1 x 100 NB Butterfly Valve from Stripping Pump (OP 214)
 2 x 500 NB Butterfly Valve from sea chest (OP 246,OP245)
 3 x 500 NB Butterfly Valve from Main line Iso (OP 206, OP 205 OP 204)
 3 x 450 NB Butterfly Valve from Oily water disch (OP 227, OP229, OP231)

Total 12 Valves.

Actuator to be overhauled:

Valve : OP 225 , OP 227, OP232

Valves to be landed to shore workshop and stripped down for inspection.


Allow removing and replacing valve rubber seat with new spare (owners supply).
On completion of overhaul, each valve to be blanked and pressure tested to rated
pressure (5 Bar).
Valves to be fitted back with all new gaskets and nuts/bolts as required.

DRY DOCK REPAIR SPECIFICATIONS


MAIN STEAM SUPPLY AND CONDENSATE RETURN VALVES ON DECK
Hot Work No Staging No Job Code C.10

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.10 Allow for dismantling and removal to workshop for inspection and overhaul of Main
Steam Valve and Condensate Return Valve on Deck.
 Main Steam Valve= 10K-250 (HC-161)
 Condensate Return Valve= 5K-125 (HC-162)
 Valve Type= Globe
 Valve Connection Type= F
 Material Body= SC / SEAT= SC

Allow for removal of 24 x M16 from Main Steam Valve and 16 x M12 from Condensate
Return Valve. Pressure Test must be carried out at 15Bar and certified by Vessel’s SI or
Representative. After job completion both valves must be given 1 coat HT silver steam
pipe paint (owner’s supply) and renewed all gaskets and new galvanized bolts/nuts used.
RETURN VALVE SUPPLY VALVE

DRY DOCK REPAIR SPECIFICATIONS


DECK SEAL INERT GAS ISOLATION VALVES
Hot Work No Staging 3m3 Job Code C.11

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C. 11 Inert Gas Isolating Valves to overhaul. (Hanil Lever type wafer valves) fitted to deck seal
outlet, aft main deck.

DETAILS (MAKERS/TYPE/SIZE)
400mm Wafer Type Butterfly.
Allow for the removal of total 36 x m24 bolts/nuts.
Allow for the removal of 3 valves from site to shore workshop.

Following work to be completed for each valve:


1) Valve and Gear box to be opened up for examination.
2) If necessary valve body seal to be renewed, Ships Supply.
3) Gear box parts to be cleaned, re-assembled, greased and proved free to operate.
4) Valve gland studs to be renewed, 2 off. Each approx. M16 thread x 60 mm long, carbon
steel.
5) Valve flange bolts to be renewed. Allow for total 36 x M24 thread x 150 mm long carbon
steel bolts with nuts.
6) Allow for the renewal of all flange joints with ships approved jointing - Klinger.
7) Allow for the renewal of valve stem packing, allow for approx. 500 mm of 10mm section
ships approved packing - Klinger.
8) Valve to be tested using cold hydraulic to working pressure as follows -
A) Valve body complete including valve stem packing,
B) Integrity between butterfly valve and seat.
C) Pressure test to 1 bar hydraulic, to be witnessed by ships staff.

DRY DOCK REPAIR SPECIFICATIONS

DRY - DOCK SPECIFICATIONS 2018


IG INLET ISOLATION VALVES TO COTS
Hot Work NO Staging 25m3 Job Code C.12
Gas Freeing NO Heavy Lift NO
Ventilation NO Access Removal NO Steel Kgs
Cleaning NO Lighting Class
Confliction with other jobs Completed

C.12 Inert Gas Isolating Valves to overhaul due excessive leakage.

Location: Main Deck

Site
Aft main deck at Deck Seal outlet.

Details (Makers/Type/Size)
400mm Wafer Type Butterfly x 3

Access
Open access

Job Aids/Equipment
Lighting gear, approx. weight 30kgs.

Connections
All flanges
Allow for the removal of total 36 x m24 bolts/nuts.

Tests
Visual examination during repair.
Pressure test to 1 bar hydraulic, to be witnessed by ships staff

Repair Description
Allow for the removal of 3 valves from site to shore workshop.
Following work to be completed for each valve -:
Price for Staging (25 m3)
Butterfly Valves
1. Valve and Gear box to be opened up for examination.
2. If necessary valve body seal to be renewed, Ships Supply.

DRY - DOCK SPECIFICATIONS 2018


3. Gear box parts to be cleaned, re-assembled, greased and proved free to operate.
4. Valve gland studs to be renewed, 2 off. Each approx. M16 thread x 60 mm long,
carbon steel.
5. Valve flange bolts to be renewed. Allow for total 36 x M24 thread x 150 mm long
carbon steel bolts with nuts.
6. Allow for the renewal of all flange joints with ships approved jointing - Klinger.
7. Allow for the renewal of valve stem packing, allow for approx. 500 mm of 10mm
section ships approved.
8. Packing - Klinger.
9. Valve to be tested using cold hydraulic to working pressure as follows:
a. Valve body complete including valve stem packing.
b. Integrity between butterfly valve and seat.

All transportation and carnage to be included within quotes

DRY DOCK REPAIR SPECIFICATIONS


MANIFOLD STRIPPIN GVALVES

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging No Job Code C.13
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.13 Allow to remove and overhaul 6 pieces of butterfly valves NUMBER S (OD
314,315,316,317,318,319), ND 125mm, JIS16K wafer type.

Following work to be completed for each valve:


1) Valve and Gear box to be opened up for examination.
2) If necessary valve body seal to be renewed, Ships Supply.
3) Gear box parts to be cleaned, re-assembled, greased and proved free to operate.
4) Valve gland studs to be renewed.
5) Valve flange bolts to be renewed. Allow for total 6 x M24 thread x 150 mm long
carbon steel bolts with nuts.
6) Allow for the renewal of all flange joints with ships approved jointing - Klinger.
7) Allow for the renewal of valve stem packing.
8) Valve to be tested using cold hydraulic to working pressure as follows:
A) Valve body complete including valve stem packing,
B) Integrity between butterfly valve and seat.
Pressure test to 1 bar hydraulic, to be witnessed by ships staff.

DRY DOCK REPAIR SPECIFICATIONS

DRY - DOCK SPECIFICATIONS 2018


MANIFOLD DRAIN VALVES
Hot Work No Staging No Job Code C.14
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.14 Allow for removal of 2 pieces of Manifold drain valves for overhaul or change if it is
require, after condition check inform superintendent if require the change.
Valves numbers OD 322,323.

Details (Makers/Type/Size)
Type globe valve, ND50mm, JIS16K, MODEL JIS F 7309.
Allow for the removal of total 32 bolts/nuts and renew.
Allow for the removal of 2 valves from site to shore workshop.
Following work to be completed for each valve -:
1) Valve to be open up for examination. Top flange 8Xm12 studs to remove
2) Seat to be grinding with the spindle seat.
3) Screw down stem to be overhaul.
4) Valve gland studs to be renewed, 2 off. Each approx. M12 thread x 60 mm long, carbon
steel.
5) Valve flange bolts to be renewed. Allow for total 32 x M16 thread x 90 mm long carbon
steel bolts with nuts.
6) Allow for the renewal of all flange joints with ships approved jointing - Klinger.
7) Allow for the renewal of valve stem packing approved packing - Klinger.
8) Valve to be tested using cold hydraulic to working pressure as follows:
A) Valve body complete including valve stem packing,
B) Integrity between valve and seat.

Pressure test to 1 bar hydraulic, to be witnessed by ships staff.

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
SPILLTANK DRAIN VALVES
Hot Work No Staging No Job Code C.15
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

DRY - DOCK SPECIFICATIONS 2018


C.15 Allow for removal of 2 pieces of SPILLDRAIN valves for overhaul or change if it is
require, after condition check inform superintendent if require the change. Valves
numbers OD 328,329. Located and manifold aft side Port and Stbd.

Details (Makers/Type/Size)
Type globe valve, ND50mm, JIS5K, MODEL JIS F 7305.

Allow for the removal of total 32 bolts/nuts and renew.

Allow for the removal of 2 valves from site to shore workshop.

Following work to be completed for each valve:

1) Valve to be open remove to flange 8xM12 screws.

2) Valve seat and spindle seat to be grinding

3) Screw down stem to be overhaul.

4) Valve gland studs to be renewed, 2 off. Each approx. M12 thread x 60 mm long,
carbon steel.
5) Valve flange bolts to be renewed. Allow for total 32 x M16 thread x 90 mm long
carbon steel
bolts with nuts.

6) Allow for the renewal of all flange joints with ships approved jointing - Klinger.

7) Allow for the renewal of valve stem packing approved packing - Klinger.

DRY - DOCK SPECIFICATIONS 2018


8) Valve to be tested using cold hydraulic to working pressure as follows -

A) Valve body complete including valve stem packing,

B) Integrity between valve and seat.

Pressure test to 1 bar hydraulic, to be witnessed by ships staff.

DRY DOCK REPAIR SPECIFICATIONS


COW LINE – MASTER VALVE OF EACH COT AND MAIN ISOLATING
Hot Work No Staging No Job Code C.16
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

DRY - DOCK SPECIFICATIONS 2018


C.16 Master Valve For Cow Lines On Each Cot In Main Deck, From Fore To Aft To Be
Removed And Fully Overhauled. Including Renewal of Handle, Seal and Securing Bolts.

Butterfly Wafer Type


16 X 100A VALVES (VALVE BODY= FC – VALVE SEAT= NBR)
4 X 80A VALVES (VALVE BODY= FC – VALVE SEAT= NBR)
9X150A VALVES (VALVE BODY= FC – VALVE SEAT= NBR

DRY DOCK REPAIR SPECIFICATIONS


MAIN CARGO LINE VALVES ON DECK
OVERHAUL
Hot Work N Staging 2m Job Code C.
3
o 17
Gas N Heavy Yes
Freeing o Lift
Ventilation N Access No Steel Kgs
o Remova
l
Cleaning Y Lighting No Class
e
s
Confliction No Completed
with other
jobs

DRY - DOCK SPECIFICATIONS 2018


C.17 Description:

Main Cargo Line Valves on Deck Overhaul

Job Scope:

– Valves to be landed to shore workshop and stripped down for inspection. All parts
to be cleaned.
– Allow removing and replacing valve rubber seat with new spare (owners supply)
– On completion of overhaul, each valve to be blanked and pressure tested to rated
pressure (16 Bar)
– Valves to be fitted back with all new gaskets and nuts/bolts as required.
– All transportation and carnage to be included within quotes
– Leak test after reassembly to be witnessed by nominated member of Ship´s Staff.
– Transportation/Reinstallation on‐board.

All transportation and carnage to be included within quotes

Cargo System Valves in Cargo Lines to be overhauled.

Allow to remove the following valves:

Manifold:

– OD-301 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD S N.1)


– OD-302 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD P N.1)
– OD-303 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD S N.2)
– OD-304 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD P N.2)
– OD-305 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD S N.3)
– OD-306 ND 450mm; Type BTFV; Material A: SC / B: NBR (MANIFOLD P N.3)

DRY - DOCK SPECIFICATIONS 2018


Crossover:
– OD-307 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 2/3 MANIFOLD S N.1)
– OD-308 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 2/3 MANIFOLD P N.1)
– OD-309 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 1/3 MANIFOLD S N.2)
– OD-310 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 1/3 MANIFOLD P N.2)
– OD-311 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 1/2 MANIFOLD S N.3)
– OD-312 ND 450mm; Type BTFV; Material A: SC / B: NBR (TO 1/2 MANIFOLD P N.3)

Drop Valves:
– OD-330 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL DIRECT FILLING N.1)
– OD-331 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL DIRECT FILLING N.2)
– OD-332 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL DIRECT FILLING N.3)

DRY - DOCK SPECIFICATIONS 2018


Block Valves

– OD-333 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL MAIN ISOLATE N.1)
– OD-334 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL MAIN ISOLATE N.2)
– OD-335 ND 450mm; Type BTFV; Material A: SC / B: NBR (CRUDE OIL MAIN ISOLATE N.3)

DRY DOCK REPAIR SPECIFICATIONS


PUMP ROOM P/S SEA CHEST BLOWING VALVE
Hot Work No Staging No Job Code C.18

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.18 Job Description:

 Pump Room P/S Sea Chest Blowing Valve (OP246, OP 245) to be overhauled.

 Valves to be landed to shore workshop and stripped down for inspection. All parts to
be cleaned.

 Allow removing and replacing valve rubber seat with new spare (owners supply) On
completion of overhaul, each valve to be blanked and pressure tested to rated
pressure (16 Bar)

 Valves to be fitted back with all new gaskets and nuts/bolts as required.

DRY DOCK REPAIR SPECIFICATIONS


BUNKER LINE VALVES
Hot Work No Staging No Job Code C.19
Gas Freeing No Heavy Lift No

DRY - DOCK SPECIFICATIONS 2018


Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.19 Position: Main Deck

Job Description:

The valves for bunker tanks to be overhauled.

Butterfly valve DN 200 A, 10k water type.

4 valves need to be overhauled.

Job Scope:

Following work to be completed for each valve -:

1. Valve and Gear box to be opened up for examination.


2. If necessary valve body seal to be renewed, Ships Supply.
3. Gear box parts to be cleaned, re-assembled, greased and proved free to operate.
4. Valve gland studs to be renewed.
5. Valve flange bolts to be renewed. Allow for total 6 x M24 thread x 150 mm long
carbon steel bolts with nuts.
6. Allow for the renewal of all flange joints with ships approved jointing - Klinger.
7. Allow for the renewal of valve stem packing.
8. Valve to be tested using cold hydraulic to working pressure as follows -
a. Valve body complete including valve stem packing,
b. Integrity between butterfly valve and seat.
9. Pressure test to 5 bar hydraulic, to be witnessed by ships staff.

DRY DOCK REPAIR SPECIFICATIONS


SEWAGE OVERBOARD FLAPVALVES
Hot Work No Staging 1 m3 Job Code C.20
Gas Freeing Required No Heavy Lift No
Ventilation No Access Removal No Steel Kgs

DRY - DOCK SPECIFICATIONS 2018


Cleaning Yes Lighting No Class
Confliction with other jobs No Completed

C.20 Job Description:

The following ships side sewage overboard valves (4 pcs) to be overhaul.

Job Scope:

Allow for lapping of flap faces and renewal of flap pin. Internals to be coated with yard
supply Apexior coating. Valves to be closed up with new gaskets.

Angle storm valve 5K-100A, Cast iron – 3 pcs

Straight storm valve 5K-100A, Cast iron – 1 pc

DRY DOCK REPAIR SPECIFICATIONS


STEAM VALVES FOR FO BUNKER TK, ME HEATER AND FWG MAIN INSULATING VALVE
Hot Work No Staging 3m3 Job Code C.21
Gas Freeing No Heavy Lift Yes
Ventilation Yes Access Removal No Steel Kgs
Cleaning Yes Lighting Yes Class
Confliction with other jobs No Completed

DRY - DOCK SPECIFICATIONS 2018


C.21 Steam Valves For FO Bunker TK, ME Heater and FWG Main Insulating Valve

Job Description: Steam Valves for: for FO bunker TK, me heater and FWG main
insulating valve and main condensate return valve need to be dismantled for
overhauled.

Job Scope:

1. Valves to be opened for examination and machining as necessary. Allow for


machining all valve lids and seats. After machining, valves to be lapped.
2. Valve gland studs to be renewed, each valve 2 pc M16 x 100mm.
3. Allow for renewal of packing and jointing with yard supply approved packing and
jointing.
4. Before refitting, valves to be hydraulically tested to satisfaction of C/E in yard
workshop.

Total: 02 Valves

BERNHARD SCHULTE SHIPMANAGEMENT CYPRUS LTD


DRY DOCK REPAIR SPECIFICATIONS
HYDRAULIC WINCH ISOLATION VALVE
Hot Work No Staging No Job Code C.22
Gas Freeing No Heavy Lift Yes
Ventilation Yes Access Removal No Steel Kgs
Cleaning Yes Lighting Yes Class
Confliction with other jobs No Completed

DRY - DOCK SPECIFICATIONS 2018


C.22 Hydraulic winch isolation valve.

Job Description: Hydraulic winch isolation valve some of them are not working properly
and leaking through spindle valve. Which need to be overhauled

Job Scope:

1. Valves to be opened for examination and sealing seat to be changed as necessary.


2. Allow for dismantled completed and overhauled.
3. Allow to check all internal part and renewed if necessary
4. Allow for renewal of packing and jointing with yard supply approved packing and
jointing.
5. Before refitting, valves to be hydraulically tested to satisfaction of C/E in yard
workshop. 200 bar.

Total: 16 valves.

DRY - DOCK SPECIFICATIONS 2018


DRY - DOCK SPECIFICATIONS 2018
DRY DOCK REPAIR SPECIFICATIONS
AUX BOILER N-1 AND N-2 HEATING COILS STEAM TO BE TEST
Hot Work NO Staging No Job Code C.23
Gas Freeing No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting No Class No
Confliction with other jobs Completed

C.23 Job Description:

Allow to check A/B #2 and # 1 heating coils as well to prevent future break down of the
system. Pressure test must be carried out and NDT to the most possible damaged
location of the coils.

Item: AUX BOILER n-1 and n-2 HEATING COILS STEAM TO BE TEST

Position: E/R, 3RD FLOOR AFT

Job Scope:

Auxiliary Boiler heating coils pipe must be tested at 10 bar


Allow to drain the complete water side from boiler and remove steam manifold from
boiler in order to access pipe, special attention when opening the water side covers for
hot water may be present.

After tested carried if one of heating coil is broken or leaking allow to repaired..

New gaskets must be used for all covers removed. Apply anti-seize to nuts and bolts. .

Quote For Renewal of Both Boilers Heating Coils

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
BOILER SAFETY VALVES /SURVEY
Hot Work No Staging No Job Code C.24
Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning No Lighting No Class No
Confliction with other jobs Completed

C.24 Position: Engine Room, Funnel Casing

Job Scope:

 OF Boilers Safety Valves (6 off) to disconnect easing gear and land to shore
workshop for overhaul.
 Valves to be stripped and inspected. Allow for seats to be machined and hand
ground. Allow for renewal of all packing.
 Sliding surfaces to be polished and lightly lubricated with Molyslip HT grease.
 Valves to be tested and adjusted for lifting pressure of 18 kg/cm2 for Aux boiler
and 7,5 Kg /cm2 for composite boiler on shore test bench.
 Certificates to issue on completion to satisfaction of BV surveyor.
 Valves to be refitted on completion.
 Valve size NB65

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
AUX BOILERS SBS SERVICE REQUIRED / SURVEY
Hot Work No Staging No Job Code C.25
Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning No Lighting No Class No
Confliction with other jobs Completed

C.25 Description: Please allow to engage Specialized Technician from SBS to perform
service and commissioning to Auxiliary Boilers.

Position: E/R 2ND Deck, Port and Stbd Side

Boiler Type: Sunrod CPH 30/28 Pin tube boilers (Smoke tube)

The Following Problem Has Been Present on the Boiler during Discharge operation:

1. Fuel oil regulator valve and transmitters are not working properly.
2. Steam atomizing valve need to be overhauled.
3. Adjustment for fan air draft force is not respond in manual even in manual have
some problems and air pressure transmitters.
4. Kinetrol need to be checked due in not working properly.

After Compensated The Boiler Parameters Full Commission Must Be Done.

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
PASSENGER ELEVATOR AND DUMP WAITER FOR SERVICE.
Hot Work No Staging No Job Code C.26
Gas Freeing No Heavy Lift No
Ventilation No Access Removal Yes Steel Kgs
Cleaning No Lighting Yes Class No
Confliction with other jobs Completed

C.26 Description: Ships Elevator to service by Qualified Service representative and


elevator wire must be renew.

Location: Accommodation Block – Port Side

Details (Makers/Type/Size)

Makers- Hyundai Elevator Co Ltd


Type - Single Warp traction Geared Type
Load - 500 kg
Speed - 30 m/min
Capacity - 6 person.

Tests
Running test on completion

Repair Description

Ships Elevator to service by Qualified Individual.


Certificate to Issue on completion.

Allow For Change Elevator Wire For New, Spare Supply By Owner.

DRY - DOCK SPECIFICATIONS 2018


BERNHARD SCHULTE SHIPMANAGEMENT CYPRUS LTD
DRY DOCK REPAIR SPECIFICATIONS
BILGE WATER SEPARATOR ULTRA-SEP® MODEL US3000 SERVICE AT DRY DOCK
Hot Work No Staging No Job Code C.27

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning No Lighting No Class No
Confliction with other Completed
jobs

C.27 Description: Unit Working Properly. Survey And Certification Must Be Carried Out.

Position: E/R, Floor Deck, Aft Side

Removal for Access: Port Side door Panel

Type: Fully automatic ULTRA-SEP® system with a HELI-SEP® bilge water separator, Bag
Filter for solids, and SPIR-O-LATORS® for enhanced waste/oil separation.

Model Number: US3000

Capacity: 3 M3/H (13 GPM)

General Design Data:

Electrical Power Input: All standard voltages. Refer to Electrical Requirements


Consumption: 8.6 kW
Clean Water Supply Ranges: (Flow) 0.6 M3/h Min. 2.6 GPM Min.(Pressure) 275-550 kPa
40-80 PSI
Temperature Ranges: (Influent) 1C - 50C 34F - 122F (Ambient) 1C - 50C 34F -
122F

Design Data:

Influent: A solution of water contaminated with Petroleum products, soaps, and


detergents.
Effluent: (Primary) Processed water, Clean Water < 20,000 molecular weight.
(Secondary) Waste oils and other compounds. Operating Pressure Range: 345-690 kPa
50 - 100 PSI

Weights and Dimensional Data:

DRY - DOCK SPECIFICATIONS 2018


Weight-Dry: 690 kg 1525 Pounds
Weight-Wet: 1275 kg 2805 Pounds
Length: 1830 MM 72 Inches
Width: 1320 MM 52 Inches
Height: 1670 MM 65 3/4 Inches

Job Scope: Allow to engage a service engineer in order to check properly all system and
certification.

DRY DOCK REPAIR SPECIFICATIONS


EXHAUST GAS BOILER 1 - INTERNAL ( COMPOSITE BOILER) SURVEY

DRY - DOCK SPECIFICATIONS 2018


Hot Work No Staging No Job Code C.28
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal Yes Steel Kgs
Cleaning Yes Lighting Yes Class Yes
Confliction with other jobs Completed

C.28 Position: Engine Room Casing

Removal for Access:

Burner to be removed to Gain Access to Furnace

Boiler Type Gadelius GCS Composite Boiler

GCS 23M Design Pressure 7 bar.

DRY - DOCK SPECIFICATIONS 2018


Allow to quote for staging, as per previous sister vessel.

To quote for refractories / cement renewal (after inspection).

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
GANGWAY LOAD TESTS
Hot Work Yes Staging Job Code C.29
Gas Freeing Heavy Lift Yes
Ventilation Access Removal Steel Kgs
Cleaning Yes Lighting Class Yes
Confliction with other jobs Completed

C.29 Port and Stbd Accommodation ladders to be rigged with sandbags or


equivalent, evenly spaced along the length of the entire gangway ladder to a
representative load of 125% rated capacity or as required by class surveyor.
Certificates to be issued on conclusion

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
ENGINE ROOM CRANE LOAD TEST
Hot Work Staging No Job Code C.30
Gas Freeing Heavy Lift
Ventilation Access Removal Steel Kgs
Cleaning Lighting Class Yes
Confliction with other jobs Completed

C.30 Engine Room Crane Load Test to be done and certificated.

Provided necessary supervisor, riggers and equipment to conduct load tested in the
presence of attending superintendent and LR surveyor. On completion, test certificates
issued to owner’s representative as follows: Engine Room crane SWL 6.5 ton

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
INCINERATOR DOOR
Hot Work No Staging No Job Code C.31
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs 285
Cleaning No Lighting No Class YES
Confliction with other jobs Completed

C.31 Job description: Incinerator door need to be repaired.

Job scope:

 Allow to remove the incinerator door


 Allow to remove all insulation material.
 Allow to renewed the foundation for the insulation
 Allow to fit new plibrico or insulating cement.

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
ME FUEL OIL VALVE TESTING BENCH
Hot Work No Staging No Job Code C.32
Gas Freeing No Heavy Lift Yes
Ventilation No Access Removal No Steel Kgs 285
Cleaning No Lighting No Class YES
Confliction with other jobs Completed

C.32 Job description:

Allow to send to workshop in order to repair the high pressure pipe and pressure gauge
calibration must be done.

Allow to check all unit for fine calibration.

DRY - DOCK SPECIFICATIONS 2018


DRY DOCK REPAIR SPECIFICATIONS
AIR CONDITIONER VENTILATION FAN ROOM INSULATION
Hot Work No Staging No Job Code C.33
Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning No Lighting No Class No
Confliction with other jobs No Completed

C.33 Position. Main deck aft side

Job scope.

Allow for install the missing insulation fire proof material to the bulkhead of AC room.

0.5 mtr

12.0 mtrs

DRY DOCK REPAIR SPECIFICATIONS


LOW TEMPERATURE F.W. COOLER SERVICE AND REPAIR
Hot Work No Staging No Job Code C.34

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning No Lighting No Class No
Confliction with other jobs No Completed

C.34 Position: Engine room second floor fwd. stbd.

Job scope:

 Allow for removal of both L.T.F.W cooler front cover and plates for repairs.

DRY DOCK REPAIR SPECIFICATIONS


BILGE WATER DUST SEPARATOR FILTER
Hot Work Yes Staging No Job Code C.35

DRY - DOCK SPECIFICATIONS 2018


Gas Freeing No Heavy Lift No
Ventilation No Access Removal No Steel Kgs
Cleaning Yes Lighting No Class No
Confliction with other jobs No Completed

C.35 Position. Engine room.

Job scope:

- Allow for crop the old filter.


- Allow for fabricate and install the new filter on the place.

DRY - DOCK SPECIFICATIONS 2018


DRY - DOCK SPECIFICATIONS 2018
DRY DOCK REPAIR SPECIFICATIONS
SEWAGE TREATMENT PLANT
Hot Work No Staging No Job Code C.36
Gas Freeing No Heavy Lift No
Ventilation Yes Access Removal Yes Steel Kgs
Cleaning Yes Lighting Yes Class No
Confliction with other jobs Completed

C.36 Position: Engine Room 2nd deck Starboard side

Maker: SASAKURA – HAMWORTHY

Model: SUPER- TRIDENT ST 4A

Job Scope:

- Allow to high pressure wash the three compartments of the sewage treatment plant
tank’s and pump out to a shore facility a volume of 3.0 m3.

- Allow to coat with special paint for water tank the welded plates and welding areas,
apply one coat of primer and two coats of special paint (150mills each).