Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 73

ABSTRACT ESTIMATE

Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in Nandyal Division of Operation Circle, Kurnool

Sl. Rate-Rs. Amount- Rs.


Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Earth work excavation in foundations for building, septic


tank, water sump and for levelling and depositing the earth
on banks with a initial lead of 10 mt and a lift of 2 mt in
mixture of gravel, soft disintegrated rock like shales,
1 56.00 Cum - 371.00 371.00 1 Cum - 20,776.00 20,776.00
ordinary gravel, stoney earth and earth mixed with fair sized
boulders including all leads and lifts, tools and plants,
labour, disposal of excess excavted earth etc., complete for
finished item of work as directed by the Engineer in charge.

Filling with sand, below and sides of foundations and


basement in layers not exceeding 15cm thick, consolidating
each deposited layer by watering and ramming including
cost and conveyance of all materials, labour charges, hire
2 64.00 Cum 1,525.00 30.00 1,555.00 1 Cum 97,600.00 1,920.00 99,520.00
charges of T&P, all leads and lifts etc., complete for
finished item of work as directed by the Engineer in charge.
The contractor shall make his own arrangements for
procuring the specified water through tankers.

Plain Cement Concrete in (1:4:8) proportion for leveling


course in foundations using 40mm size HBG metal from
approved quarry including cost and conveyance charges of
cement and all other materials to site, all leads and lifts,
seigniorage charges, dewatering, labour charges, machine
3 7.00 Cum mixing, laying concrete, ramming in 15 cm thick layers, 2,844.00 1,983.00 4,827.00 1 Cum 19,908.00 13,881.00 33,789.00
finishing top surface to the required level, curing etc.,
complete for finished item of work as directed by the
Engineer in charge. The contractor shall make his own
arrangements for procuring the specified water through
tankers.

Random Rubble stone Masonry in CM(1:6) using Hard


granite stones from approved quarry including cost and
conveyance charges of cement and all other materials to site
and including cost of seigniorage charges, labour charges
4 19.00 Cum 2,281.00 2,001.00 4,282.00 1 Cum 43,339.00 38,019.00 81,358.00
for cutting stones to required size and shape, mixing of
cement mortar, dewatering charges, scaffolding, curing , all
leads and lifts etc complete for finished item of work as
directed by the Engineer in charge .

Page 1 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

RCC Footings, plinth beams, walls, columns, beams, lintles,


roof slab, stair case slab and sun shades by laying vibrated
R.C.C M20 grade design mix using 12mm to 20mm size
graded HBG machine crushed metal (50% each) from
approved quarry and a minimum of 400 Kgs of cement for 1
Cum of concrete including cost and conveyance charges of
cement and all other materials to site, scaffolding charges,
5 -
centering, shuttering, machine mixing, laying concrete,
curing, vibrating, all incidental and operational charges, all
leads and lifts etc., but excluding cost of steel and its
fabrication complete for finished item of work as directed
by the Engineer in charge. The contractor shall make his
own arrangements for procuring the specified water through
tankers.

5.1 9.50 CumFootings 4,636.00 3,880.00 8,516.00 1 Cum 44,042.00 36,860.00 80,902.00
5.2 3.50 CumPlinth Beam 5,834.00 4,866.00 10,700.00 1 Cum 20,419.00 17,031.00 37,450.00
5.3 3.00 CumColumns 4,582.00 5,729.00 10,311.00 1 Cum 13,746.00 17,187.00 30,933.00
5.4 1.30 CumLintels 5,182.00 5,168.00 10,350.00 1 Cum 6,736.60 6,718.40 13,455.00
5.5 2.30 CumRoof Beams 5,839.00 3,438.00 9,277.00 1 Cum 13,429.70 7,907.40 21,337.00
5.6 9.00 CumRoof Slab 5,696.00 3,354.00 9,050.00 1 Cum 51,264.00 30,186.00 81,450.00
Sun shades and chajjas (62mm average thickness and 60 cm
5.7 17.00 RM 263.00 230.00 493.00 1 RM 4,471.00 3,910.00 8,381.00
width)

Reinforcement steel supply and labour charges for cutting,


bending of HYSD steel bars / mild steel bars of different
diameters to required size and shape placing in position with
cover blocks of approved size and tying with binding wire
of 20 SWG, forming grills for reinforcement work as per
approved designs and drawings, providing of fan hooks with
6 2.700 MT 71,165.00 14,144.00 85,309.00 1 MT 192,145.50 38,188.80 230,334.00
16mm dia MS rods including cost and conveyance charges
of steel , including cost of binding wire, cover blocks,
including cost of overlaps, welding, wastage, couplings,
space bars, chairs etc., all incidental & operational charges,
all labour charges etc., complete for finished item of work
as directed by the Engineer in charge .

Page 2 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Brick masonry for walls in super structure with CM(1:6)


using local made bricks of approved quality from approved
source having including cost and conveyance charges of
cement and all materials to site, seigniorage charges etc.
7 30.50 Cum 5,451.00 1,620.00 7,071.00 1 Cum 166,255.50 49,410.00 215,666.00
complete for finished item of work as as directed by the
Engineer in charge .The contractor shall make his own
arrangements for procuring the specified water through
tankers.

Reinforced Brick masonry for walls in super structure with


CM(1:5) using local made bricks of approved quality from
approved source having minimum crushing strength of 35
Kg/cm2 and 6mm MS steel rods 2nos at 75cm centre to
centre up to total height of the wall including cost and
conveyance charges of cement but excluding cost of steel
and its fabrication charges ( steel cost will be paid
8 1.20 Cum 5,451.00 2,397.00 7,848.00 1 Cum 6,541.20 2,876.40 9,418.00
separately) and all materials to site, seigniorage charges,
incidental and operational charges, all labour charges,
scaffolding charges, construction, mixing charges, all leads
and lifts, curing etc., complete for finished item of work as
directed by the Engineer in charge. The contractor shall
make his own arrangements for procuring the specified
water through tankers.

Bed blocks and hold fasts using plain Cement Concrete in


(1:3:6) proportion with 12mm to 20 mm graded HBG metal
(50% each) from approved quarry including cost and
conveyance charges of cement , all other materials to site,
9 2.00 Cum all leads and lifts, seigniorage charges, labour charges, 3,533.00 1,444.00 4,977.00 1 Cum 7,066.00 2,888.00 9,954.00
laying concrete, form work, curing etc., complete for
finished item of work as directed by the Engineer in charge.
The contractor shall make his own arrangements for
procuring the specified water through tankers.

Page 3 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Plastering 12 mm thick in one coat for superstructurefor


even faces of walls with CM(1:5) with smooth finish at all
heights including cost and conveyance charges of cement
and all other materials to site, scaffolding charges,
seigniorage charges, incidental and operational charges, all
10 134.96 Sqm 47.00 262.00 309.00 1 Sqm 6,343.12 35,359.52 41,703.00
labour charges for mixing mortar, finishing, all leads and
lifts, curing, cutting grooves etc., complete for finished
item of work and as directed by the Engineer in charge. The
contractor shall make his own arrangements for procuring
the specified water through tankers.

Plastering 20 mm thick in for superstructure for un-even


faces of walls with CM (1:5) with sponge finish at all
heights including cost and conveyance charges of cement
and all other materials to site, scaffolding charges,
seigniorage charges, incidental and operational charges, all
11 248.00 Sqm 73.00 263.00 336.00 1 Sqm 18,104.00 65,224.00 83,328.00
labour charges for mixing mortar, finishing, all leads and
lifts, curing, cutting grooves etc., complete for finished
item of work and as directed by the Engineer in charge. The
contractor shall make his own arrangements for procuring
the specified water through tankers.

Plastering to ceiling 12 mm thick in one coat in CM(1:3)


with sponge finish at all heights including cost and
conveyance charges of cement and all other materials to
site, scaffolding charges, seigniorage charges, incidental
and operational charges, all labour charges for mixing
12 72.00 Sqm 60.00 262.00 322.00 1 Sqm 4,320.00 18,864.00 23,184.00
mortar, finishing, all leads and lifts, curing, cutting grooves
etc., complete for finished item of work and as directed by
the Engineer in charge. The contractor shall make his own
arrangements for procuring the specified water through
tankers.

Providing impervious coat with CM(1:3) 20 mm thick using


approved waterproofing compound over terrace including
cost and conveyance charges of cement and all other
materials to site, scaffolding charges, seigniorage charges,
incidental and operational charges, all labour charges for
13 82.00 Sqm 93.00 361.00 454.00 1 Sqm 7,626.00 29,602.00 37,228.00
mixing mortar, finishing, all leads and lifts, curing, cutting
grooves etc., complete for finished item of work and as
directed by the Engineer in charge. The contractor shall
make his own arrangements for procuring the specified
water through tankers.

Page 4 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Flooring with a bed of 100mm thick in CC (1:4:8) with


40mm & 20mm size HBG Metal from approved quarry
including cost and conveyance charges of cement and all
other materials to site, seigniorage charges, labour charges
14 6.00 Cum for machine mixing, laying concrete, finishing top surface to 3,135.00 1,983.00 5,118.00 1 Cum 18,810.00 11,898.00 30,708.00
the required level, curing etc., complete for finished item of
work as directed by the Engineer in charge. The contractor
shall make his own arrangements for procuring the specified
water through tankers.

Flooring with High Polished Granite 16 to 18mm thick up to


2.43M black of black colour and design set over a base coat
of CM(1:8) , 12 mm thick over CC bed already laid with
neat cement slurry of honey like consistency spread at the
rate of 3.3 Kgs per Sqm and filling the joints with white
cement paste mixed with pigment of matching shade is to be
15 66.00 Sqm done including cost and conveyance charges of cement and 2,345.00 738.00 3,083.00 1 Sqm 154,770.00 48,708.00 203,478.00
all other materials to site, seigniorage charges, incidental
and operational charges, all labour charges for mixing
mortar, finishing, all leads and lifts, etc., complete for
finished item of work and as directed by the Engineer in
charge.The contractor shall make his own arrangements for
procuring the specified water through tankers.

Flooring with Non - skid red or white full body Ceramic


floor tiles of size 300 x 300 mm and thickness between 7-
8mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 - 15) of any colour and finish in all shades
and designs set over base coat of cement mortar (1:8), 12
mm thick over CC bed already laid or RCC roof slab,
16 3.00 Sqm including neat cement slurry of honey like consistency 485.00 401.00 886.00 1 Sqm 1,455.00 1,203.00 2,658.00
spread @ 3.3.kgs per sqm & jointed neatly with white
cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, sand
water and tiles etc., complete for finished item of work.The
contractor shall make his own arrangements for procuring
the specified water through tankers.

Page 5 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Dadooing in toilets and bath rooms with glazed red or


white fully body ceramic tiles of size 200 x 300 mm / 245 x
325 mm and thickness 6mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour
and finish in all shades and designs set over a base coat of
CM(1:3) 12 mm thick with neat cement slurry of honey
like consistency spread at the rate of 3.3 Kgs per Sqm and
filling the joints with white cement paste mixed with
17 10.00 Sqm 501.00 401.00 902.00 1 Sqm 5,010.00 4,010.00 9,020.00
pigment of matching shade is to be done including cost and
conveyance charges of cement and all other materials to
site, seigniorage charges, incidental and operational charges,
all labour charges for mixing mortar, finishing, all leads
and lifts, etc., complete for finished item of work and as
directed by the Engineer in charge.The contractor shall
make his own arrangements for procuring the specified
water through tankers.

Supplying & fixing Flush door shutters, solid bond wood


block board type with teak ply on both faces.: 30 mmthick
18 6.00 Sqm conforming to IS:2202 including providing special PVC 2,871.00 634.00 3,505.00 1 Sqm 17,226.00 3,804.00 21,030.00
braket on hinge side, etc complete as per direction of
Engineer–in–charge, manufacturers specification.

Providing and fixing factory made solid Wood Polymer


Composite (WPC) single extruded Door Frame section of
size with encapsulation of 8MM rigid layer on all the six
surfaces. The door frame will have a rebat of 32MM. Door
Frame section of 63.5x100 MM.The two Vertical members
are to be joined together with the horizontal member using
8x75 MM long MS Star full thread screws to be used with
19 24.72 RM 940.00 144.00 1,084.00 1 RM 23,236.80 3,559.68 26,796.00
reverse forward speed control hand drilling machine. The
ready/assembled door frame is fixed to the wall using hold
fast or bolt fasteners. A minimum of 4 No of screws to be
provided for each vertical member & minimum 2no for
horizontal member. The price inclusive of all material at
site complete for finished item of work as directed by the
Engineer in charge.

Page 6 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Supplying & fixing Flush door shutters, 28 -30 MM thick


solid Wood Polymer Composite(WPC) single extruded door
shutter with 3MM top and bottom rigid layer with an overall
density of 750kg/Cum. It will be fixed to the frame using 3
20 2.00 Sqm inch /4 inch hinges. A minimum of 4 hinges will be required 3,711.00 634.00 4,345.00 1 Sqm 7,422.00 1,268.00 8,690.00
for fixing the door with the frame including cost and
conveyance of all materials and labour charges , etc
complete as per direction of Engineer–in–charge,
manufacturers specification.

Providing and fixing factory made uPVC white colour


sliding glazed window upto 1.50 m in height dimension
comprising of uPVC multi-chamberedframe with in-built
roller track and sash extruded profiles duly reinforcedwith
1.60 ± 0.2 mm thick galvanized mild steel section made
from rollforming process of required length (shape & size
according to uPVCprofile), appropriate dimension of uPVC
extruded glazing beads andu PVC extruded interlocks,
EPDM gasket, wool pile, zinc alloy (white powder coated)
touch locks with hook, zinc alloy body with single
nylonrollers (weight bearing capacity to be 40 kg), G.I
fasteners 100 x 8 mm size for fixing frame to finished wall
and necessary stainless steel screwsetc. Profile of frame &
21 13.00 Sqm 4,876.00 2,090.00 6,966.00 1 Sqm 63,388.00 27,170.00 90,558.00
sash shall be mitred cut and fusion welded at allcorners,
including drilling of holes for fixing hardware's and
drainage ofwater etc. After fixing frame the gap between
frame and adjacent finishedwall shall be filled with weather
proof silicon sealent over backer rod of required size and of
approved quality, all complete as per approved drawing&
direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes, wire mesh and silicon sealent .
Note: For uPVC frame and sash extruded profiles minus 5%
tolerancein dimension i.e. in depth & width of profile shall
be acceptable.Variation in profile dimension in higher side
shall be accepted. But no extra payment on this account
shall be made.

Supply and fixing of MS grill for Stair case hand rail,gates


etc. of different sizes including cost and conveyance of all
the materials, fabrication charges,fixing charges, labour
22 442.00 Kg 64.00 41.00 105.00 1 Kg 28,288.00 18,122.00 46,410.00
charges and painting with two coats of synthetic enamel
paint over one coat of primer etc., complete for finished
item of work as directed by the Engineer-in-charge.

Page 7 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Painting the walls (Inside) and ceiling with two coats of


Plastic emulsion paint grade-I of Asian make over one coat
of primer of approved colour, make and shade over one
coat of white cement primer including cost and conveyance
of all materials to site, water to site, cost of brushes,
23 272.00 Sqm scaffolding charges, all labour charges, curing, tools and 59.00 128.00 187.00 1 Sqm 16,048.00 34,816.00 50,864.00
plant, incidental charges, all leads and lifts etc at all
heights of all floors complete for finished item of work and
as directed by the Engineer in charge.The contractor shall
make his own arrangements for procuring the specified
water through tankers.

Painting to walls (out side) with two coats of Weather proof


acrylic exterior emulsion or equivalent quality paint of
approved colour, make and shade over one coat of white
cement primer including cost and conveyance of all
materials, water to site, cost of brushes, scaffolding charges,
24 174.85 Sqm all labour charges, curing, tools and plant, incidental 40.00 182.00 222.00 1 Sqm 6,994.00 31,822.70 38,817.00
charges, all leads and lifts etc at all heights of all floors
complete for finished item of work and as directed by the
Engineer in charge.The contractor shall make his own
arrangements for procuring the specified water through
tankers.

Painting new iron work with Synthetic enamel paints 2


coats over a coat of approved red oxide primer making 3
coats in all to give an even shade including cost and
25 12.00 Sqm 44.00 121.00 165.00 1 Sqm 528.00 1,452.00 1,980.00
conveyance of all materials to work site and all operational,
incidental, labour charges etc., complete for finished item of
work..

Painting new wood work with Synthetic enamel paints 2


coats over a coat of approved wood primer making 3 coats
26 22.00 Sqm in all to give an even shade including cost and conveyance 37.00 128.00 165.00 1 Sqm 814.00 2,816.00 3,630.00
of all materials to work site and all operational, incidental,
labour charges etc., complete for finished item of work..

Supplying & fixing of 110mm dia. Rain water down take


pipe with PVC Pipes of Prince or sudhakar or equivalent
27 7.50 RM 155.00 82.00 237.00 1 RM 1,162.50 615.00 1,778.00
make including cost and conveyance of PVC Pipes,
specials, labour charges etc complete…
Supply and fixing of 25mm outer dia heavy (2.10mm
thickness) regid PVC pipe ( ISI mark) concealed in wall
28 113.00 RM 57.00 55.00 112.00 1 RM 6,441.00 6,215.00 12,656.00
with all required accessories including masonry work and
labour charges complete

Page 8 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Wiring with 2 runs of 14/0.3mm (1.0 sqmm) FRLS/HFFR


PVC insulated 1100V grade as per IS: 694/1990
specification for Copper cable of makes Finolex / RR Kabel
/ KEI 6A /10A Modular switch of Legrand Arteor / MK
29 22.00 Nos Blenge / Schneider Zen Celo , ceiling rose, suitable hot dip 581.00 266.00 847.00 1 No 12,782.00 5,852.00 18,634.00
Galvanized metal box with cover frame to switch control
box including all labour chages etc. complete for light, bell,
fan and exhaust fan points for finished item of work as
directed by the Engineer-in-charge.

Supply and fixing of 6A /10A 3/2 Pin Modular Socket with


shutter of Legrand Arteor / MK Blenge / Schneider Zen
Celo with switch control of 6A /10A Modular switch of
30 -
Legrand Arteor / MK Blenge / Schneider Zen Celo with
earth continuity including wire leads, earth connections
along with all labour charges etc., complete.
30.1 9.00 Nos Independent Mounting 373.00 94.00 467.00 1 No 3,357.00 846.00 4,203.00
30.2 3.00 Nos Dependent Mounting 210.00 94.00 304.00 1 No 630.00 282.00 912.00
Supply and run of 2 of 36/0.3 mm (2.5 sqmm) FRLS /
HFFR PVC insulated 1100V grade as per IS:694/1990
31 85.00 RM specification for Copper cable of makes Finolex / RR Kabel 60.00 22.00 82.00 1 RM 5,100.00 1,870.00 6,970.00
/ KEI in existing pipe for mains including all labour charges
complete.

Supply and run of 1 of 14/0.3mm (1.0 sqmm) FRLS/HFFR


PVC insulated 1100V grade as per IS: 694/1990
32 30.00 RM specification for Copper cable of makes Finolex / RR Kabel 13.00 11.00 24.00 1 RM 390.00 330.00 720.00
/ KEI in existing pipe for earth continuity including all
labour charges complete.

Supply and run of 2 of 56/0.3mm (4.0 Sqmm) FRLS /


HFFR PVC insulated 1100V grade as per IS:694/1990
33 10.00 RM specification for Copper cable of makes Finolex / RR Kabel 91.00 33.00 124.00 1 RM 910.00 330.00 1,240.00
/ KEI in existing pipe for mains including all labour charges
complete.

Supply and run of 1 of 36/0.3 mm (2.5 sqmm) FRLS /


HFFR PVC insulated 1100V grade as per IS:694/1990
34 10.00 RM specification for Copper cable of makes Finolex / RR Kabel 30.00 11.00 41.00 1 RM 300.00 110.00 410.00
/ KEI in existing pipe for earth continuity including all
labour charges complete.

Page 9 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Supply and fixing of 4-way VTPN Distribution board


suitable for accommodating 4 pole Isolator as incomer with
IP 43 Protection as per IS:13032 and suitable for 4Nos
T.P.outgoings etc., complete of makes Legrand / Schneider
35 1.00 Nos including cost of D.B., 1No.63A FP isolator, 12 Nos. 6-32A 12,632.00 1,646.00 14,278.00 1 No 12,632.00 1,646.00 14,278.00
10KA SP MCBs of make Legrand / Schneider., giving all
internal connections and labour charges for surface/flush
mounting etc. complete for finished item of work as directed
by the Engineer-in-charge.

Supply and fixing of 25 Sqmm 3.5 core XLPE insulated,


1100V grade armoured alluminimum cable as per
specification confirming to IS:7098 (Part - I) of makes
Polycab / RPG / Finolex / Havells / Paragon / V-Guard /
36 30.00 RM 46.00 35.00 81.00 1 RM 1,380.00 1,050.00 2,430.00
Fortune Art / Gloster / Suncab from Source to Distribution
Board including all accessories and labour chargesfor
giving all connections etc. complete for finished item of
work as directed by the Engineer-in-charge.

Providing fuse carrier board comprises of 3Nos porcelain


fuse carriers 63Amp/415V with HRC fuses assembled over
10"x7" teak wood peeta board fixed to wall surface with
37 1.00 Nos incoming from electric pole and out going to distribution 1,263.00 676.00 1,939.00 1 No 1,263.00 676.00 1,939.00
board as per relevant standard specifications including cost
and conveyance of all materials, screws, nails and labour
charges etc., complete for finished item of work.

Supply and fixing of 1x 36/40 W Patty type tube light


luminarie powder coated CRCA sheet steel housing with
Copper Chokes and all standard accessories of makes
38 10.00 Nos Crompton / Bajaj / Surya / Havells / HPL / Fortune Art and 643.00 132.00 775.00 1 No 6,430.00 1,320.00 7,750.00
1 No. 36/40 W tube light including cost and conveyance of
all materials and labour complete for finished item of work
as directed by Engineer - In - Charge

Supply and fixing of batten holder/ slanting holder in lieu of


ceiling rose of light point complete with all connections and
39 5.00 Nos 133.00 70.00 203.00 1 No 665.00 350.00 1,015.00
labour charges, cost of 40 W bulb etc., complete for
finished item of work.

Page 10 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL
Supply and fixing of CEILING fan of 48" Sweep, 5 Star
rated Ceiling Fan, with double ball bearings, power input
not more than 53W, air delivery more than 218 cubic
40 3.00 Nos meter/min and service value 4.11 with stepped type 2,940.00 176.00 3,116.00 1 No 8,820.00 528.00 9,348.00
electronic regulator including cost and conveyance of all
materials and labour charges complete for finished item of
work as directed by the Engineer-in-Charge.

Providing Independent earthing by excavating a trench to a


depth of 2.70M in all soils as per size specified in the data
using 75mm dia CI(spun) pipe of 3.00Mtr length with
41 1.00 Nos necessary accessories with humepipe ring duly providing 4,266.00 629.00 4,895.00 1 No 4,266.00 629.00 4,895.00
stagered holes including filling with equal proportion of salt
and charchol in layers and all labour charges etc. complete
for small finished item of work.

Supply of Polyethylene water storage tank double layer


conforming to IS:12701 - 1996 of 500 Ltr capacity with lid
42 1.00 Nos 4,836.00 1,040.00 5,876.00 1 No 4,836.00 1,040.00 5,876.00
including cost and conveyance of all materials, labour
charges etc., complete for finished item of work

Supply and fixing of different dia.Unplasticised PVC


Pipes,10 kg/cm2 for potable water supplies conforming to
IS : 4985/2000 (third revision) with bell ends (Socket) as
per specification in light Grey/Natural Ivory Grey/ Any
43 other Color including Labour charges for laying, fixing, and -
commissioning the pipes including couplers, bends, plugs,
junctions, tees etc. with solvent jointing as per Standard
practice for finished item work as directed by the Engineer-
in-charge.
44.1 48.00 RM 25mm dia UPVC pipe 30.00 82.00 112.00 1 RM 1,440.00 3,936.00 5,376.00
44.2 15.00 RM 20mm dia UPVC pipe 20.00 82.00 102.00 1 RM 300.00 1,230.00 1,530.00
Supply and fixing of 25mm GM Gate (GM peet) valves as
per IS 778 Class I -Indian make heavy type of different
44 sizes including cost and conveyance of all materials and -
labour Charges complete for finished item work as directed
by the Engineer-in-charge..
A 3.00 Nos 25mm GM Gate Valves 1,160.00 52.00 1,212.00 1 No 3,480.00 156.00 3,636.00

Supply and fixing of CP Long body bib cock fancy type


delux heavy duty 12.7mm dia Indian make Seiko / Senior /
45 1.00 Nos Nice or equivalent including cost and conveyance of all 597.00 34.00 631.00 1 No 597.00 34.00 631.00
materials, labour charges etc., complete for finished item of
work as directed by the Engineer - In - Charge

Page 11 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Supply and fixing of CP Short body bib cock fancy type


delux heavy duty 12.7mm dia Indian make Seiko / Senior /
46 3.00 Nos Nice or equivalent including cost and conveyance of all 571.00 34.00 605.00 1 No 1,713.00 102.00 1,815.00
materials, labour charges etc., complete for finished item of
work as directed by the Engineer - In - Charge

Supply and fixing of Angle stop cock 12.7 mm dia first


quality Indian make heavy duty Seiko / Senior / Nice or
47 2.00 Nos equivalent including cost and conveyance of all materials, 420.00 51.00 471.00 1 No 840.00 102.00 942.00
labour charges etc., complete for finished item of work as
directed by the Engineer - In - Charge

Supplying and fixing colour glazed porcelain European


type Parry ware make or equivalent quality water closets
with ISI make, P or S trap including cost and conveyance of
48 1.00 Nos water closet, P or S trap, plastic seat and lid and all other 2,630.00 402.00 3,032.00 1 No 2,630.00 402.00 3,032.00
materials, labour charges for fixing etc., complete for
finished item of work as directed by the Engineer in charge
of work

Supplying and fixing of PVC flushing tank of parry ware


make or equivalent ISI make with all fixtures including cost
49 1.00 Nos and conveyance of tank and all other materials, labour 1,844.00 623.00 2,467.00 1 No 1,844.00 623.00 2,467.00
charges for fixing etc., complete for finished item of work
as directed by the Engineer in charge of work

Supplying and fixing (550mm x 400 mm) Indian make Flat


back wash hand basin(HSW/ Parryware/Neycer) 1st quality
conforming to IS:2556-Part-4:1972 with waste fittings like
rubber plug, chain,32 mm nominal size C.P.Fitting with
parallel pipe thread confirming to IS:2963-1979 and fitting
50 1.00 Nos 1,355.00 376.00 1,731.00 1 Nos 1,355.00 376.00 1,731.00
with 15 mm nominal bore Chromium plated pillar tap of 1st
quality Indian make 400gms Seiko / Senior / Nice / Esso or
equivalent complete with standard CI brackets including
wooden block etc. complete for finished item of work as
directed by the Engineer in charge of work

Supply and fixing of 12.7mm dia UPVC Health faucet of


51 1.00 Nos 988.00 94.00 1,082.00 1 No 988.00 94.00 1,082.00
ISI make WATER-TECH or equivalent
Supply & Fixing 12.7mm PVC connection with brass union
nut C.P.Coated including cost and conveyance of all
52 2.00 Nos 79.00 20.00 99.00 1 No 158.00 40.00 198.00
materials and labour charges complete for finished item of
work as directed by the Engineer - in - charge

Page 12 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL
Supply & Fixing 31.75mm dia PVC flexibile waste pipe of
914.40mm length of 1st quality including cost and
53 1.00 Nos conveyance of all materials and labour charges complete for 25.00 6.00 31.00 1 No 25.00 6.00 31.00
finished item of work as directed by the Engineer - in -
charge

Supplying & fixing in walls,ground different dia PVC Pipes


of Prince or sudhakar or equivalent make for sewer lines
54 -
including cost and conveyance of PVC Pipes, specials, PVC
cowls labour charges etc complete…

55.1 14.00 RM 110mm dia.(6 kg/cm2) 265.00 82.00 347.00 1 RM 3,710.00 1,148.00 4,858.00
55.2 30.00 RM 75 mm dia.( 6kg/cm2) 151.00 82.00 233.00 1 RM 4,530.00 2,460.00 6,990.00
Supply and Fixing of 100mm Nahani traps of
Prince/sudhakar or any ISI brand including cost and
55 2.00 Nos conveyance of all materials, labour charges etc., complete 84.00 9.00 93.00 1 No 168.00 18.00 186.00
for finished item of work as directed by the Engineer - In -
Charge

Construction of Manholes of size 457.2x457.2mm brick in


CM(1:6) proportion masonary Inspection chamber upto
914.4mm depth and fitted with suitable CI frame and cover
of 20 kg including cost and conveyance of all materials,
56 1.00 Nos 2,987.00 747.00 3,734.00 1 No 2,987.00 747.00 3,734.00
labour charges etc., complete for finished item of work as
directed by the Engineer - In - Charge. The contractor shall
make his own arrangements for procuring the specified
water through tankers.

Providing 15mm thick moulded cement mortar bands in


cement mortar 1:4 (1Cement:4Sand) upto 300mm in width
including cost and conveyance charges of cement and all
57 -
materials to site, seigniorage charges etc., complete for
finished item of work as directed by the Engineer - in -
Charge.
A 34.00 RM 10.00CM wide band - - - 1 RM - - -
B 24.00 RM 4.00CM wide band 3.00 26.00 29.00 1 RM 72.00 624.00 696.00

Providing name boards to office buildings on wall surface


of the buildings with two coats of Synthetic Enamel Paint of
approved quality, colour and shade painted over a coat of
58 7.50 Sqm 40.00 272.00 312.00 1 Sqm 300.00 2,040.00 2,340.00
primer of approved quality including cost and conveyance
of all materials, labour charges, leads and lifts, scaffolding
charges etc., complete for finished item of work.

Page 13 of 73
Sl. Rate-Rs. Amount- Rs.
Quantity Description of work per
No Material Labour TOTAL Material Labour TOTAL

Construction of soak pit with 4' dia RCM rings upto a depth
59 1.00 No 3,900.00 260.00 4,160.00 1 No 3,900.00 260.00 4,160.00
of 5' including cost and conveyance of all materials

Supply and laying Polished black Kadapa slabs of all sizes


between 25 -30mm thickness as shelf slabs including cost of
all materials like cement, sand, and water and flooring
60 24.00 Sqm 212.00 46.00 258.00 1 Sqm 5,087.92 1,103.98 6,192.00
stones etc., complete, including seigniorage charges, labour
charges for dressing of flooring stones etc., complete for
finished item of work.
Sub Total 1,174,835.84 666,648.88 1,841,486.00
Add BWW Cess @1% on Material+labour excluding taxes 18,414.86
Transaction value 1859900.86
GST @18% on Transaction value 334782.15
Add for unforseen items 316.99
Total 2,195,000.00

Page 14 of 73
DETAILED ESTIMATE

Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in
Nandyal Division of Operation Circle, Kurnool

S. No Description of work No. L B D Quantity

Earth work excavation in foundations for building, septic tank, water sump and for
levelling and depositing the earth on banks with a initial lead of 10 mt and a lift of 2
mt in mixture of gravel, soft disintegrated rock like shales, ordinary gravel, stoney
1
earth and earth mixed with fair sized boulders including all leads and lifts, tools and
plants, labour, disposal of excess excavted earth etc., complete for finished item of
work as directed by the Engineer in charge.

For foundation of column footings 8 x 1 1.68 1.68 1.52 34.17


1 x 1 1.98 1.98 1.52 5.97
For foundation of wall alround 1 x 1 30.82 0.60 0.92 17.01
Deduct for already excavated portion for
-8 x 1 1.68 0.60 0.92 -7.40
column footings
For steps 3 x 1 1.68 1.20 0.92 5.56
Add variation 0.69
Total: 56.00
Cum

Filling with sand, below and sides of foundations and basement in layers not
exceeding 15cm thick, consolidating each deposited layer by watering and ramming
including cost and conveyance of all materials, labour charges, hire charges of T&P,
2
all leads and lifts etc., complete for finished item of work as directed by the Engineer
in charge. The contractor shall make his own arrangements for procuring the
specified water through tankers.

For foundation of column footings 8 x 1 1.68 1.68 0.15 3.37


1 x 1 1.98 1.98 0.15 0.59
For foundation of wall alround 1 x 1 30.82 0.60 0.15 2.77
Deduct for columns coming in walls line -9 x 1 0.23 0.60 0.23 -0.29
For back filling upto ground level
Earth work in excavation for footings 8 x 1 1.68 1.68 1.98 44.52
1 x 1 1.98 1.98 1.98 7.77
walls alround 1 x 1 30.82 0.60 0.75 13.87
Deduct for already excavated portion for
-8 x 1 1.68 0.60 1.83 -14.73
column footings
Deduct for sand filling in footings -8 x 1 1.68 1.68 0.15 -3.37
-1 x 1 1.98 1.98 0.15 -0.59

Page 15 of 73
S. No Description of work No. L B D Quantity
Deduct for PCC in footings -8 x 1 1.68 1.68 0.10 -2.25
-1 x 1 1.98 1.98 0.10 -0.39
Deduct for RCC in footings -8 x 1 1.68 1.68 0.30 -6.74

-1 x 1 1.98 1.98 0.30 -1.18

-8 x 1 0.70 0.70 0.45 -1.76

-1 x 1 1.00 1.00 0.45 -0.45


Balance portion of columns upto bottom
-9 x 1 0.23 0.30 0.78 -0.48
level of earthwork for wall alround
2 x 1 1.67 0.08 1.53 0.41
For steps 3 x 1 1.68 1.20 0.15 0.91
For basement filling 1 x 1 6.78 7.09 0.45 21.63
Add variation 0.39
Total 64.00
Cum

Plain Cement Concrete in (1:4:8) proportion for leveling course in foundations using
40mm size HBG metal from approved quarry including cost and conveyance
charges of cement and all other materials to site, all leads and lifts, seigniorage
3 charges, dewatering, labour charges, machine mixing, laying concrete, ramming in
15 cm thick layers, finishing top surface to the required level, curing etc., complete
for finished item of work as directed by the Engineer in charge. The contractor shall
make his own arrangements for procuring the specified water through tankers.

For foundation of column footings 8 x 1 1.68 1.68 0.15 3.37


1 x 1 1.98 1.98 0.15 0.59
For foundation of wall alround 1 x 1 30.82 0.60 0.10 1.85
Deduct for columns coming in walls line -9 x 1 0.23 0.30 0.10 -0.06
For steps 3 x 1 1.68 1.20 0.10 0.60
Add for variations 0.65
Total 7.00
Cum

Page 16 of 73
S. No Description of work No. L B D Quantity

Random Rubble stone Masonry in CM(1:6) using Hard granite stones from approved
quarry including cost and conveyance charges of cement and all other materials to
site and including cost of seigniorage charges, labour charges for cutting stones to
4
required size and shape, mixing of cement mortar, dewatering charges, scaffolding,
curing , all leads and lifts etc complete for finished item of work as directed by the
Engineer in charge .

BGL 1 x 2 8.00 0.45 0.67 4.82


1 x 2 7.09 0.45 0.67 4.28
Column Deductions -9 1 0.23 0.30 0.95 -0.59
AGL 1 x 2 7.85 0.45 0.45 3.18
1 x 2 8.15 0.45 0.45 3.30
Column Deductions -9 1 0.23 0.30 0.45 -0.28
For steps 3 x 1 1.68 1.20 0.67 4.05
Add for variations 0.24
Total 19.00
Cum

RCC Footings, plinth beams, walls, columns, beams, lintles, roof slab, stair case slab
and sun shades by laying vibrated R.C.C M20 grade design mix using 12mm to
20mm size graded HBG machine crushed metal (50% each) from approved quarry
and a minimum of 400 Kgs of cement for 1 Cum of concrete including cost and
conveyance charges of cement and all other materials to site, scaffolding charges,
5
centering, shuttering, machine mixing, laying concrete, curing, vibrating, all
incidental and operational charges, all leads and lifts etc., but excluding cost of steel
and its fabrication complete for finished item of work as directed by the Engineer in
charge. The contractor shall make his own arrangements for procuring the specified
water through tankers.

5.1 Footings 8 x 1 1.52 1.52 0.30 5.54


8 x 1 1.00 1.00 0.30 2.40
1 x 1 1.83 1.83 0.30 1.00
1 x 1 1.20 1.20 0.30 0.43
Add for variations 0.13
Total 9.50
Cum
5.2 Plinth Beam
Alround building 1 x 1 30.48 0.23 0.30 2.10
Inside building 1 x 1 7.54 0.23 0.30 0.52
1 x 1 7.09 0.23 0.30 0.49
Add for variation 0.39
Total 3.50
Cum
5.3 Columns

Page 17 of 73
S. No Description of work No. L B D Quantity
Columns excluding Plinth beam, Lintel beam
9 x 1 0.23 0.30 4.75 2.95
and Roof Beam
Add for variation 0.05
Total Total: 3.00
Cum
5.4 Lintels
Alround building over windows 3 x 1 1.68 0.23 0.23 0.27
1 x 1 3.96 0.23 0.23 0.21
1 x 1 3.05 0.23 0.23 0.16
Over Main door 2 x 1 3.43 0.23 0.23 0.36
Over Toilet Door 1 x 1 1.07 0.23 0.23 0.06
Inside building 2 x 1 1.68 0.23 0.23 0.18
Add for variation 0.06
Total 1.30
Cum
5.5 Roof Beams
building 1 x 3 8.00 0.23 0.30 1.66
1 x 1 8.21 0.23 0.30 0.57
Add for variation 0.07
Total 2.30
Cum
5.6 Roof Slab 1 x 1 8.90 8.00 0.125 8.90
Add for variation 0.10
Total 9.00
Cum
5.7 Sun Shades and Chajjas (62mm average thickness and 60 cm width)-Ground Floor

Windows 5 x 1 1.68 - - 8.40


Doors 2 x 1 3.43 - - 6.86
Toilet Door 1 x 1 1.07 - - 1.07
Add for variations 0.67
Total 17.00
RM

Page 18 of 73
S. No Description of work No. L B D Quantity

Reinforcement steel supply and labour charges for cutting, bending of HYSD steel
bars / mild steel bars of different diameters to required size and shape placing in
position with cover blocks of approved size and tying with binding wire of 20 SWG,
forming grills for reinforcement work as per approved designs and drawings,
6 providing of fan hooks with 16mm dia MS rods including cost and conveyance
charges of steel , including cost of binding wire, cover blocks, including cost of
overlaps, welding, wastage, couplings, space bars, chairs etc., all incidental &
operational charges, all labour charges etc., complete for finished item of work as
directed by the Engineer in charge .

Footings 9.50 x 50 KG/Cum 475.00


Plinth beams 3.50 x 120 KG/Cum 420.00
columns 3.00 x 130 KG/Cum 390.00
Lintel 1.30 x 100 KG/Cum 130.00
Roof beam 2.30 x 140 KG/Cum 322.00
Roof slab 9.00 x 100 KG/Cum 900.00
sunshade (17.00x0.60x0.0625=0.90cum) 0.64 x 60 KG/Cum 38.40
Add for variation 24.60
2700.00
Total 2.700
MT

Brick masonry for walls in super structure with CM(1:6) using local made bricks of
approved quality from approved source having including cost and conveyance
7 charges of cement and all materials to site, seigniorage charges etc. complete for
finished item of work as as directed by the Engineer in charge .The contractor shall
make his own arrangements for procuring the specified water through tankers.

walls 3 x 2 3.66 0.23 2.85 14.39


3 x 1 3.89 0.23 2.85 7.65
2 x 1 3.05 0.23 2.85 4.00
Steps at Door entrances 3 x 1 1.52 1.20 0.15 0.82
3 x 1 1.52 0.90 0.15 0.62
3 x 1 1.52 0.60 0.15 0.41
3 x 1 1.52 0.30 0.15 0.21
Deduct for Doors 'D' -3 x 1 1.06 0.23 2.10 -1.54
Deduct for Windows -8 x 1 1.22 0.23 1.37 -3.08
Deduct for Ventilators in W/C Room -1 x 1 0.60 0.23 0.30 -0.04
Deduct for bed blocks for fixing hold fasts of
-4 x 4 0.23 0.23 0.23 -0.19
Doors
Deduct for bed blocks at sill level of
-7 x 1 1.68 0.23 0.05 -0.14
Windows
-1 x 1 1.06 0.23 0.05 -0.01

Page 19 of 73
S. No Description of work No. L B D Quantity
Add for Parapet wall 1 x 1 33.20 0.23 0.92 7.03
Add for variation 0.37
Total 30.50
Cum

Reinforced Brick masonry for walls in super structure with CM(1:5) using local
made bricks of approved quality from approved source having minimum crushing
strength of 35 Kg/cm2 and 6mm MS steel rods 2nos at 75cm centre to centre up to
total height of the wall including cost and conveyance charges of cement but
excluding cost of steel and its fabrication charges ( steel cost will be paid separately)
9
and all materials to site, seigniorage charges, incidental and operational charges, all
labour charges, scaffolding charges, construction, mixing charges, all leads and lifts,
curing etc., complete for finished item of work as directed by the Engineer in
charge. The contractor shall make his own arrangements for procuring the specified
water through tankers.

Toilet wall 1 x 1 3.17 0.11 3.20 1.12

Add for variation 0.08


Total 1.20
Cum

Bed blocks and hold fasts using plain Cement Concrete in (1:3:6) proportion with
12mm to 20 mm graded HBG metal (50% each) from approved quarry including
cost and conveyance charges of cement , all other materials to site, all leads and lifts,
9 seigniorage charges, labour charges, laying concrete, form work, curing etc.,
complete for finished item of work as directed by the Engineer in charge. The
contractor shall make his own arrangements for procuring the specified water
through tankers.
for hold fasts of doors 4 x 4 0.23 0.23 0.23 0.19
at window sill level 7 x 1 1.68 0.23 0.05 0.14
at ventilator sill level 1 x 1 1.06 0.23 0.05 0.01
Cub board walls 5 x 1 0.30 0.12 2.10 0.38
Sump bottom 1 x 1 2.44 1.83 0.10 0.45
Below sump slab 1 x 1 10.36 0.45 0.05 0.23
0.60
Total 2.00
Cum

Page 20 of 73
S. No Description of work No. L B D Quantity

Plastering 12 mm thick in one coat for superstructurefor even faces of walls with
CM(1:5) with smooth finish at all heights including cost and conveyance charges of
cement and all other materials to site, scaffolding charges, seigniorage charges,
10 incidental and operational charges, all labour charges for mixing mortar, finishing,
all leads and lifts, curing, cutting grooves etc., complete for finished item of work
and as directed by the Engineer in charge. The contractor shall make his own
arrangements for procuring the specified water through tankers.

External walls
Walls alround including parapet wall height 1 x 2 8.00 - 4.43 70.88
1 x 2 7.70 - 4.43 68.22
Entrance steps
Treads/top 2 x 1 1.52 1.95 5.93
Risers 2 x 1 1.52 - 1.05 3.19
Sides 2 x 2 1.95 - 0.15 1.17
2 x 2 1.80 - 0.15 1.08
2 x 2 1.50 - 0.15 0.90
2 x 2 1.20 - 0.15 0.72
2 x 2 0.90 - 0.15 0.54
2 x 2 0.60 - 0.15 0.36
2 x 2 0.30 - 0.15 0.18
Deduct for Doors 'D' -3 x 1 1.06 - 2.13 -6.77
Deduct for windows 'W' -8 x 1 1.06 - 1.37 -11.62
Deduct for Ventilators 'V' -1 x 1 0.60 - 0.45 -0.27
Add for variation 0.45
Total 134.96
Sqm

Plastering 20 mm thick in for superstructure for un-even faces of walls with CM


(1:5) with sponge finish at all heights including cost and conveyance charges of
cement and all other materials to site, scaffolding charges, seigniorage charges,
11 incidental and operational charges, all labour charges for mixing mortar, finishing,
all leads and lifts, curing, cutting grooves etc., complete for finished item of work
and as directed by the Engineer in charge. The contractor shall make his own
arrangements for procuring the specified water through tankers.

Internal
Alround AE's Room 1 x 1 15.24 - 3.23 49.23
Alround SBE Room 1 x 1 13.42 - 3.23 43.35
Alround Store Room 1 x 1 15.24 - 3.23 49.23
Alround Staff Room 1 x 1 13.42 - 3.23 43.35
Alround Toilet 1 x 1 6.10 - 3.23 19.70
Top of parapet wall 1 x 1 33.80 0.25 - 8.45
Inside parapet 1 x 2 33.80 - 0.60 40.56
Deduct for Doors 'D' -1 x 2 1.06 - 2.13 -4.52

Page 21 of 73
S. No Description of work No. L B D Quantity
Deduct for Doors 'D1' -1 x 1 0.75 - 2.13 -1.60
Add for variations 0.25
Total 248.00
Sqm

Plastering to ceiling 12 mm thick in one coat in CM(1:3) with sponge finish at all
heights including cost and conveyance charges of cement and all other materials to
site, scaffolding charges, seigniorage charges, incidental and operational charges, all
12 labour charges for mixing mortar, finishing, all leads and lifts, curing, cutting
grooves etc., complete for finished item of work and as directed by the Engineer in
charge. The contractor shall make his own arrangements for procuring the specified
water through tankers.

Ceiling AE's Room 1 x 1 3.66 3.66 - 13.40


Ceiling SBE Room 1 x 1 4.27 3.66 - 15.63
Ceiling Store Room & Toilet 1 x 1 3.66 2.44 - 8.93
Ceiling Staff Room 1 x 1 4.27 3.66 - 15.63
Sun-Shades Ceiling over Windows 5 x 1 1.68 0.60 - 5.04
Sun-Shades Ceiling over Doors 2 x 1 3.43 0.6 - 4.12
Sun-Shades Ceiling over Toilet Door 1 x 1 1.07 0.6 - 0.64
Inside building Sun-Shades 1 x 2 3.96 0.6 - 4.75
1 x 2 3.05 0.6 - 3.66
Add for variations 0.20
Total 72.00
Sqm

Providing impervious coat with CM(1:3) 20 mm thick using approved waterproofing


compound over terrace including cost and conveyance charges of cement and all
other materials to site, scaffolding charges, seigniorage charges, incidental and
13 operational charges, all labour charges for mixing mortar, finishing, all leads and
lifts, curing, cutting grooves etc., complete for finished item of work and as directed
by the Engineer in charge. The contractor shall make his own arrangements for
procuring the specified water through tankers.

Over roof slab 1 x 1 7.84 8.74 68.52


Sump 1 x 1 2.44 1.83 4.46
1 x 2 2.44 2.0 4.88
1 x 2 1.83 2.0 3.66
Add for variations 0.48
Total 82.00
Sqm

Page 22 of 73
S. No Description of work No. L B D Quantity

Flooring with a bed of 100mm thick in CC (1:4:8) with 40mm & 20mm size HBG
Metal from approved quarry including cost and conveyance charges of cement and
all other materials to site, seigniorage charges, labour charges for machine mixing,
14
laying concrete, finishing top surface to the required level, curing etc., complete for
finished item of work as directed by the Engineer in charge. The contractor shall
make his own arrangements for procuring the specified water through tankers.

Flooring Concrete
AE Room 1 x 1 3.66 3.96 0.10 1.45
SBE Room 1 x 1 3.66 7.24 0.10 2.65
Store Room & Toilet 1 x 1 3.66 3.05 0.10 1.12
Add for variations 0.78
Total 6.00
Cum

Flooring with High Polished Granite 16 to 18mm thick up to 2.43M black of black
colour and design set over a base coat of CM(1:8) , 12 mm thick over CC bed
already laid with neat cement slurry of honey like consistency spread at the rate of
3.3 Kgs per Sqm and filling the joints with white cement paste mixed with pigment
of matching shade is to be done including cost and conveyance charges of cement
15
and all other materials to site, seigniorage charges, incidental and operational
charges, all labour charges for mixing mortar, finishing, all leads and lifts, etc.,
complete for finished item of work and as directed by the Engineer in charge.The
contractor shall make his own arrangements for procuring the specified water
through tankers.

Flooring of AE's Room 1 x 1 3.66 3.96 - 14.49


Skirting 1 x 1 15.24 - 0.10 1.52
Flooring of Staff Room 1 x 1 3.66 6.33 - 23.17
Skirting 1 x 1 19.98 - 0.10 2.00
Flooring of Store Room 1 x 1 3.66 2.63 - 9.63
1 x 1 1.71 1.33 2.27
Skirting 1 x 1 12.58 - 0.10 1.26
Entrance steps
Treads/top 2 x 1 1.52 1.20 3.65
Risers 2 x 1 1.52 - 1.05 3.19
Sides 2 x 2 1.95 - 0.15 1.17
2 x 2 1.80 - 0.15 1.08
2 x 2 1.50 - 0.15 0.90
2 x 2 1.20 - 0.15 0.72
2 x 2 0.90 - 0.15 0.54
2 x 2 0.60 - 0.15 0.36
2 x 2 0.30 - 0.15 0.18
Deduct for doors -1 x 3 1.06 - 0.10 -0.32
Page 23 of 73
S. No Description of work No. L B D Quantity
-1 x 1 0.75 - 0.10 -0.08
Add for variations 0.27
Total 66.00
Sqm

Flooring with Non - skid red or white full body Ceramic floor tiles of size 300 x 300
mm and thickness between 7-8mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 - 15) of any colour and finish in all shades and designs set over
base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof
16 slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, sand water and tiles etc.,
complete for finished item of work.The contractor shall make his own arrangements
for procuring the specified water through tankers.

Toilet 1 x 1 1.83 1.22 - 2.23


Riser of platform 1 x 1 1.22 - 0.15 0.18
Door offsets 1 x 1 0.75 0.25 - 0.19
Add for variations 0.40
Total 3.00
Sqm

Dadooing in toilets and bath rooms with glazed red or white fully body ceramic tiles
of size 200 x 300 mm / 245 x 325 mm and thickness 6mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and designs set over a base coat of CM(1:3) 12 mm thick with neat cement slurry of
honey like consistency spread at the rate of 3.3 Kgs per Sqm and filling the joints
17 with white cement paste mixed with pigment of matching shade is to be done
including cost and conveyance charges of cement and all other materials to site,
seigniorage charges, incidental and operational charges, all labour charges for
mixing mortar, finishing, all leads and lifts, etc., complete for finished item of
work and as directed by the Engineer in charge.The contractor shall make his own
arrangements for procuring the specified water through tankers.

Dadoing in W/C Room 1 x 1 6.10 - 1.83 11.16


Dedecut for Door -1 x 1 0.75 - 1.83 -1.37
Add for variations 0.21
Total 10.00
Sqm

Supplying & fixing Flush door shutters, solid bond wood block board type with teak
ply on both faces.: 30 mmthick conforming to IS:2202 including providing special
18
PVC braket on hinge side, etc complete as per direction of Engineer–in–charge,
manufacturers specification.

Door Shutters 3 x 1 0.94 - 2.07 5.84


Add for variations 0.16

Page 24 of 73
S. No Description of work No. L B D Quantity
Total 6.00
Sqm

Providing and fixing factory made solid Wood Polymer Composite (WPC) single
extruded Door Frame section of size with encapsulation of 8MM rigid layer on all
the six surfaces. The door frame will have a rebat of 32MM. Door Frame section of
63.5x100 MM.The two Vertical members are to be joined together with the
horizontal member using 8x75 MM long MS Star full thread screws to be used with
19
reverse forward speed control hand drilling machine. The ready/assembled door
frame is fixed to the wall using hold fast or bolt fasteners. A minimum of 4 No of
screws to be provided for each vertical member & minimum 2no for horizontal
member. The price inclusive of all material at site complete for finished item of
work as directed by the Engineer in charge.

Door shutter of W/C Room 3 x 1 6.28 - 18.84


Toilet door 1 x 1 5.64 - 5.64
Add for variations 0.24
Total 24.72
RM

Supplying & fixing Flush door shutters, 28 -30 MM thick solid Wood Polymer
Composite(WPC) single extruded door shutter with 3MM top and bottom rigid layer
with an overall density of 750kg/Cum. It will be fixed to the frame using 3 inch /4
20
inch hinges. A minimum of 4 hinges will be required for fixing the door with the
frame including cost and conveyance of all materials and labour charges , etc
complete as per direction of Engineer–in–charge, manufacturers specification.

Toilet door 1 x 1 0.75 - 2.07 1.55


Add for variations 0.45
Total 2.00
Sqm

Page 25 of 73
S. No Description of work No. L B D Quantity
Providing and fixing factory made uPVC white colour sliding glazed window upto
1.50 m in height dimension comprising of uPVC multi-chamberedframe with in-built
roller track and sash extruded profiles duly reinforcedwith 1.60 ± 0.2 mm thick
galvanized mild steel section made from rollforming process of required length
(shape & size according to uPVCprofile), appropriate dimension of uPVC extruded
glazing beads andu PVC extruded interlocks, EPDM gasket, wool pile, zinc alloy
(white powder coated) touch locks with hook, zinc alloy body with single
nylonrollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8 mm size for
fixing frame to finished wall and necessary stainless steel screwsetc. Profile of frame
21
& sash shall be mitred cut and fusion welded at allcorners, including drilling of holes
for fixing hardware's and drainage ofwater etc. After fixing frame the gap between
frame and adjacent finishedwall shall be filled with weather proof silicon sealent
over backer rod of required size and of approved quality, all complete as per
approved drawing& direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes, wire mesh and silicon sealent .
Note: For uPVC frame and sash extruded profiles minus 5% tolerancein dimension
i.e. in depth & width of profile shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment on this account shall be made.
Windows 7 x 1 1.22 1.37 - 11.70
Ventilator 1 x 1 0.60 0.45 - 0.27
Add for variations 1.03
Total 13.00
Sqm

Supply and fixing of MS grill for Stair case hand rail,gates etc. of different sizes
including cost and conveyance of all the materials, fabrication charges,fixing
22 charges, labour charges and painting with two coats of synthetic enamel paint over
one coat of primer etc., complete for finished item of work as directed by the
Engineer-in-charge.

Ventilators @ 15Kg/1Sqm 1 x 1 0.60 0.45 10 2.70


Windows @ 30Kg/1Sqm 7 x 1 1.22 1.37 20 234.00
For Removable Ladder
100 x 50 x 4mm (RHS) Rectangular Steel
1 x 4 5.79 8.86 205.24
Hollow Section (8.86 Kg/m)
Add for variations 0.06
442.00
Kgs

Page 26 of 73
S. No Description of work No. L B D Quantity

Painting the walls (Inside) and ceiling with two coats of Plastic emulsion paint
grade-I of Asian make over one coat of primer of approved colour, make and shade
over one coat of white cement primer including cost and conveyance of all materials
to site, water to site, cost of brushes, scaffolding charges, all labour charges, curing,
23
tools and plant, incidental charges, all leads and lifts etc at all heights of all floors
complete for finished item of work and as directed by the Engineer in charge.The
contractor shall make his own arrangements for procuring the specified water
through tankers.

Ceilings vide item no.12 above 72.00


Internal
Alround AE's Room 1 x 1 15.24 - 3.23 49.23
Alround SBE Room 1 x 1 13.42 - 3.23 43.35
Alround Store Room 1 x 1 15.24 - 3.23 49.23
Alround Staff Room 1 x 1 13.42 - 3.23 43.35
Alround Toilet 1 x 1 6.10 - 3.23 19.70
Deduct for Doors 'D' -1 x 1 1.06 - 2.13 -2.26
Deduct for Doors 'D1' inside -1 x 1 0.75 - 0.30 -0.22
Deduct for Doors 'D1' outside -1 x 1 0.75 - 2.13 -1.60
Deduct for two sides of opening -2 x 1 1.10 - 2.13 -4.69
Add for variations 3.91
Total 272.00
Sqm

Painting to walls (out side) with two coats of Weather proof acrylic exterior
emulsion or equivalent quality paint of approved colour, make and shade over one
coat of white cement primer including cost and conveyance of all materials, water to
24 site, cost of brushes, scaffolding charges, all labour charges, curing, tools and plant,
incidental charges, all leads and lifts etc at all heights of all floors complete for
finished item of work and as directed by the Engineer in charge.The contractor shall
make his own arrangements for procuring the specified water through tankers.

External walls
Walls alround including parapet wall height 1 x 2 8.00 - 4.43 70.88
1 x 2 7.70 - 4.43 68.22
Deduct for windows 'W' -7 x 1 1.06 - 1.37 -10.17
Deduct for Ventilators 'V1' -1 x 1 0.60 - 0.45 -0.27
External side of septic tank wall for a height
1 x 1 9.16 - 0.58 5.31
of 0.45mtr+slab thickness
Top of Sun-Shades alround building 5 x 1 1.22 0.60 - 3.66
Doors 2 x 1 3.43 0.6 - 4.12
Toilet Door 1 x 1 1.07 0.6 - 0.64
Top of parapet wall 1 x 1 33.20 0.25 - 8.30
Inside parapet 1 x 1 33.80 - 0.60 20.28
Add for variations 3.88
Page 27 of 73
S. No Description of work No. L B D Quantity
Total 174.85
Sqm

Painting new iron work with Synthetic enamel paints 2 coats over a coat of approved
red oxide primer making 3 coats in all to give an even shade including cost and
25
conveyance of all materials to work site and all operational, incidental, labour
charges etc., complete for finished item of work..

Window grills 7 x 1 1.22 1.37 11.70


Ventilator Grills 1 x 1 0.60 0.45 - 0.27
Add for variations 0.03
Total 12.00
Sqm

Painting new wood work with Synthetic enamel paints 2 coats over a coat of
approved wood primer making 3 coats in all to give an even shade including cost and
26
conveyance of all materials to work site and all operational, incidental, labour
charges etc., complete for finished item of work..

Main Doors 4 x 2 1.06 - 2.13 18.06


Door for Toilet 1 x 2 0.75 - 2.13 3.20
Add for variations 0.74
Total 22.00
Sqm
Supplying & fixing of 110mm dia. Rain water down take pipe with PVC Pipes of
27 Prince or sudhakar or equivalent make including cost and conveyance of PVC
Pipes, specials, labour charges etc complete.
Rain water down take pipe 2 x 1 3.66 7.32
Add for variation 0.18
Total 7.50
RM
Supply and fixing of 25mm outer dia heavy (2.10mm thickness) regid PVC pipe ( ISI
28 mark) concealed in wall with all required accessories including masonry work and
labour charges complete
In roof slab for wiring
AE room 1 x 1 4.92 4.92
1 x 1 4.31 4.31
SBE Room 1 x 1 4.92 4.92
1 x 1 4.31 4.31

Staff Room 1 x 1 4.31 4.31

1 x 1 4.31 4.31

Page 28 of 73
S. No Description of work No. L B D Quantity

Store Room & Toilet 1 x 1 4.31 4.31

1 x 1 4.31 4.31
For D.B from slab 1 x 1 1.80 1.80
In alround walls for computer circuilts from
1 x 1 40.00 40.00
DB to computer points
In alround walls for house wiring from DB to
1 x 1 35.00 35.00
wiring points and switch board
Add for variation 0.50
Total 113.00
RM

Wiring with 2 runs of 14/0.3mm (1.0 sqmm) FRLS/HFFR PVC insulated 1100V
grade as per IS: 694/1990 specification for Copper cable of makes Finolex / RR
Kabel / KEI 6A /10A Modular switch of Legrand Arteor / MK Blenge / Schneider
29
Zen Celo , ceiling rose, suitable hot dip Galvanized metal box with cover frame to
switch control box including all labour chages etc. complete for light, bell, fan and
exhaust fan points for finished item of work as directed by the Engineer-in-charge.

Tube lights
AE room 2 x 1 - - - 2
SBE Room 2 x 1 - - - 2
Staff Room 2 x 1 - - - 2
Store Room & Toilet 2 x 1 - - - 2
Open Area in front of W/c Room 1 x 1 - - - 1
Fan
AE room 1 x 1 - - - 1
SBE Room 1 x 1 - - - 1
Staff Room 1 x 1 - - - 1
Exhast Fan @ Toilet 1 x 1 - - - 1
Ceiling Rose/Batten Holders 4 x 1 - - - 4
Bulk head fittings outside building 4 x 1 - - - 4
Add for variations 1
Total 22.00
Nos

Supply and fixing of 6A /10A 3/2 Pin Modular Socket with shutter of Legrand
Arteor / MK Blenge / Schneider Zen Celo with switch control of 6A /10A Modular
30
switch of Legrand Arteor / MK Blenge / Schneider Zen Celo with earth continuity
including wire leads, earth connections along with all labour charges etc., complete.

Page 29 of 73
S. No Description of work No. L B D Quantity
30.1 Independent Mounting
AE room 1 x 3 - - - 3
SBE Room 1 x 3 - - - 3
Staff Room 1 x 3 - - - 3
Total 9
No
30.2 Dependent Mounting
AE room 1 x 1 - - - 1
SBE Room 1 x 1 - - - 1
Staff Room 1 x 1 - - - 1
Total 3
No
Supply and run of 2 of 36/0.3 mm (2.5 sqmm) FRLS / HFFR PVC insulated 1100V
31 grade as per IS:694/1990 specification for Copper cable of makes Finolex / RR
Kabel / KEI in existing pipe for mains including all labour charges complete.
from DB to common switch boards in every
room
AE room 1 x 1 15.00 - - 15.00
SBE Room 1 x 1 10.00 - - 10.00
Staff Room 1 x 1 5.00 - - 5.00
Store Room 1 x 1 5.00 - - 5.00
W/C Room 1 x 1 20.00 - - 20.00
Computer Circuit from DB to Computer
1 x 1 30.00 - - 30.00
Points
Total 85.00

RM
Supply and run of 1 of 14/0.3mm (1.0 sqmm) FRLS/HFFR PVC insulated 1100V
grade as per IS: 694/1990 specification for Copper cable of makes Finolex / RR
32
Kabel / KEI in existing pipe for earth continuity including all labour charges
complete.
1 x 6 5.00 - - 30.00
Total 30.00
RM
Supply and run of 2 of 56/0.3mm (4.0 Sqmm) FRLS / HFFR PVC insulated 1100V
33 grade as per IS:694/1990 specification for Copper cable of makes Finolex / RR
Kabel / KEI in existing pipe for mains including all labour charges complete.
1 x 1 10.00 - - 10.00
Total 10.00
RM

Page 30 of 73
S. No Description of work No. L B D Quantity
Supply and run of 1 of 36/0.3 mm (2.5 sqmm) FRLS / HFFR PVC insulated 1100V
grade as per IS:694/1990 specification for Copper cable of makes Finolex / RR
34
Kabel / KEI in existing pipe for earth continuity including all labour charges
complete.
1 x 1 10.00 - - 10.00
Total 10.00
RM
Supply and fixing of 4-way VTPN Distribution board suitable for accommodating 4
pole Isolator as incomer with IP 43 Protection as per IS:13032 and suitable for 4Nos
T.P.outgoings etc., complete of makes Legrand / Schneider including cost of D.B.,
35 1No.63A FP isolator, 12 Nos. 6-32A 10KA SP MCBs of make Legrand / 1
Schneider., giving all internal connections and labour charges for surface/flush
mounting etc. complete for finished item of work as directed by the Engineer-in-
charge.
No.

Supply of 10 Sqmm WPTC (Weather Proof Twin Core) ISI Alluminium Wire.
Makes: Gold Medal / Million / GM / Vimal / Finecab / Nakoda / Nanadicab / Payal /
36 30
Fybros by Kundan cab.in existing pipe for mains including all labour charges
complete for finished item of work and as directed by the Engineer in charge.

RM

Providing fuse carrier board comprises of 3Nos porcelain fuse carriers 63Amp/415V
with HRC fuses assembled over 10"x7" teak wood peeta board fixed to wall surface
37 with incoming from electric pole and out going to distribution board as per relevant 1
standard specifications including cost and conveyance of all materials, screws, nails
and labour charges etc., complete for finished item of work.

No.

Supply and Transportation of 20W, T8,1200mm length LED retrofit tube light, input
voltage AC 220 - 260 Volts with PF>0.9, Surge protection: 2KV,THD<10%, with
inbuilt driver and frosted cover CCT: 3000K - 5700K, minimum CRI>70, .etc.,
38 complete as per IS 10322 (Part 5/ Sec 1)..2012 Makes: Wipro / Phillips / GE /
Crompton / Bajaj / VIN b) LED MAKE : PHILIPS LUMILEDS / CREE / NICHIA /
OSRAM / SAMSUNG.t including cost and conveyance of all materials and labour
complete for finished item of work as directed by Engineer - In - Charge

Tube lights
AE room 2 x 1 - - - 2
SBE Room 2 x 1 - - - 2
Staff Room 2 x 1 - - - 2
Store Room 2 x 1 - - - 2
Front side 2 x 1 - - - 2
Total 10

Page 31 of 73
S. No Description of work No. L B D Quantity
No
Supply and fixing of batten holder/ slanting holder in lieu of ceiling rose of light
39 point complete with all connections and labour charges, cost of 40 W bulb etc.,
complete for finished item of work.
Batten Holders in rooms 4 x 1 - - - 4
W/c Room 1 x 1 - - - 1
Total 5
No
Supply and fixing of CEILING fan of 48" Sweep, 5 Star rated Ceiling Fan, with
double ball bearings, power input not more than 53W, air delivery more than 218
40 cubic meter/min and service value 4.11 with stepped type electronic regulator
including cost and conveyance of all materials and labour charges complete for
finished item of work as directed by the Engineer-in-Charge.

Ceiling fans
AE room 1 x 1 - - - 1
SBE Room 1 x 1 - - - 1
Staff Room 1 x 1 - - - 1
Total 3
No
Providing Independent earthing by excavating a trench to a depth of 2.70M in all
soils as per size specified in the data using 75mm dia CI(spun) pipe of 3.00Mtr
41 length with necessary accessories with humepipe ring duly providing stagered holes
including filling with equal proportion of salt and charchol in layers and all labour
charges etc. complete for small finished item of work.
for section office building 1 x 1 - - - 1
Total 1
No
Supply of Polyethylene water storage tank double layer conforming to IS:12701 -
42 1996 of 500 Ltr capacity with lid including cost and conveyance of all materials,
labour charges etc., complete for finished item of work
Over section office 1 x 1 - - - 1
Total: 1
No.

Supply and fixing of different dia.Unplasticised PVC Pipes,10 kg/cm2 for potable
water supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket)
as per specification in light Grey/Natural Ivory Grey/ Any other Color including
43
Labour charges for laying, fixing, and commissioning the pipes including couplers,
bends, plugs, junctions, tees etc. with solvent jointing as per Standard practice for
finished item work as directed by the Engineer-in-charge..

Page 32 of 73
S. No Description of work No. L B D Quantity

44.1 25mm dia UPVC pipe


from Borw well to over head tank 1 x 1 40.00 - - 40.00
Over head tank to Toilet 1 x 1 8.00 - - 8.00
48.00
RM
44.2 20mm dia UPVC pipe
internal connections in toilet 1 x 1 10.00 - - 10.00
Add for variatoins 5.00
Total: 15.00
RM
Supply and fixing of 25mm GM Gate (GM peet) valves as per IS 778 Class I -Indian
make heavy type of different sizes including cost and conveyance of all materials
44
and labour Charges complete for finished item work as directed by the Engineer-in-
charge..
A 25mm GM Gate Valves
at Bore & Motor 1 x 2 - - - 2
in the line of water storage tank to toilets 1 x 1 - - - 1
Total: 3
No.
Supply and fixing of CP Long body bib cock fancy type delux heavy duty 12.7mm
dia Indian make Seiko / Senior / Nice or equivalent including cost and conveyance of
45
all materials, labour charges etc., complete for finished item of work as directed by
the Engineer - In - Charge
in toilets 1 x 1 - - - 1
Total: 1
No.
Supply and fixing of CP Short body bib cock fancy type delux heavy duty 12.7mm
dia Indian make Seiko / Senior / Nice or equivalent including cost and conveyance of
46
all materials, labour charges etc., complete for finished item of work as directed by
the Engineer - In - Charge
in toilets 1 x 2 - - - 2
outside building 1 x 1 - - - 1
Total: 3
No.

Supply and fixing of Angle stop cock 12.7 mm dia first quality Indian make heavy
duty Seiko / Senior / Nice or equivalent including cost and conveyance of all
47
materials, labour charges etc., complete for finished item of work as directed by the
Engineer - In - Charge

for flush tanks of ewc's in toilets 1 x 1 - - - 1


for wash hand basins 1 x 1 - - - 1

Page 33 of 73
S. No Description of work No. L B D Quantity
Total: 2
No.

Supplying and fixing colour glazed porcelain European type Parry ware make or
equivalent quality water closets with ISI make, P or S trap including cost and
48 conveyance of water closet, P or S trap, plastic seat and lid and all other materials,
labour charges for fixing etc., complete for finished item of work as directed by the
Engineer in charge of work

W/C 1 x 1 - - - 1
Total: 1
No.
Supplying and fixing of PVC flushing tank of parry ware make or equivalent ISI
make with all fixtures including cost and conveyance of tank and all other materials,
49
labour charges for fixing etc., complete for finished item of work as directed by the
Engineer in charge of work
W/C 1 x 1 - - - 1
Total: 1
No.

Supplying and fixing (550mm x 400 mm) Indian make Flat back wash hand
basin(HSW/ Parryware/Neycer) 1st quality conforming to IS:2556-Part-4:1972 with
waste fittings like rubber plug, chain,32 mm nominal size C.P.Fitting with parallel
pipe thread confirming to IS:2963-1979 and fitting with 15 mm nominal bore
50
Chromium plated pillar tap of 1st quality Indian make 400gms Seiko / Senior /
Nice / Esso or equivalent complete with standard CI brackets including wooden
block etc. complete for finished item of work as directed by the Engineer in charge
of work

W/C Room 1 x 1 - - - 1
Total: 1
No.
Supply and fixing of 12.7mm dia UPVC Health faucet of ISI make WATER-TECH
51
or equivalent
W/C 1 x 1 - - - 1
Total: 1
No.
Supply & Fixing 12.7mm PVC connection with brass union nut C.P.Coated
52 including cost and conveyance of all materials and labour charges complete for
finished item of work as directed by the Engineer - in - charge
for hand wash basin and W/C 1 x 2 - - - 2
Total: 2
No.

Page 34 of 73
S. No Description of work No. L B D Quantity
Supply & Fixing 31.75mm dia PVC flexibile waste pipe of 914.40mm length of 1st
53 quality including cost and conveyance of all materials and labour charges complete
for finished item of work as directed by the Engineer - in - charge
for hand wash basin 1 x 1 - - - 1
Total: 1
No.

Supplying & fixing in walls,ground different


dia PVC Pipes of Prince or sudhakar or
54 equivalent make for sewer lines including
cost and conveyance of PVC Pipes, specials,
PVC cowls labour charges etc complete…

55.1 110mm dia.(6 kg/cm2)


for ewc's lines to outside man holes 1 x 1 2.00 - - 2.00
from man hole to septic tank 1 x 1 10.00 - - 10.00
Add for variations 2.00
Total: 14.00
RM
55.2 75mm dia.(6 kg/cm2)
for urinals and wash hand basins lines 1 x 1 3.00 - - 3.00
from man hole to dispose the water to outside
1 x 1 25.00 - - 25.00
drain
Add for variations 2.00
Total: 30.00
RM
Supply and Fixing of 100mm Nahani traps of Prince/sudhakar or any ISI brand
55 including cost and conveyance of all materials, labour charges etc., complete for
finished item of work as directed by the Engineer - In - Charge
in W/C Room 1 x 2 - - - 2
Total: 2
No.
Construction of Manholes of size 457.2x457.2mm brick in CM(1:6) proportion
masonary Inspection chamber upto 914.4mm depth and fitted with suitable CI frame
and cover of 20 kg including cost and conveyance of all materials, labour charges
56
etc., complete for finished item of work as directed by the Engineer - In - Charge.
The contractor shall make his own arrangements for procuring the specified water
through tankers.
for ewc line 1 x 1 - - - 1
Total: 1
No.

Page 35 of 73
S. No Description of work No. L B D Quantity
Providing 15mm thick moulded cement mortar bands in cement mortar 1:4
(1Cement:4Sand) upto 300mm in width including cost and conveyance charges of
57
cement and all materials to site, seigniorage charges etc., complete for finished item
of work as directed by the Engineer - in - Charge.
A 10.00cm wide raised band
Alround building at parapet level 1 x 1 33.26 - - 33.26
Add for variations 0.74
Total 34.00
RM
B 4.00cm wide raised band
Over sunshades at bottom on front side as
8 x 1 2.88 - - 23.04
water band
Add for variations 0.96
Total 24.00
RM
Providing name boards to office buildings on wall surface of the buildings with two
coats of Synthetic Enamel Paint of approved quality, colour and shade painted over a
58 coat of primer of approved quality including cost and conveyance of all materials,
labour charges, leads and lifts, scaffolding charges etc., complete for finished item of
work.
Front side for section office 1 x 1 8.01 0.90 - 7.21
Add for variations 0.29
Total 7.50
Sqm
Construction of soak pit with 4' dia RCM rings upto a depth of 5' including cost and
59
conveyance of all materials
1x 1 - - - 1.00
No

Supply and laying Polished black Kadapa slabs of all sizes between 25 -30mm
thickness as shelf slabs including cost of all materials like cement, sand, and water
60
and flooring stones etc., complete, including seigniorage charges, labour charges for
dressing of flooring stones etc., complete for finished item of work.

SBE rom 1 x 4 1.83 0.45 - 3.29


AE room 1 x 4 2.74 0.45 - 4.94
Store Room 1 x 4 8.50 0.45 - 15.30
Add for variations 0.47
Total: 24.00
Sqm

Page 36 of 73
Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in
Nandyal Division of Operation Circle, Kurnool
DATA 2023-24
Sl No Qty Description Rate Unit in Amount
1 2 3 4 5 6 7 8 9

Earth work excavation in foundations for building, septic tank, water sump and for levelling
and depositing the earth on banks with a initial lead of 10 mt and a lift of 2 mt in mixture of
gravel, soft disintegrated rock like shales, ordinary gravel, stoney earth and earth mixed with
1
fair sized boulders including all leads and lifts, tools and plants, labour, disposal of excess
excavted earth etc., complete for finished item of work as directed by the Engineer in
charge.

Unit:1Cum
Taking Output:10 cum
Material 0.00
Labour
3.64 Nos Mazdoor(Unskilled) 560.00 1 No. 2,038.40
Add 75% extra for foundations 1,528.80
3,567.20
Add towards C.P & O.H 4% 142.69
Rate/ 10 cum 3,709.89
Rate/1Cum 370.99 371.00
Filling with sand, below and sides of foundations and basement in layers not exceeding
15cm thick, consolidating each deposited layer by watering and ramming including cost and
2 conveyance of all materials, labour charges, hire charges of T&P, all leads and lifts etc.,
complete for finished item of work as directed by the Engineer in charge. The contractor
shall make his own arrangements for procuring the specified water through tankers.
Unit: 1Cum
Material
1.00 cum Sand for filling 1,465.90 1 cum 1,465.90
Add towards C.P & O.H 4% 58.64
Total Material cost/1Cum 1,524.54 1,525.00
Labour ( Filling charges )
0.052 No Mazdoor(Unskilled) 560.00 1 No. 28.93
Add towards C.P & O.H 4% 1.16
Total Labour charges/1Cum 30.09 30.00
Rate/1Cum 1,555.00

Plain Cement Concrete in (1:4:8) proportion for leveling course in foundations using 40mm
size HBG metal from approved quarry including cost and conveyance charges of cement
and all other materials to site, all leads and lifts, seigniorage charges, dewatering, labour
3 charges, machine mixing, laying concrete, ramming in 15 cm thick layers, finishing top
surface to the required level, curing etc., complete for finished item of work as directed by
the Engineer in charge. The contractor shall make his own arrangements for procuring the
specified water through tankers.

Unit: 1Cum
Material
0.90 cum 40mm HBG metal 1,473.70 1 cum 1,326.33
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
162.00 kg cement 4.22 1 kg 683.64
2,734.88
Page 37 of 73
Add towards C.P & O.H 4% 109.40
Total Material cost/1Cum 2,844.28 2,844.00
Labour
1.00 cum labour charges as per labour chart 1,388.60 1 cum 1,388.60
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1,906.80
Add towards C.P & O.H 4% 76.27
Total Labour charges/1Cum 1,983.07 1,983.00
Rate/1Cum 4,827.00

Random Rubble stone Masonry in CM(1:6) using Hard granite stones from approved quarry
including cost and conveyance charges of cement and all other materials to site and
including cost of seigniorage charges, labour charges for cutting stones to required size and
4
shape, mixing of cement mortar, dewatering charges, scaffolding, curing , all leads and lifts
etc complete for finished item of work as directed by the Engineer in charge .The contractor
shall make his own arrangements for procuring the specified water through tankers.

Unit-1cum
Material
79.20 Kg Cement 4.22 1 kg 334.22
0.3300 Cum Sand for mortar 1,726.90 1 cum 569.88

0.94 Cum Rough stone 1,016.80 1 cum 955.79

Bond stones of Min.size 0.25 X 0.25 X


7.00 No. 47.60 1 No. 333.20
0.45 to 0.60m rate vide MAT-00417

2,193.09
Add towards C.P & O.H 4% 87.72
Total Material cost 2,280.81 2,281.00
Labour
1.00 cum labour charges as per labour chart 1,924.00 1 cum 1,924.00
Add towards C.P & O.H 4% 76.96
Total Labour charges 2,000.96 2,001.00
Rate/1cum 4,282.00

RCC Footings, plinth beams, walls, columns, beams, lintles, roof slab, stair case slab and
sun shades by laying vibrated R.C.C M20 grade design mix using 12mm to 20mm size
graded HBG machine crushed metal (50% each) from approved quarry and a minimum of
400 Kgs of cement for 1 Cum of concrete including cost and conveyance charges of cement
5 and all other materials to site, scaffolding charges, centering, shuttering, machine mixing,
laying concrete, curing, vibrating, all incidental and operational charges, all leads and lifts
etc., but excluding cost of steel and its fabrication complete for finished item of work as
directed by the Engineer in charge. The contractor shall make his own arrangements for
procuring the specified water through tankers.

Index Code No:BLD-CSTN-3-13


Basic cost For Footings&Plinth Beams
5.1 Footings
Unit: 1Cum
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
Page 38 of 73
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
1.00 cum Material 301.00 1 cum 301.00
4,457.84
Add towards C.P & O.H 4% 178.31
Total Material cost/1Cum 4,636.15 4,636.00
Labour
1.00 cum Labour charges 2,266.65 1 cum 2,266.65
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1.00 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 274.40
Centering Charges
1.00 cum labour 672.00 1 cum 672.00
3,731.25
Add towards C.P & O.H 4% 149.25
Total Labour charges/1Cum 3,880.50 3,880.00
Rate/1Cum 8,516.00
5.2 Plinth Beam
Unit: 1Cum
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
1.00 cum Material 1,453.00 1 cum 1,453.00
5,609.84
Add towards C.P & O.H 4% 224.39
Total Material cost/1Cum 5,834.23 5,834.00
Labour
1.00 cum Labour charges 2,266.65 1 cum 2,266.65
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1.00 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 274.40
Centering Charges
1.00 cum labour 1,620.00 1 cum 1,620.00
4,679.25
Add towards C.P & O.H 4% 187.17
Total Labour charges/1Cum 4,866.42 4,866.00
Rate/1Cum 10,700.00
Basic Cost For Columns, RCC walls,
Water tank & lintels
5.3 Columns
Unit: 1Cum
Materials
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
1.00 cum Material 249.00 1 cum 249.00
4,405.84
Add towards C.P & O.H 4% 176.23
Page 39 of 73
Total Material cost/1Cum 4,582.07 4,582.00
Labour
1.00 cum Labour charges 2,844.93 1 cum 2,844.93
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1.00 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 274.40
Centering Charges
1.00 cum labour 1,871.00 1 cum 1,871.00
5,508.53
Add towards C.P & O.H 4% 220.34
Total Labour charges/1Cum 5,728.87 5,729.00
Rate/1Cum 10,311.00
5.4 Lintels
Unit: 1Cum
Materials
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
1.00 cum Material 826.00 1 cum 826.00
4,982.84
Add towards C.P & O.H 4% 199.31
Total Material cost/1Cum 5,182.15 5,182.00
Labour
1.00 cum Labour charges 2,844.93 1 cum 2,844.93
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1.00 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 274.40
Centering Charges
1.00 cum labour 1,332.00 1 cum 1,332.00
4,969.53
Add towards C.P & O.H 4% 198.78
Total Labour charges/1Cum 5,168.30 5,168.00
Rate/1Cum 10,350.00
5.5 Beams
Unit: 1Cum
Materials
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
1.00 cum Material 1,458.00 1 cum 1,458.00
5,614.84
Add towards C.P & O.H 4% 224.59
Total Material cost/1Cum 5,839.43 5,839.00
Labour
1.00 cum Labour charges 1,525.36 1 cum 1,525.36
Machinary
0.267 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 138.36
0.267 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 73.26
Page 40 of 73
Centering Charges
1.00 cum labour 1,569.00 1 cum 1,569.00
3,305.98
Add towards C.P & O.H 4% 132.24
Total Labour charges/1Cum 3,438.22 3,438.00
Rate/1Cum 9,277.00
5.6 Slabs 125mm thick
Unit: 1Cum
Materials
0.45 cum 20mm HBG Metal 2,095.70 1 cum 943.06
0.45 cum 12 mm HBG Metal 1,779.70 1 cum 800.87
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
400.00 kg Cement 4.22 1 kg 1,688.00
Centering Charges
8.00 Sqm Material 165.00 1 cum 1,320.00
5,476.84
Add towards C.P & O.H 4% 219.07
Total Material cost/1Cum 5,695.91 5,696.00
Labour
1.00 cum Labour charges 1,525.36 1 cum 1,525.36
Machinary
0.267 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 138.36
0.267 hr Needle vibrator 40 mm ( petrol ) 274.40 1 hr 73.26
Centering Charges
8.00 Sqm labour 186.00 1 cum 1,488.00
3,224.98
Add towards C.P & O.H 4% 129.00
Total Labour charges/1Cum 3,353.98 3,354.00
Rate/1Cum 9,050.00

Sun shades and chajjas (62mm


5.7
average thickness and 60 cm width)

Unit:1RM
0.0167 cum 20mm HBG Metal 2,095.70 1 cum 35.08
0.0167 cum 12 mm HBG Metal 1,779.70 1 cum 29.79
0.0167 cum Sand for concrete 1,610.90 1 cum 26.97
14.88 kg Cement 4.22 1 kg 62.79
Centering Charges
0.60 Sqm Material 163.00 1 Sqm 97.80
252.43
Add towards C.P & O.H 4% 10.10
Total Material cost/1RM 262.53 263.00
Labour
0.0372 cum Concrete mixer 300 / 200 ( diesel) 518.20 1 cum 19.28
0.0372 cum Needle vibrator 40 mm ( petrol ) 274.40 1 cum 10.21
Centering Charges
0.0167 cum labour 2,844.93 1 hr 47.62
Centering Charges
0.60 Sqm labour 240.00 1 Sqm 144.00
221.11
Add towards C.P & O.H 4% 8.84

Page 41 of 73
Total Labour charges/1RM 229.95 230.00
Rate/1RM 493.00

Reinforcement steel supply and labour charges for cutting, bending of HYSD steel bars /
mild steel bars of different diameters to required size and shape placing in position with
cover blocks of approved size and tying with binding wire of 20 SWG, forming grills for
reinforcement work as per approved designs and drawings, providing of fan hooks with
6
16mm dia MS rods including cost and conveyance charges of steel , including cost of
binding wire, cover blocks, including cost of overlaps, welding, wastage, couplings, space
bars, chairs etc., all incidental & operational charges, all labour charges etc., complete for
finished item of work as directed by the Engineer in charge .

Index Code No:BLD-CSTN-4-1


Unit:1 MT
Material
HYSD bars including 5% for Overlaps
1.05 MT 64,769.80 1 MT 68,008.29
and wastages.
6.00 Kg Binding wire (MAT-00003) 70.00 1 KG 420.00
68,428.29
Add towards C.P & O.H 4% 2,737.13
Total Material cost/1MT 71,165.42 71,165.00
Labour charges
10.00 Nos Bar bender 800.00 1 No. 8,000.00
10.00 Nos Mazdoor (Unskilled) 560.00 1 No. 5,600.00
13,600.00
Add Area Allowence 0% 0.00
Add towards C.P & O.H 4% 544.00
Total Labour Charges/1MT 14,144.00 14,144.00
Rate / 1 MT 85,309.00
Brick masonry for walls in super structure with CM(1:6) using local made bricks of
BLD- approved quality from approved source having including cost and conveyance charges of
7 CSTN-5- cement and all materials to site, seigniorage charges etc. complete for finished item of work
9 as as directed by the Engineer in charge .The contractor shall make his own arrangements for
procuring the specified water through tankers.
UNIT: 1Cum
Material
512.00 Nos Cost of bricks 9,166.50 1000 Nos 4,693.25
48.00 Kg Cement 4.22 1 cum 202.56
0.20 cum Sand 1,726.90 1 cum 345.38
5,241.19
Add towards C.P & O.H 4% 209.65
Total Material cost/1Cum 5,450.84 5,451.00
Labour
1.00 cum Labour charges 1,558.00 1 cum 1,558.00
1,558.00
Add towards C.P & O.H 4% 62.32
Total Labour charges/1Cum 1,620.32 1,620.00
Rate/ 1Cum 7,071.00

Page 42 of 73
Reinforced Brick masonry for walls in super structure with CM(1:6) using local made bricks
of approved quality from approved source having minimum crushing strength of 35 Kg/cm2
and 6mm MS steel rods 2nos at 75cm centre to centre up to total height of the wall including
BLD- cost and conveyance charges of cement but excluding cost of steel and its fabrication
8 CSTN-5- charges ( steel cost will be paid separately) and all materials to site, seigniorage charges,
12 incidental and operational charges, all labour charges, scaffolding charges, construction,
mixing charges, all leads and lifts, curing etc., complete for finished item of work as
directed by the Engineer in charge. The contractor shall make his own arrangements for
procuring the specified water through tankers.

UNIT: 1 cum
Material
512.00 Nos Cost of bricks 9,166.50 1000 nos 4,693.25
48.00 Kg Cement 4.22 1 cum 202.56
0.200 cum Sand 1,726.90 1 cum 345.38
5,241.19
Add towards C.P & O.H 4% 209.65
Total Material cost/1Cum 5,450.84 5,451.00
Labour
1.00 cum Labour charges 2,305.00 1 cum 2,305.00
2,305.00
Add towards C.P & O.H 4% 92.20
Total Labour charges/1Cum 2,397.20 2,397.00
Rate/ 1Cum 7,848.00
Bed blocks and hold fasts using plain Cement Concrete in (1:3:6) proportion with 12mm to
20 mm graded HBG metal (50% each) from approved quarry including cost and conveyance
charges of cement , all other materials to site, all leads and lifts, seigniorage charges, labour
9
charges, laying concrete, form work, curing etc., complete for finished item of work as
directed by the Engineer in charge. The contractor shall make his own arrangements for
procuring the specified water through tankers.
Unit-1cum
Material
0.45 cum 12mm HBG metal 1,779.70 1 cum 800.87
0.45 cum 20mm HBG metal 2,095.70 1 cum 943.06
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
220.00 kg Cement 4.22 1 Kg 928.40
3,397.24
Add towards C.P & O.H 4% 135.89
Total Material cost/1Cum 3,533.13 3,533.00
Labour
1.00 cum Labour charges 1,388.60 1 cum 1,388.60
1,388.60
Add towards C.P & O.H 4% 55.54
Total Labour charges/1Cum 1,444.14 1,444.00
Rate /1Cum 4,977.00

Page 43 of 73
Plastering 12 mm thick in one coat for superstructurefor even faces of walls with CM(1:5)
with smooth finish at all heights including cost and conveyance charges of cement and all
other materials to site, scaffolding charges, seigniorage charges, incidental and operational
10 charges, all labour charges for mixing mortar, finishing, all leads and lifts, curing, cutting
grooves etc., complete for finished item of work and as directed by the Engineer in charge.
The contractor shall make his own arrangements for procuring the specified water through
tankers.
Index Code No:BLD-CSTN-8-3
UNIT:10 Sqm
Material
43.20 kg Cement 4.22 1 Kg 182.30
0.1575 cum Sand for mortar 1,726.90 1 cum 271.99
454.29
Add towards C.P & O.H 4% 18.17
Total Material cost/10Sqm 472.46
Total Material cost/1sqm 47.25 47.00
Labour
10.00 sqm Labour charges 2,504.75 10 sqm 2,504.75
0.15 cum Mortor mixing charges ( manual) 112.00 1 cum 16.80
2,521.55
Add towards C.P & O.H 4% 100.86
Total labour charges/10Sqm 2,622.41
Total Labour charges/1sqm 262.24 262.00
Rate/1Sqm 309.00
Plastering 20 mm thick in for superstructure for un-even faces of walls with CM (1:4) with
sponge finish at all heights including cost and conveyance charges of cement and all other
materials to site, scaffolding charges, seigniorage charges, incidental and operational
11 charges, all labour charges for mixing mortar, finishing, all leads and lifts, curing, cutting
grooves etc., complete for finished item of work and as directed by the Engineer in charge.
The contractor shall make his own arrangements for procuring the specified water through
tankers.
Index Code No:BLD-CSTN-6-7
Unit-1Sqm(out put taken for 10Sqm)
Material
75.60 kg Cement 4.22 1 Kg 319.03
0.22 cum Sand for mortar 1,726.90 1 cum 379.92
698.95
Add towards C.P & O.H 4% 27.96
Total Material cost/10Sqm 726.91
Total Material cost/1sqm 72.69 73.00
Labour
10.00 sqm Labour charges 2,504.75 10 sqm 2,504.75
0.21 cum Mortor mixing charges ( manual) 112.00 1 cum 23.52
2,528.27
Add towards C.P & O.H 4% 101.13
Total labour charges/10Sqm 2,629.40
Total Labour charges/1sqm 262.94 263.00
Rate/ 1Sqm 336.00

Page 44 of 73
Plastering to ceiling 12 mm thick in one coat in CM(1:3) with sponge finish at all heights
including cost and conveyance charges of cement and all other materials to site,
scaffolding charges, seigniorage charges, incidental and operational charges, all labour
12
charges for mixing mortar, finishing, all leads and lifts, curing, cutting grooves etc.,
complete for finished item of work and as directed by the Engineer in charge. The contractor
shall make his own arrangements for procuring the specified water through tankers.

Index Code No:BLD-CSTN-8-1


Unit-1Sqm(out put taken for 10Sqm)
Material
72.00 kg Cement 4.22 1 Kg 303.84
0.1575 cum Sand for mortar 1,726.90 1 cum 271.99
575.83
Add towards C.P & O.H 4% 23.03
Total Material cost/10Sqm 598.86
Total Material cost/1sqm 59.89 60.00
Labour
10.00 sqm Labour charges 2,504.75 10 sqm 2,504.75
0.15 cum Mortor mixing charges ( manual) 112.00 1 cum 16.80
2,521.55
Add towards C.P & O.H 4% 100.86
Total labour charges/10Sqm 2,622.41
Total Labour charges/1Sqm 262.24 262.00
Rate/1Sqm 322.00
Providing impervious coat with CM(1:3) 20 mm thick using approved waterproofing
compound over terrace including cost and conveyance charges of cement and all other
materials to site, scaffolding charges, seigniorage charges, incidental and operational
13 charges, all labour charges for mixing mortar, finishing, all leads and lifts, curing, cutting
grooves etc., complete for finished item of work and as directed by the Engineer in charge.
The contractor shall make his own arrangements for procuring the specified water through
tankers.
Unit-1Sqm(out put taken for 10Sqm)
Material
100.80 kg Cement 4.22 1 Kg 425.38
0.2205 cum Sand for mortar 1,726.90 1 cum 380.78
Integral Cement Waterproofing Liquid
0.40 Ltr Confirming to IS:2645-2003 213.00 1 Ltr 85.20
(BMT-H.85)
891.36
Add towards C.P & O.H 4% 35.65
Total Material cost/10Sqm 927.01
Total Material cost/1sqm 92.70 93.00
Labour
10.00 sqm Labour charges 3,445.90 10 sqm 3,445.90
0.21 cum Mortor mixing charges ( manual) 112.00 1 cum 23.52
3,469.42
Add towards C.P & O.H 4% 138.78
Total labour charges/10Sqm 3,608.20
Total Labour charges/1sqm 360.82 361.00
Rate/1Sqm 454.00

Page 45 of 73
Flooring with a bed of 100mm thick in CC (1:4:8) with 40mm & 20mm size HBG Metal
from approved quarry including cost and conveyance charges of cement and all other
materials to site, seigniorage charges, labour charges for machine mixing, laying concrete,
14
finishing top surface to the required level, curing etc., complete for finished item of work as
directed by the Engineer in charge. The contractor shall make his own arrangements for
procuring the specified water through tankers.

Unit-1Cum
Material
0.45 cum 40mm HBG metal 1,473.70 1 cum 663.17
0.45 cum 20mm HBG metal 2,095.70 1 cum 943.06
0.45 cum Sand for concrete 1,610.90 1 cum 724.91
162.00 kg Cement 4.22 1 kg 683.64
3,014.78
Add towards C.P & O.H 4% 120.59
Total Material cost/1Cum 3,135.37 3,135.00
Labour
1.00 cum labour charges as per statement 1,388.60 1 cum 1,388.60
Machinary
1.00 hr Concrete mixer 300 / 200 ( diesel) 518.20 1 hr 518.20
1,906.80
Add towards C.P & O.H 4% 76.27
Total Labour charges/1Cum 1,983.07 1,983.00
Rate/1Cum (40&20mmPCC 1:4:8) 5,118.00

Flooring with High Polished Granite 16 to 18mm thick up to 2.43M black of black colour
and design set over a base coat of CM(1:8) , 12 mm thick over CC bed already laid with neat
cement slurry of honey like consistency spread at the rate of 3.3 Kgs per Sqm and filling the
joints with white cement paste mixed with pigment of matching shade is to be done
15 including cost and conveyance charges of cement and all other materials to site, seigniorage
charges, incidental and operational charges, all labour charges for mixing mortar, finishing,
all leads and lifts, etc., complete for finished item of work and as directed by the Engineer
in charge.The contractor shall make his own arrangements for procuring the specified water
through tankers.

Unit: 10 sqm
Material
High Polished Granite 16 to 18mm thick
10.5 Sqm 2100.00 1 Sqm 22050.00
up to 2.43M black (BMT-B.11)
Cement for base coat of CM(1:8) , 12
21.6 Kg 4.22 1 Kg 91.15
mm thick
33 Kg Cement for slurry 4.22 1 Kg 139.26
6 Kg Cement for pointing 4.22 1 Kg 25.32
0.12 cum sand 1726.90 1 cum 207.23
0.02 cum sand for pointing 1726.90 1 cum 34.54
22,547.50
Add towards C.P & O.H 4% 901.90
Total Material cost/10 Sqm 23,449.40
Material cost/1 Sqm 2,344.94 2,345.00
Labour
10.00 sqm Labour charges 7095.00 10 sqm 7,095.00
Add towards C.P & O.H 4% 283.80
Total Labour charges/10 Sqm 7,378.80
Labour charges/1 Sqm 737.88 738.00

Page 46 of 73
Rate/ 1 sqm 3,083.00

Flooring with Non - skid red or white full body Ceramic floor tiles of size 300 x 300 mm and
thickness between 7-8mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 -
15) of any colour and finish in all shades and designs set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry
16
of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement
paste to full depth mixed with pigment of matching shade, including cost of all materials like
cement, sand water and tiles etc., complete for finished item of work.The contractor shall
make his own arrangements for procuring the specified water through tankers.

Index Code No:BLD-CSTN-9-5


Unit: 10 sqm
Non - skid red or white full body
Ceramic floor tiles of size 300 x 300
mm and thickness between 7-8mm 1st
10.5 Sqm quality conforming to IS:13711, 396.40 1 Sqm 4,162.20
IS:13712, IS:13630 (Parts 1 - 15) of any
colour and finish in all shades and
designs (BMT-C.01)
Cement for base coat of CM(1:8) , 12
21.6 Kg 4.22 1 Kg 91.15
mm thick
33 Kg Cement for slurry 4.22 1 Kg 139.26
White Cement vide item code BMS-
2 kg 31.00 1 Kg 62.00
W.68
0.12 cum Sand 1726.90 1 cum 207.23
4,661.84
Add towards C.P & O.H 4% 186.47
Total Material cost/10Sqm 4,848.31
Total Material cost/1Sqm 484.83 485.00
Labour
10.00 sqm Labour charges 3846.40 10 sqm 3,846.40
0.12 cum Mortor mixing charges ( manual) 112.00 1 cum 13.44
Add towards C.P & O.H 4% 154.39
Total Labour cost/10Sqm 4,014.23
Total Labour cost/1Sqm 401.42 401.00
Rate/1Sqm 886.00

Dadooing in toilets and bath rooms with glazed red or white fully body ceramic tiles of size
200 x 300 mm / 245 x 325 mm and thickness 6mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs set over
a base coat of CM(1:3) 12 mm thick with neat cement slurry of honey like consistency
spread at the rate of 3.3 Kgs per Sqm and filling the joints with white cement paste mixed
17
with pigment of matching shade is to be done including cost and conveyance charges of
cement and all other materials to site, seigniorage charges, incidental and operational
charges, all labour charges for mixing mortar, finishing, all leads and lifts, etc., complete
for finished item of work and as directed by the Engineer in charge.The contractor shall
make his own arrangements for procuring the specified water through tankers.

Unit: 10 sqm
Material

Page 47 of 73
glazed red or white fully body ceramic
tiles of size 200 x 300 mm / 245 x 325
mm and thickness 6mm 1st quality
10.5 Sqm conforming to IS:13711, IS:13712, 396.40 1 Sqm 4,162.20
IS:13630 (Parts 1 to 15) of any colour
and finish in all shades and designs
(BMT-C.01)
57.6 Kg Cement 4.22 1 Kg 243.07
0.12 cum Sand 1726.90 1 cum 207.23
33 Kg Cement for slurry 4.22 1 Kg 139.26
White Cement vide item code BMS-
2 Kg 31.00 1 Kg 62.00
W.68
4,813.76
Add towards C.P & O.H 4% 192.55
Total Material cost/10Sqm 5,006.31
Total Material cost/1Sqm 500.63 501.00
Labour
10 sqm Labour charges 3846.40 10 sqm 3,846.40
0.12 cum Mortor mixing charges ( manual) 112.00 1 cum 13.44
3,859.84
Add towards C.P & O.H 4% 154.39
Total Labour Charges/10Sqm 4,014.23
Total Labour Charges/1Sqm 401.42 401.00
Rate/1Sqm 902.00

Supplying & fixing Flush door shutters, solid bond wood block board type with teak ply on
18 both faces.: 30 mmthick conforming to IS:2202 including providing special PVC braket on
hinge side, etc complete as per direction of Engineer–in–charge, manufacturers specification.

Unit : Calculation for 0.9M x 1.9M


a)Material
Flush door shutters, solid bond wood
block board type with teak ply on both
1.71 Each 2165.00 1.00 Each 3702.15
faces.: 30 mm thick conforming to
IS:2202 (BMT-N.13)
AluminiumButthinges(IS:205)-
3 No 109.00 1.00 No 327.00
100mmLong (BMT-G.24)

Aluminium Tower Bolt-10 mm


2 No 87.00 1.00 No 174.00
Bolt(IS:204)150mmLong (BMT-G.08)

Aluminium Door
1 No Handles(IS:208)150mm Long (BMT- 122.00 1.00 No 122.00
G.34)
Aluminium Aldrop (IS:2681)
1 No 331.00 1.00 No 331.00
250mmlong (BMT-G.41)
Heavy duty Aluminium Door stopper
1 No 64.00 1.00 No 64.00
(BMT-G.57)
Contractors Profit and Over Head
4% 188.81
charges@
Total Materials for 1.71Sqm 4,908.96
Total Materials for 1.0 Sqm 2,870.73 2871.00
b)Labour Charges:

Page 48 of 73
Labour charges for fixing Flush door
shutters of any thickness to the existing
1.71 Sqm door frame including fixing the fixtures 463.00 1.00 Sqm 791.73
to the door shutter excluding cost of
shutter as per (BMM-V.23)

1 LS Transport charges 250.00 1.00 LS 250.00


Contractors Profit and Over Head
4% 41.67
charges@
Total Materials for 1.71Sqm 1,083.40
Total Labour for 1.00 Sqm 633.57 634.00
Total (Materials+Labour) 3505.00

Providing and fixing factory made solid Wood Polymer Composite (WPC)
single extruded Door Frame section of size with encapsulation of 8MM rigid
layer on all the six surfaces. The door frame will have a rebat of 32MM. Door
Frame section of 63.5x100 MM.The two Vertical members are to be joined
together with the horizontal member using 8x75 MM long MS Star full thread
19
screws to be used with reverse forward speed control hand drilling machine. The
ready/assembled door frame is fixed to the wall using hold fast or bolt fasteners.
A minimum of 4 No of screws to be provided for each vertical member &
minimum 2no for horizontal member. The price inclusive of all material at site
complete for finished item of work as directed by the Engineer in charge.

Door Frame
Unit :1 RM
a)Material
Material Door frame Size 100 x63.5mm
Data taken for
(1.05+1.05+2.10+2.10 =6.3RM)

factory made solid Wood Polymer


Composite (WPC) single extruded Door
Frame section of size with
encapsulation of 8MM rigid layer on all
6.30 Rmt 786.25 1.00 Rmt 4953.38
the six surfaces. The door frame will
have a rebat of 32MM. Door Frame
section of 63.5x100 MM (BMT-N.83.C)
(85% of 925 =786.25)

10.00 Set Anchor bolts & PVC Plug 6" length 30.00 1.00 Set 300.00
1.00 Bot Silicon gel 150.00 1.00 Bot 150.00
0.20 Kg Araldite 980.00 1.00 Kg 196.00
12.00 No Screws 8.00 1.00 No 96.00
5695.38
Add towards C.P & O.H 4% 227.82
Total Materials for 6.3 Mt 5923.20
Total Materials for 1 Mt 940.19 940.00
b)Labour Charges:
6.30 Rmt Fixing charges (15% of 925 =138.75) 138.75 1.00 Rmt 874.13
874.13

Page 49 of 73
Add towards C.P & O.H 4% 34.97
Total Labour 909.10
Total Labour 144.30 144.00
Total (Materils+Labour) 1084.00

Supplying & fixing Flush door shutters, 28 -30 MM thick solid Wood Polymer
Composite(WPC) single extruded door shutter with 3MM top and bottom rigid layer with an
overall density of 750kg/Cum. It will be fixed to the frame using 3 inch /4 inch hinges. A
20
minimum of 4 hinges will be required for fixing the door with the frame including cost and
conveyance of all materials and labour charges , etc complete as per direction of Engineer–
in–charge, manufacturers specification.

Unit : Calculation for 0.9M x 1.9M


a)Material

Providing and fixing 28 -30 MM thick


solid Wood Polymer Composite(WPC)
single extruded door shutter with 3MM
top and bottom rigid layer with an
overall density of 750kg/Cum. It will be
1.71 Each fixed to the frame using 3 inch /4 inch 2947.00 1.00 Each 5039.37
hinges. A minimum of 4 hinges will be
required for fixing the door with the
frame (BMT-N.88)
(3,410.00 - 463.00 (BMM-V.23) =
2947.00)

AluminiumButt hinges(IS:205)-
4 No 109.00 1.00 No 436.00
100mmLong (BMT-G.24)

Aluminium Tower Bolt-10 mm


2 No 87.00 1.00 No 174.00
Bolt(IS:204)150mmLong (BMT-G.08)

Aluminium Door
1 No Handles(IS:208)150mm Long (BMT- 122.00 1.00 No 122.00
G.34)
Aluminium Aldrop (IS:2681)
1 No 331.00 1.00 No 331.00
250mmlong (BMT-G.41)
Contractors Profit and Over Head
4% 244.09
charges@
Total Materials for 1.71Sqm 6,346.46
Total Materials for 1.0 Sqm 3,711.38 3711.00
b)Labour Charges:

Labour charges for fixing Flush door


shutters of any thickness to the existing
1.71 Sqm door frame including fixing the fixtures 463.00 1.00 Sqm 791.73
to the door shutter excluding cost of
shutter as per (BMM-V.23)

1 LS Transport charges 250.00 1.00 LS 250.00


Contractors Profit and Over Head
4% 41.67
charges@
Total Materials for 1.71Sqm 1,083.40

Page 50 of 73
Total Labour for 1.00 Sqm 633.57 634.00
Total (Materials+Labour) 4345.00

Providing and fixing factory made uPVC white colour sliding glazed window upto 1.50 m in
height dimension comprising of uPVC multi-chamberedframe with in-built roller track and
sash extruded profiles duly reinforcedwith 1.60 ± 0.2 mm thick galvanized mild steel section
made from rollforming process of required length (shape & size according to uPVCprofile),
appropriate dimension of uPVC extruded glazing beads andu PVC extruded interlocks,
EPDM gasket, wool pile, zinc alloy (white powder coated) touch locks with hook, zinc alloy
body with single nylonrollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8
mm size for fixing frame to finished wall and necessary stainless steel screwsetc. Profile of
21 frame & sash shall be mitred cut and fusion welded at allcorners, including drilling of holes
for fixing hardware's and drainage ofwater etc. After fixing frame the gap between frame and
adjacent finishedwall shall be filled with weather proof silicon sealent over backer rod of
required size and of approved quality, all complete as per approved drawing& direction of
Engineer-in-Charge inclusive of cost of Single / double glass panes, wire mesh and silicon
sealent .
Note: For uPVC frame and sash extruded profiles minus 5% tolerancein dimension i.e. in
depth & width of profile shall be acceptable.Variation in profile dimension in higher side
shall be accepted. But no extra payment on this account shall be made.

Two track two panels sliding window


made of (small series) frame 52 x 44
mm &sash 32 x 60 mm both having
wall thickness of 1.9 ± 0.2 mm and
single glazing bead of appropriate
dimension. (Area of window upto 1.75
sqm) - BMT-P.80 A
Rate / 1 Sqm (BMT-P.80.A ) 6698.00
Material 70% 4688.60 4,688.60
Add towards C.P & O.H 4% 187.54
Total Material 4,876.14 4,876.00

Labour 2009.4 2,009.40


2,009.40
Add towards C.P & O.H 4% 80.38
LabourTotal 1 Sqm 2,089.78 2,090.00
Total Material and Labour 6966.00
Supply and fixing of MS grill for Stair case hand rail,gates etc. of different sizes including
cost and conveyance of all the materials, fabrication charges,fixing charges, labour charges
22
and painting with two coats of synthetic enamel paint over one coat of primer etc., complete
for finished item of work as directed by the Engineer-in-charge.
Unit: 1 Kg
Material
1 MT MS rods, angles,channels, flats etc. 61,269.80 1 MT 61269.80
Add towards C.P & O.H 4% 2,450.79
Total Material cost 63,720.59
Material Cost/1Kg 63.72 64.00
Labour
Fabrication charges vide item code
1 Kg 33.00 1 Kg 33.00
BMM-V.14
Fixing charges vide item code BMM-
1 Kg 6.00 1 kg 6.00
V.15
39.00
Page 51 of 73
Add towards C.P & O.H 4% 1.56
Labour charges/1Kg 40.56 41.00
Rate/1kg 105.00

Painting the walls (Inside) and ceiling with two coats of Plastic emulsion paint grade-I of
Asian make over one coat of primer of approved colour, make and shade over one coat of
white cement primer including cost and conveyance of all materials to site, water to site, cost
23 of brushes, scaffolding charges, all labour charges, curing, tools and plant, incidental
charges, all leads and lifts etc at all heights of all floors complete for finished item of work
and as directed by the Engineer in charge.The contractor shall make his own arrangements
for procuring the specified water through tankers.

Unit: 10 sqm
Water based Cement primer interior
1.00 Kg 173.00 1 Kg 173.00
Grade - 1 vide item code BMT-J.01

Synthetic polymer luxury plastic


emulsion paint of superior grade having
0.80 L VOC ( Volatile Organic Compound) 490.00 1L 392.00
content less than 50grams / liter - vide
item code BMT-J.22

565.00
Add towards C.P & O.H 4% 22.60
Total Material cost/10Sqm 587.60
Material cost/1Sqm 58.76 59.00
Labour
10.00 sqm labour charges - Primer 1 coat 453.95 10 sqm 453.95
10.00 sqm labour charges - 2 coats 778.20 10 sqm 778.20
1,232.15
Add towards C.P & O.H 4% 49.29
Total labour charges/10Sqm 1,281.44
Labour charges/1Sqm 128.14 128.00
Rate/ 1Sqm 187.00

Painting to walls (out side) with two coats of Weather proof acrylic exterior emulsion or
equivalent quality paint of approved colour, make and shade over one coat of white cement
primer including cost and conveyance of all materials, water to site, cost of brushes,
24 scaffolding charges, all labour charges, curing, tools and plant, incidental charges, all leads
and lifts etc at all heights of all floors complete for finished item of work and as directed
by the Engineer in charge.The contractor shall make his own arrangements for procuring the
specified water through tankers.

Unit: 10 sqm

Water based Cement Primer of Exterior


1.00 kg 201.00 1 kg 201.00
Grade - 2 vide item code BMT-J.02

Acrylic exterior emulsion paint having


VOC ( Volatile Organic Compound)
0.80 lit. 231.00 1 lit 184.80
content less than 50grams / liter vide
item code BMT-J.34

385.80
Add towards C.P & O.H 4% 15.43
Total Material cost/10Sqm 401.23

Page 52 of 73
Material cost/1Sqm 40.12 40.00
Labour
10.00 sqm labour charges for Primer 1 coat 453.95 10 sqm 453.95
labour charges for weather proof /
10.00 sqm 1,293.95 10 sqm 1,293.95
Plastic exterior emulsion - 2 coats
1,747.90
Add towards C.P & O.H 4% 69.92
Labour charges/10Sqm 1,817.82
Labour charges/1Sqm 181.78 182.00
Rate/ 1sqm 222.00
Painting new iron work with Synthetic enamel paints 2 coats over a coat of approved red
oxide primer making 3 coats in all to give an even shade including cost and conveyance of
25
all materials to work site and all operational, incidental, labour charges etc., complete for
finished item of work..
Unit - 10Sqm
Material
Red Oxide primer gr-I vide item code
0.70 lit 160.00 1 lit 112.00
BMT-J.03
Syn enamel paint gr-I vide item code
1.10 lit 281.00 1 lit 309.10
BMT-J.29
421.10
Add towards C.P & O.H 4% 16.84
Total Material cost/10Sqm 437.94
Total Material cost/1Sqm 43.79 44.00
Labour
10 sqm Labour charges for priming coat 453.95 10 sqm 453.95
10 sqm Labour charges for two coats painting 713.35 10 sqm 713.35
1,167.30
Add towards C.P & O.H 4% 46.69
Total labour charges/10Sqm 1,213.99
Total labour charges/1Sqm 121.40 121.00
Rate /1sqm 165.00
Painting new wood work with Synthetic enamel paints 2 coats over a coat of approved wood
primer making 3 coats in all to give an even shade including cost and conveyance of all
26
materials to work site and all operational, incidental, labour charges etc., complete for
finished item of work.
0.70 Ltr Cost of Wood Primer BMT-J.05 176.00 1 Ltr 123.20
Cost of Synthetic Enamel Paint BMT-
1.20 Ltr 191.00 1 Ltr 229.20
J.30
352.40
Add towards C.P & O.H 4% 14.10
Total Material cost/10Sqm 366.50
Total Material cost/1Sqm 36.65 37.00
Labour
10 sqm Labour charges for priming coat 453.95 10 sqm 453.95
10 sqm Labour charges for enamel 2 coats 778.20 10 sqm 778.20
1,232.15
Add towards C.P & O.H 4% 49.29
Total Labour Charges/10Sqm 1,281.44
Total Labour Charges/1Sqm 128.14 128.00
Rate /1Sqm 165.00
Page 53 of 73
Supplying & fixing of 110mm dia. Rain water down take pipe with PVC Pipes of Prince or
27 sudhakar or equivalent make including cost and conveyance of PVC Pipes, specials, labour
charges etc complete.
Unit-1RM
Material
110mm dia PVC Pipe vide item
1.00 RM 447.00 3 RM 149.00
code:BMW-G.13
Add towards C.P & O.H 4% 5.96
Total Material cost/1RM 154.96 155.00
Labour
Labour charges for laying, fixing, and
commissioning the PVC pipes including
couplers, bends, plugs, junctions, tees
1.00 RM 79.00 1 RM 79.00
etc. with solvent jointing as per
Standard practice vide item code:BMW-
G.152)
79.00
Add towards C.P & O.H 4% 3.16
Total labour charges/1RM 82.16 82.00
Rate/1RM 237.00
Supply and fixing of 25mm outer dia heavy (2.20mm thickness) regid PVC pipe ( ISI mark)
28 concealed in wall with all required accessories including masonry work and labour charges
complete
Index code:BLD-ELEC-1- 4,
Specification No.1.4.2(a)
Material
25mm outer dia heavy (2.20mm
100 RM thickness) regid PVC pipe vide item 46.00 1 RM 4600.00
code ELEC-1.2.1(b)
200 Nos U-Nails vide item code ELEC-8.1.4 36.00 100 Nos 72.00
25mm dia 1,2,3&4 way deep junction
12 Nos 36.00 1 Nos 432.00
box ELEC-1.2.7(b)
12 Nos 25mm PVC bends ELEC-1.2.8(b) 12.00 1 Nos 144.00
50 Kg cement 4.22 1 Kg 211.00
5,459.00
Add towards C.P & O.H 4% 218.36
Total Material cost/100RM 5,677.36
Total Material cost/1RM 56.77 57.00
Labour charges
2 Nos Skilled electrician 745.00 1 No 1,490.00
2 Nos Semi Skilled electrician 605.00 1 No 1,210.00
2 Nos Helpers 605.00 1 No 1,210.00
2 Nos Mason 1st class 670.00 1 No 1,340.00
5,250.00
Add towards C.P & O.H 4% 210.00
Total Labour charges/100RM 5,460.00
Total Labour charges/1RM 54.60 55.00
Rate/1RM 112.00

Page 54 of 73
Wiring with 2 runs of 14/0.3mm (1.0 sqmm) FRLS/HFFR PVC insulated 1100V grade as per
IS: 694/1990 specification for Copper cable of makes Finolex / RR Kabel / KEI 6A /10A
Modular switch of Legrand Arteor / MK Blenge / Schneider Zen Celo , ceiling rose, suitable
29
hot dip Galvanized metal box with cover frame to switch control box including all labour
chages etc. complete for light, bell, fan and exhaust fan points for finished item of work as
directed by the Engineer-in-charge.

Index code:BLD-ELEC-2-1,
Specification No.2.1.1
Taking Out put for 6 points
Material

14/0.3mm (1.0 sqmm) FRLS/HFFR


PVC insulated 1100V grade as per IS:
200 RM 694/1990 specification for Copper cable 1,238.00 100 RM 2,476.00
of makes Finolex / RR Kabel / KEIvide
item code ELEC-1.5.1.a

6A /10A 1 way Modular switch of


6 Nos Legrand/Arteor/MK Blenge/Schneider 80.00 1 No. 480.00
Zen celo vide item code ELEC-1.8.1(a)

Metal Box- 6 module vide item code


1 Nos 155.00 1 No. 155.00
ELEC-1.3.1(d)
6 Modular Cover frame of Legrand
1 Nos Arteor/MK Blenge/Schneider Zen Celo 110.00 1 No. 110.00
vide item code ELEC-1.8.4(d)
6A , 2-way Ceiling Rose vide item
6 Nos 22.00 1 No. 132.00
code ELEC-1.7.1.m
3,353.00
Add towards C.P & O.H 4% 134.12
Total Material cost/6Nos 3,487.12
Total Material cost/1No 581.19 581.00
Labour charges
0.6 Nos Skilled electrician 745.00 1 No 447.00
1.2 Nos Semi Skilled electrician 605.00 1 No 726.00
0.6 Nos Helpers 605.00 1 No 363.00
1,536.00
Add towards C.P & O.H 4% 61.44
Total Labour charges/6Nos 1,597.44
Total Labour charges/1No 266.24 266.00
Rate/1No 847.00

Supply and fixing of 6A /10A 3/2 Pin Modular Socket with shutter of Legrand Arteor / MK
Blenge / Schneider Zen Celo with switch control of 6A /10A Modular switch of Legrand
30
Arteor / MK Blenge / Schneider Zen Celo with earth continuity including wire leads, earth
connections along with all labour charges etc., complete.

Index code:BLD-ELEC-2-1,
Specification No.2.1.4
30.1 Independent Mounting
Material

Page 55 of 73
6A /10A Modular Socket of Legrand
1 Nos Arteor / MK Blenge / Schneider Zen 122.00 1 No. 122.00
Celo vide item code ELEC-1.8.1(d)

6A /10A 1 way Modular switch of


1 Nos Legrand/Arteor/MK Blenge/Schneider 80.00 1 No. 80.00
Zen celo vide item code ELEC-1.8.1(a)

3 Modular Cover frame of Legrand


1 Nos Arteor/MK Blenge/Schneider Zen Celo 77.00 1 No. 77.00
vide item code ELEC-1.8.3(b)

6A /10A 1 way Modular switch of


1 Nos Legrand/Arteor/MK Blenge/Schneider 80.00 1 No. 80.00
Zen celo vide item code ELEC-1.8.1(a)

359.00
Add towards C.P & O.H 4% 14.36
Total Material cost/1No 373.36 373.00
Labour charges
0.067 Nos Skilled electrician 745.00 1 No 49.92
0.067 Nos Helpers 605.00 1 No 40.54
90.45
Add towards C.P & O.H 4% 3.62
Total Labour charges/1No 94.07 94.00
Rate /1No 467.00
30.2 Dependent Mounting
Material
6A /10A Modular Socket of Legrand
1 Nos Arteor / MK Blenge / Schneider Zen 122.00 1 No. 122.00
Celo vide item code ELEC-1.8.1(d)

6A /10A 1 way Modular switch of


1 Nos Legrand/Arteor/MK Blenge/Schneider 80.00 1 No. 80.00
Zen celo vide item code ELEC-1.8.1(a)

202.00
Add towards C.P & O.H 4% 8.08
Total Material cost/1No 210.08 210.00
Labour charges
0.067 Nos Skilled electrician 745.00 1 No 49.92
0.067 Nos Helpers 605.00 1 No 40.54
90.45
Add towards C.P & O.H 4% 3.62
Total Labour charges/1No 94.07 94.00
Rate /1No. 304.00
Supply and run of 2 of 36/0.3 mm (2.5 sqmm) FRLS / HFFR PVC insulated 1100V grade as
31 per IS:694/1990 specification for Copper cable of makes Finolex / RR Kabel / KEI in
existing pipe for mains including all labour charges complete.
Index code:BLD-ELEC-3-1,
Specification No.3.1.4
Taking Out put for 100 RM
Material

Page 56 of 73
36/0.3 mm (2.5 sqmm) FRLS / HFFR
PVC insulated 1100V grade as per
200 RM IS:694/1990 specification for Copper 2874.00 100 RM 5748.00
cable of makes Finolex / RR Kabel /
KEI vide item code ELEC-1.5.1(c)
Add towards C.P & O.H 4% 229.92
Total Material cost/100RM 5,977.92
Total Material cost/1RM 59.78 60.00
Labour charges
0.67 Nos Skilled Electrician 745.00 1 No 499.15
2 Nos Semi Skilled electrician 605.00 1 No 1,210.00
0.67 Nos Helpers 605.00 1 No 405.35
2,114.50
Add towards C.P & O.H 4% 84.58
Total Labour charges/100RM 2,199.08
Total Labour charges/1RM 21.99 22.00
Rate/1RM 82.00

Supply and run of 1 of 14/0.3mm (1.0 sqmm) FRLS/HFFR PVC insulated 1100V grade as
32 per IS: 694/1990 specification for Copper cable of makes Finolex / RR Kabel / KEI in
existing pipe for earth continuity including all labour charges complete.

Index code:BLD-ELEC-3-1,
Specification No.3.1.2
Taking Out put for 100 RM
Material
14/0.3mm (1.0 sqmm) FRLS/HFFR
PVC insulated 1100V grade as per IS:
100 RM 694/1990 specification for Copper cable 1238.00 100 RM 1238.00
of makes Finolex / RR Kabel vide item
code ELEC-1.5.1(a)
Add towards C.P & O.H 4% 49.52
Total Material cost/100RM 1,287.52
Total Material cost/1RM 12.88 13.00
Labour charges
0.34 Nos Skilled Electrician 745.00 1 No 253.30
1.00 Nos Semi Skilled electrician 605.00 1 No 605.00
0.34 Nos Helpers 605.00 1 No 205.70
1,064.00
Add towards C.P & O.H 4% 42.56
Total Labour charges/100RM 1,106.56
Total Labour charges/1RM 11.07 11.00
Rate/1RM 24.00

Supply and run of 2 of 56/0.3mm (4.0 Sqmm) FRLS / HFFR PVC insulated 1100V grade
33 as per IS:694/1990 specification for Copper cable of makes Finolex / RR Kabel / KEI in
existing pipe for mains including all labour charges complete.

Index code:BLD-ELEC-3-1,
Specification No.3.1.5
Taking Out put for 100 RM
Material

Page 57 of 73
56/0.3mm (4.0 Sqmm) FRLS / HFFR
PVC insulated 1100V grade as per
200 RM IS:694/1990 specification for Copper 4388.00 100 RM 8776.00
cable of makes Finolex / RR Kabel /
KEI vide item code ELEC-1.5.1(d)
Add towards C.P & O.H 4% 351.04
Total Material cost/100RM 9,127.04
Total Material cost/1RM 91.27 91.00
Labour charges
1 Nos Skilled electrician 745.00 1 No 745.00
3 Nos Semi Skilled electrician 605.00 1 No 1,815.00
1 Nos Helpers 605.00 1 No 605.00
3,165.00
Add towards C.P & O.H 4% 126.60
Total Labour charges/100RM 3,291.60
Total Labour charges/1RM 33.00 33.00
Rate/1RM 124.00
Supply and run of 1 of 36/0.3 mm (2.5 sqmm) FRLS / HFFR PVC insulated 1100V grade as
34 per IS:694/1990 specification for Copper cable of makes Finolex / RR Kabel / KEI in
existing pipe for earth continuity including all labour charges complete.

Index code:BLD-ELEC-3-1,
Specification No.3.1.4 (a)
Taking Out put for 100 RM
Material
36/0.3 mm (2.5 sqmm) FRLS / HFFR
PVC insulated 1100V grade as per
100 RM IS:694/1990 specification for Copper 2874.00 100 RM 2874.00
cable of makes Finolex / RR Kabel /
KEI vide item code ELEC-1.5.1.(c)
Add towards C.P & O.H 4% 114.96
Total Material cost/100RM 2,988.96
Total Material cost/1RM 29.89 30.00
Labour charges
0.34 Nos Skilled electrician 745.00 1 No 253.30
1 Nos Semi Skilled electrician 605.00 1 No 605.00
0.34 Nos Helpers 605.00 1 No 205.70
1,064.00
Add towards C.P & O.H 4% 42.56
Total Labour charges/100RM 1,106.56
Total Labour charges/1RM 11.07 11.00
Rate/1RM 41.00
Supply and fixing of 4-way VTPN Distribution board suitable for accommodating 4 pole
Isolator as incomer with IP 43 Protection as per IS:13032 and suitable for 4Nos
T.P.outgoings etc., complete of makes Legrand / Schneider including cost of D.B., 1No.63A
35
FP isolator, 12 Nos. 6-32A 10KA SP MCBs of make Legrand / Schneider., giving all
internal connections and labour charges for surface/flush mounting etc. complete for finished
item of work as directed by the Engineer-in-charge.
Material

Page 58 of 73
Supply of 4-way VTPN Distribution
board suitable for accommodating 4
pole Isolator as incomer with IP 43
1 Nos Protection as per IS:13032 and suitable 8328.00 1 No 8328.00
for 4Nos T.P.outgoings etc., complete
of makes Legrand / Schneider vide item
code ELEC-2.13.7(a)

Supply of 63A FP Isolator of make


1 Nos Legrand / Schneider vide item code 1082.00 1 No 1082.00
ELEC-2.11.1(g)
Supply of 6-32A 10KA SP MCB, C/D
Curve ISI Mark of make Legrand /
12 Nos 228.00 1 No 2736.00
Schneider vide item code ELEC-
2.10.1(a)
12,146.00
Add towards C.P & O.H 4% 485.84
Total Material cost/1No 12,631.84 12,632.00
Labour charges
0.5 Nos Skilled electrician 745.00 1 No 372.50
1 Nos Semi Skilled electrician 605.00 1 No 605.00
1 Nos Helpers 605.00 1 No 605.00
1,582.50
Add towards C.P & O.H 4% 63.30
Total Labour charges/1No 1,645.80 1,646.00
Rate /1No 14,278.00

Supply of 10 Sqmm WPTC (Weather Proof Twin Core) ISI Alluminium Wire. Makes: Gold
Medal / Million / GM / Vimal / Finecab / Nakoda / Nanadicab / Payal / Fybros by Kundan
36
cab.in existing pipe for mains including all labour charges complete for finished item of
work and as directed by the Engineer in charge.

Material

Supply of 10 Sqmm WPTC (Weather


Proof Twin Core) ISI Alluminium Wire.
Makes: Gold Medal / Million / GM /
100 m 4469.00 100 Rmt 4469.00
Vimal / Finecab / Nakoda / Nanadicab /
Payal / Fybros by Kundan cab. vide
item code ELEC-1.6.2(b)

4,469.00
Add towards C.P & O.H 4% 178.76
Total Material cost/100RM 4,647.76
Total Material cost/1RM 46.48 46.00
labour charges
2.5 no Man Mazdoor 560.00 1 No. 1,400.00
1 no. skilled electrician 745.00 1 No. 745.00
2 no., Helper 605.00 1 No. 1,210.00
3,355.00
Add towards C.P & O.H 4% 134.20
Total Labour charges/100RM 3,489.20
Total Labour charges/1RM 34.89 35.00

Page 59 of 73
Rate /1RM 81.00

Providing fuse carrier board comprises of 3Nos porcelain fuse carriers 63Amp/415V with
HRC fuses assembled over 10"x7" teak wood peeta board fixed to wall surface with
37 incoming from electric pole and out going to distribution board as per relevant standard
specifications including cost and conveyance of all materials, screws, nails and labour
charges etc., complete for finished item of work.

Unit:1No
Material
Cost of fuse carries 63Amp/415V with
3.00 Nos Porcelain Rewirable Fuse Units vide 318.00 1 No 954.00
item code ELEC-2.7.1.C

1.00 No Cost of neutral link (local market rate) 175.00 1 No 175.00


Cost of 8" x 10" teak wood peeta board
1.00 No 65.00 1 No 65.00
(ELEC-1.4.1.e)
LS Cost of screws and nails LS 20.00
1,214.00
Add towards C.P & O.H 4% 48.56
Total Material cost/1No 1,262.56 1,263.00
Labour
Cost of labour for fixing of fuse carriers
and neutral link to peeta board and then
1.00 No fixing the assembled unit to wall 450.00 1 No 650.00
securedly with required screws and nails
(Local Market Rate)
Add towards C.P & O.H 4% 26.00
676.00
Total Labour Cost/1No 676.00 676.00
Total cost/1No 1,939.00

Supply and Transportation of 20W, T8,1200mm length LED retrofit tube light, input voltage
AC 220 - 260 Volts with PF>0.9, Surge protection: 2KV,THD<10%, with inbuilt driver and
frosted cover CCT: 3000K - 5700K, minimum CRI>70, .etc., complete as per IS 10322 (Part
38 5/ Sec 1)..2012 Makes: Wipro / Phillips / GE / Crompton / Bajaj / VIN b) LED MAKE :
PHILIPS LUMILEDS / CREE / NICHIA / OSRAM / SAMSUNG including cost and
conveyance of all materials and labour complete for finished item of work as directed by
Engineer - In - Charge

a)Material

20W, T8,1200mm length LED retrofit


tube light, input voltage AC 220 - 260
Volts with PF>0.9, Surge protection:
2KV,THD<10%, with inbuilt driver and
frosted cover CCT: 3000K - 5700K,
minimum CRI>70, .etc., complete as
1.00 No. 588.00 1.00 No. 588.00
per IS 10322 (Part 5/ Sec 1)..2012
Makes: Wipro / Phillips / GE /
Crompton / Bajaj / VIN b) LED
MAKE : PHILIPS LUMILEDS /
CREE / NICHIA / OSRAM /
SAMSUNG. ( ELEC-3.8.16 )

Page 60 of 73
Supply of 14/0.3mm (1.0 Sqmm)
FRLS / ZHFR PVC insulated 1100V
grade as per IS : 694 / 1990
2.00 M specification for Copper cable. Makes: 1238.00 100.00 M 24.76
Nandicab / Star / Airson/ Benlo /
Gemscab /
Rajnigandha/Avocab/CRI/Salzer /ollvin

2.00 No. PVC Rawl Plugs ( ELEC-8.1.2 ) 36.00 100.00 No 0.72


2.00 No. TW Separators / Gutties ( ELEC-8.1.1 ) 218.00 100.00 No 4.36
Sub-Total 617.84
Add towards C.P & O.H 4% 24.71
Total Materials 642.55 643.00
b)Labour Charges:
0.10 No. Skilled Electrician 745.00 1.00 No. 74.50
0.10 No. Semi skilled Electrician 525.00 1.00 No. 52.50
Area Allowence 0% 0.00
Sub-Total 127.00
Add towards C.P & O.H 4% 5.08
Total Labour 132.08 132.00
Total (Materials+Labour) 775.00

Supply and fixing of batten holder/ slanting holder in lieu of ceiling rose of light point
39 complete with all connections and labour charges, cost of 40 W bulb etc., complete for
finished item of work.

Index code:BLD-ELEC-2-1,
Specification No.2.1.4
Material
Supply of PVC Batten holder (MAT-
1 Nos 18.00 1 No 18.00
02820)
Supply of 5.0W LED Bulb vide item
1 Nos 110.00 1 No 110.00
code MAT-03286
128.00
Add towards C.P & O.H 4% 5.12
Total Material cost/1No 133.12 133.00
Labour charges
0.05 Nos Skilled electrician 745.00 1 No 37.25
0.05 Nos Helpers 605.00 1 No 30.25
67.50
Add towards C.P & O.H 4% 2.70
Total labour charges/1No 70.20 70.00
Rate/1No 203.00

Supply and fixing of CEILING fan of 48" Sweep, 5 Star rated Ceiling Fan, with double ball
bearings, power input not more than 53W, air delivery more than 218 cubic meter/min and
40 service value 4.11 with stepped type electronic regulator including cost and conveyance of
all materials and labour charges complete for finished item of work as directed by the
Engineer-in-Charge.

Material

Page 61 of 73
CEILING fan 1200mm sweep 5 star
rated, without regulator of make
1.00 No. 2405.00 1 No 2405.00
Crompton greeves/ Bajaj/ Havels /
Orient ELEC-5.1.3
Supply of 1 Module Modular type
1.00 No. Electronic step type Fan Regulator 421.00 1 No 421.00
ELEC-1.8.1 (N)
2,826.00
Add towards C.P & O.H 4% 113.04
Total Material cost/1No 2,939.04 2,940.00
Labour charges
0.125 Nos Skilled electrician 745.00 1 No 93.13
0.125 Nos Helpers 605.00 1 No 75.63
168.75
Add towards C.P & O.H 4% 6.75
Total labour charges 175.50 176.00
Rate/1No 3,116.00

Providing Independent earthing by excavating a trench to a depth of 2.70M in all soils as per
size specified in the data using 75mm dia CI(spun) pipe of 3.00Mtr length with necessary
41 accessories with humepipe ring duly providing stagered holes including filling with equal
proportion of salt and charchol in layers and all labour charges etc. complete for small
finished item of work.

Earthwork excavation in all soils for


2.19 cum 371.00 1 cum 812.49
trench 0.90x0.90x2.70
20% extra for narrow trench ,pit an back
filling with sand, coke,salt etc. and 162.50
levelling
75mm dia C.I (spun) pipe vide item
3.00 Rmt 1387.00 3 RM 1387.00
code BMW-H.01
GI strip 25 x 6 mm with 4nos., holes of
0.48 Kg 85.00 1 kg 40.80
12mm dia( ELEC-8.3.6)
GI Nuts ,bolts and washers (ELEC-
4 sets 14.00 1 set 56.00
8.4.21)
18" dia 2" thick hume pipe ring (ELEC-
1 No. 303.00 1 No 303.00
8.4.22)
40 Kg hard coke (ELEC-8.1.10) 24.00 1 kg 960.00
20 Kg salt (ELEC-8.1.11) 19.00 1 kg 380.00
4,101.79
Add towards C.P & O.H 4% 164.07
Total Material cost 4,265.86 4,266.00
labour charges
0.5 No. Semi skilled Electrician 605.00 1 No 302.50
0.5 No. Helper 605.00 1 No 302.50
605.00
Add towards C.P & O.H 4% 24.20
Total labour charges 629.20 629.00
Rate/1No 4,895.00
Supply of Polyethylene water storage tank Triple layer of 500 Ltr capacity with lid including
42
cost and conveyance of all materials, labour charges etc., complete for finished item of work
Unit - 1No

Page 62 of 73
Polyethylene water storage tank Triple
500 Ltr layer of 1000 Ltr capacity with lid 7.50 1.00 Ltr 3,750.00
(BMW-G.01) (8.5-1=7.5)

Cost of SS Nipples (Local Market Rate)


3 Nos 300.00 1.00 No 900.00
for inlet, outlet and delivery pipes

Material cost 4,650.00


Add towards C.P & O.H 4% 186.00
Total Material Cost 4,836.00 4,836.00
Labour Charges
Transpotation charges LS 500.00
Labour charges for erection 500 Ltrs
500 Ltr capacity including fixing of ss nipples, 1.00 1 Ltr 500.00
washers etc., complete
Add towards C.P & O.H 4% 40.00
Total labour charges 1,040.00 1,040.00
Rate/1No 5,876.00

Supply and fixing of different dia.Unplasticised PVC Pipes,10 kg/cm2 for potable water
supplies conforming to IS : 4985/2000 (third revision) with bell ends (Socket) as per
specification in light Grey/Natural Ivory Grey/ Any other Color including Labour charges for
43
laying, fixing, and commissioning the pipes including couplers, bends, plugs, junctions, tees
etc. with solvent jointing as per Standard practice for finished item work as directed by the
Engineer-in-charge.

45.1 25mm dia UPVC pipe


Material
Cost of 25 mm dia UPVC pipe vide
1 RM 29.00 1 RM 29.00
page 83 PH SSR Table 20
Add towards C.P & O.H 4% 1.16
Total Material cost 30.16 30.00
Labour

Labour charges for laying, fixing, and


commissioning the pipes including
couplers/bends/tees etc any diameter
1 RM including fixing necessary fittings like 79.00 1 RM 79.00
bends, plugs, couplers, junctions, tees
etc with solvent jointing as per Standard
practice vide item code BMW-G.152

Sub-Total 79.00
Add towards C.P & O.H 4% 3.16
Total Labour Charges 82.16 82.00
Rate/ 1 RM 112.00
45.2 20mm dia UPVC pipe
Material
Cost of 20 mm dia UPVC pipe vide
1 RM 19.00 1 RM 19.00
page 83 PH SSR Table 20
Add towards C.P & O.H 4% 0.76
Total Material cost 19.76 20.00
Labour

Page 63 of 73
Labour charges for laying, fixing, and
commissioning the pipes including
couplers/bends/tees etc any diameter
1 RM including fixing necessary fittings like 79.00 1 RM 79.00
bends, plugs, couplers, junctions, tees
etc with solvent jointing as per Standard
practice vide item code BMW-G.152

Sub-Total 79.00
Add towards C.P & O.H 4% 3.16
Total Labour Charges 82.16 82.00
Rate/ 1 RM 102.00
Supply and fixing of 25mm GM Gate (GM peet) valves as per IS 778 Class I -Indian make
44 heavy type of different sizes including cost and conveyance of all materials and labour
Charges complete for finished item work as directed by the Engineer-in-charge.
25mm GM Gate Valves
Material
Rate as per item code BMW-F.17
1 No excluding labour charges 1165-50=1115 1115.00 1 No. 1115.00
)
Add towards C.P & O.H 4% 44.60
Total Material cost 1159.60 1160.00
Labour
Labour charges vide item code BMW-
1 No 50.00 1 No 50.00
F.18
Add towards C.P & O.H 4% 2.00
Total Labour Charges 52.00 52.00
Rate/1No 1212.00
Supply and fixing of CP Long body bib cock fancy type delux heavy duty 12.7mm dia
Indian make Seiko / Senior / Nice or equivalent including cost and conveyance of all
45
materials, labour charges etc., complete for finished item of work as directed by the Engineer
- In - Charge
Material
Rate as per item code BMW-
1 No E.21excluding labour charges (607-33= 574.00 1 No 574.00
574)
Add towards C.P & O.H 4% 22.96
Total Material cost 596.96 597.00
Labour
1 No Rate as per item code BMW-E.20 33.00 1 No 33.00
Add towards C.P & O.H 4% 1.32
Total Labour Charges 34.32 34.00
Rate/1No 631.00
Supply and fixing of CP Short body bib cock fancy type delux heavy duty 12.7mm dia
Indian make Seiko / Senior / Nice or equivalent including cost and conveyance of all
46
materials, labour charges etc., complete for finished item of work as directed by the Engineer
- In - Charge
Material

Rate as per item code BMW-E.22


1 No 549.00 1 No 549.00
excluding labour charges (582-33= 549)

Page 64 of 73
Add towards C.P & O.H 4% 21.96
Total Material cost 570.96 571.00
Labour
1 No Rate as per item code BMW-E.20 33.00 1 No 33.00
Add towards C.P & O.H 4% 1.32
Total Labour Charges 34.32 34.00
Rate/1No 605.00

Supply and fixing of Angle stop cock 12.7 mm dia first quality Indian make heavy duty
47 Seiko / Senior / Nice or equivalent including cost and conveyance of all materials, labour
charges etc., complete for finished item of work as directed by the Engineer - In - Charge

Material
Rate as per item code BMW-E.05
1 No excluding labour charges (453-49 = 404.00 1 No 404.00
404)
Add towards C.P & O.H 4% 16.16
Total Material cost 420.16 420.00
Labour
1 No Rate as per item code BMW-E.06 49.00 1 No 49.00
Add towards C.P & O.H 4% 1.96
Total Labour Charges 50.96 51.00
Rate/1No 471.00

Supplying and fixing colour glazed porcelain European type Parry ware make or equivalent
quality water closets with ISI make, P or S trap including cost and conveyance of water
48
closet, P or S trap, plastic seat and lid and all other materials, labour charges for fixing etc.,
complete for finished item of work as directed by the Engineer in charge of work

Material
Rate of European Water Closet 1st
quality as per item code BMW-D.13
1.00 No. 1679.00 1 No. 1679.00
excluding labour charges (1979-
300=1679)

Rate of best indian make plastic seat


and lid for European water closet with
1.00 No. rubber or plastic Buffers as per IS 2548- 850.00 1 No. 850.00
1996 vide BMW-D.16 excluding labour
charges (850-87=763)

2529.00
Add towards C.P & O.H 4% 101.16
Total Material cost 2,630.16 2630.00
Labour
Labour for fixing of European WC as
1.00 no 300.00 1 no 300.00
per item code BMW-D.15)
Labour for fixing of plastic seat and lid
1.00 no for European water closer as per item 87.00 1 no 87.00
code BMW-D.17
387.00
Add towards C.P & O.H 4% 15.48
Total Labour Charges 402.48 402.00
Rate/1No 3,032.00

Page 65 of 73
Supplying and fixing of PVC flushing tank of parry ware make or equivalent ISI make with
49 all fixtures including cost and conveyance of tank and all other materials, labour charges for
fixing etc., complete for finished item of work as directed by the Engineer in charge of work

As per Sl No143, item code: BMW-


1.00 No 1,773.00 1 No 1,773.00
D.11(2468-599=1869)
Material Cost 1773.00
Add towards C.P & O.H 4% 70.92
Rate/ 1 No 1,843.92 1844.00
1.00 No Labour Charges (BMW-D.12) 599 1 No 599.00
Add towards C.P & O.H 4% 23.96
Total Labour Charges 622.96 623.00
Rate/1No 2467.00
Supplying and fixing (550mm x 400 mm) Indian make Flat back wash hand basin(HSW/
Parryware/Neycer) 1st quality conforming to IS:2556-Part-4:1972 with waste fittings like
rubber plug, chain,32 mm nominal size C.P.Fitting with parallel pipe thread confirming to
50 IS:2963-1979 and fitting with 15 mm nominal bore Chromium plated pillar tap of 1st quality
Indian make 400gms Seiko / Senior / Nice / Esso or equivalent complete with standard CI
brackets including wooden block etc. complete for finished item of work as directed by the
Engineer in charge of work
Material
Rate of flat back hand wash basin as per
1.00 No item code BMW-D.24 excluding labour 1,303.00 1 No 1,303.00
charges (1736-362=1374)
Add towards C.P & O.H 4% 52.12
Material Cost 1,355.12
Total Material cost 1355.12 1355.00
Labour Charges
Labour charges vide item code BMW-
1.00 No 362.00 1 No 362.00
D.28
Add towards C.P & O.H 4% 14.48
Total Labour Charges 376.48 376.00
Rate/1No 1731.00
Supply and fixing of 12.7mm dia UPVC Health faucet of ISI make WATER-TECH or
51
equivalent
(Local Market rates) Rate/1No. 950.00
Add towards C.P & O.H 4% 38.00
Material Cost 988.00
(Local Market rates)Rate/ 1 No 988.00 988.00
Labour Charges 90.00
Add towards C.P & O.H 4% 3.60
Total Labour Charges 93.60 94.00
Rate/1No 1082.00
Supply & Fixing 12.7mm PVC connection with brass union nut C.P.Coated including cost
52 and conveyance of all materials and labour charges complete for finished item of work as
directed by the Engineer - in - charge
Material
Rate as per BMW - I.48 excluding
1.00 No 76.00 1 No 76.00
labour charges (95-19=76)
Add towards C.P & O.H 4% 3.04

Page 66 of 73
Material Cost 79.04
Total Material Cost 79.04 79.00
Labour Charges
Labour charges vide item code BMW-
1.00 No 19.00 1 No 19.00
I.49
Add towards C.P & O.H 4% 0.76
Total Labour Charges 19.76 20.00
Rate/1No 99.00

Supply & Fixing 31.75mm dia PVC flexibile waste pipe of 914.40mm length of 1st quality
53 including cost and conveyance of all materials and labour charges complete for finished item
of work as directed by the Engineer - in - charge

Material
Rate as per item code BMW-G.05
1.00 No 24.00 1 No 24.00
excluding labour charges
Add towards C.P & O.H 4% 0.96
Material Cost 24.96
Total Material Cost 24.96 25.00
Labour
1.00 No Labour charges 6.00 1 No 6.00
Add towards C.P & O.H 4% 0.24
Total Labour Charges 6.24 6.00
Rate/1No 31.00
Supplying & fixing in walls, ground different dia PVC Pipes of Prince or sudhakar or
54 equivalent make for sewer lines including cost and conveyance of PVC Pipes, specials,
PVC cowls labour charges etc complete.
55.1 110mm dia.(6 kg/cm2)
110mm dia PVC Pipe vide item
1.00 RM 765.00 3 RM 255.00
code:BMW-G.35
Add towards C.P & O.H 4% 10.20
Total Material cost 265.20 265.00
Labour charges for laying, fixing, and
commissioning the PVC pipes including
couplers, bends, plugs, junctions, tees
1.00 RM 79.00 1 RM 79.00
etc. with solvent jointing as per
Standard practice. (S.No.486,index
code:BMW-G.152)
Add towards C.P & O.H 4% 3.16
Total Labour Charges 82.16 82.00
Rate/1RM 347.00
55.2 75 mm dia.( 6kg/cm2)
75mm dia PVC Pipe item code: BMW-
1.00 RM 437.00 3 RM 145.67
G.36
Add towards C.P & O.H 4% 5.83
Total Material cost 151.50 151.00

Page 67 of 73
Labour charges for laying, fixing, and
commissioning the PVC pipes including
couplers, bends, plugs, junctions, tees
1.00 RM 79.00 1 RM 79.00
etc. with solvent jointing as per
Standard practice. (S.No.486,index
code:BMW-G.152)
Add towards C.P & O.H 4% 3.16
Total Labour Charges 82.16 82.00
Rate/1RM 233.00

Supply and Fixing of 100mm Nahani traps of Prince/sudhakar or any ISI brand including
55 cost and conveyance of all materials, labour charges etc., complete for finished item of work
as directed by the Engineer - In - Charge

1 No Rate/1No.,(Rate as per BMW-G.116) 90.00 1 No 90.00


Material cost 81.00
Add towards C.P & O.H 4% 3.24
Total Material Cost 84.24 84.00
Labour Charges 9.00
Add towards C.P & O.H 4% 0.36
Total labour charges 9.36 9.00
Rate/1No 93.00

Construction of Manholes of size 457.2x457.2mm brick in CM(1:6) proportion masonary


Inspection chamber upto 914.4mm depth and fitted with suitable CI frame and cover of 20
56 kg including cost and conveyance of all materials, labour charges etc., complete for finished
item of work as directed by the Engineer - In - Charge. The contractor shall make his own
arrangements for procuring the specified water through tankers.

1 No Rate/1No.,(Rate as per BMW-B.06) 3590.00 1 No 3,590.00


Material Cost 2872.00
Add towards C.P & O.H 4% 114.88
Rate/ 1 No 2,986.88 2987.00
Labour Charges 718.00
Add towards C.P & O.H 4% 28.72
Total Labour Charges 746.72 747.00
Rate/1No 3734.00
Providing 15mm thick moulded cement mortar bands in cement mortar 1:4 (1Cement:4Sand)
upto 300mm in width including cost and conveyance charges of cement and all materials to
57
site, seigniorage charges etc., complete for finished item of work as directed by the Engineer
- in - Charge.
Raised band
Basic Cost for 10Mtr long and 10Cm
wide band
Material
8.28 Kg O.P.Cement 53 grade 4.22 1 Kg 34.94
0.024 Cum Sand for mortar 1,726.90 1 Cum 41.45
76.39
Add towards C.P & O.H 4% 3.06
Total Material cost/10RM 79.45
Total Material cost/1RM 7.95 8.00
Labour

Page 68 of 73
0.87 Nos Mason 2nd Class 605.00 1 No 526.35
0.92 Nos Mazdoor 560.00 1 No 515.20
1,041.55
Add towards C.P & O.H 4% 41.66
Total Labour charges/10RM 1,083.21
Total Labour charges/1RM 108.32 108.00
A 10.00CM wide band
Material/1RM 8.00
Labour/1RM 108.00
Total Rate/1RM 116.00 116.00
C 4.00CM wide band
Material
Rate of 10cm wide band/1RM 8.00
Rate of 4.00CM wide band/1RM
3.20 3.00
(8.00/10*4.00)
Labour
Rate of 10cm wide band/1RM -
Rate of 4.00CM wide band/1RM
26.40 26.00
(66.00/10*4.00)
Total Rate/1RM 29.00

Providing name boards to office buildings on wall surface of the buildings with two coats of
Synthetic Enamel Paint of approved quality, colour and shade painted over a coat of primer
58
of approved quality including cost and conveyance of all materials, labour charges, leads and
lifts, scaffolding charges etc., complete for finished item of work.

Unit:1Sqm
Material

Water based Cement Primer of Exterior


1.00 kg 201.00 1 kg 201.00
Grade - 2 vide item code BMT-J.02

Acrylic exterior emulsion paint having


VOC ( Volatile Organic Compound)
0.80 lit. 231.00 1 lit 184.80
content less than 50grams / liter vide
item code BMT-J.34

385.80
Add towards C.P & O.H 4% 15.43
Total Material cost/10Sqm 401.23
Total Material cost/1Sqm 40.12 40.00
Labour
10.00 sqm labour charges 453.95 10 sqm 453.95
10.00 sqm labour charges 1,293.95 10 sqm 1,293.95
for writing letters including cost of
paint
Cost of labour for writing letters over
1.00 Sqm base paint including cost of paint (local 864.11 1 Sqm 864.11
market rate @ Rs. 80/Sft)
2,612.01
Add towards C.P & O.H 4% 104.48
Total Labour cost/10Sqm 2,716.49
Total Labour cost/1Sqm 271.65 272.00

Page 69 of 73
Rate/ 1sqm 312.00
Construction of soak pit with 4' dia RCM rings upto a depth of 5' including cost and
59
conveyance of cover and all other required materials
a)Material
5.00 No. RCM rings ( local market rate ) 750.00 1.00 No. 3750.00
Add towards C.P & O.H 4% 150.00
Total Materials 3900.00 3900.00
b)Labour Charges:
5.00 No. Fixing Charges ( local market rate ) 50.00 1.00 No. 250.00
Add towards C.P & O.H 4% 10.00
Total Labour 260.00 260.00
Total (Materials+Labour) 4160.00
Supply and laying Polished black Kadapa slabs of all sizes between 25 -30mm thickness as
shelf slabs including cost of all materials like cement, sand, and water and flooring stones
60
etc., complete, including seigniorage charges, labour charges for dressing of flooring stones
etc., complete for finished item of work.
Unit- 10 sqmt
A) Materials
Polished black Kadapa slabs of all sizes
11.00 Sqmt between 25 -30mm thickness (BMT- 1850.00 10 Sqmt 2035.00
B.17)
Add towards C.P & O.H 4% 81.40
Total Materials for 10 Sqm 2116.40
Total Materials for 1sqm 211.70 212.00
B.LABOUR
0.25 Nos Mason 2nd class 605.00 1 Nos 151.25
0.25 Nos Mazdoor (unskilled) 560.00 1 Nos 140.00
1.00 No Transportation charges 150.00 1 No 150.00
Add towards C.P & O.H 4% 17.65
Total Labour for 10 Sqm 459.00
Total Labour for 1 Sqm 45.90 46.00
Total (Materils+Labour) 257.60 258.00

Page 70 of 73
DATA 2023-24

Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in Nandyal Division of Operation Circle, Kurnool
Mazdoor
Mason:
Mason:1s Add Area
670.00 2nd 605.00 560.00 Gross for Allowance @ Gross for
Sl No Description of item Unit t class (Unskilled)
class Rural areas Rural areas
Qty Amount Qty Amount Qty Amount 0%
1 Plain Cement concrete (PCC),machine mixing 1 cum 0.10 67.00 0.00 0.00 2.36 1321.60 1388.60 0.00 1388.60
2(a) RCC (Footings&Plinth Beams) 1 cum 0.133 89.11 0.267 161.54 3.600 2016.00 2266.65 0.00 2266.65
RCC (Columns, Lintels, Water tanks, RCC walls & Sun
2(b) 1 cum 0.167 111.89 0.167 101.04 4.700 2632.00 2844.93 0.00 2844.93
shades)
2(c) RCC (Slabs & Beams) 1 cum 0.067 44.89 0.133 80.47 2.500 1400.00 1525.36 0.00 1525.36
3 Brick Masonry 230mm wide 1 cum 0.24 160.80 0.56 338.80 1.89 1058.40 1558.00 0.00 1558.00
3 Brick Masonry 115mm wide 1 cum 0.60 402.00 0.60 363.00 2.75 1540.00 2305.00 0.00 2305.00
4 RR Masonry 1 cum 1.20 804.00 0.00 0.00 2.00 1120.00 1924.00 0.00 1924.00
5 CR Masonry 1 cum 0.75 502.50 1.75 1058.75 1.40 784.00 2345.25 0.00 2345.25
6 Plastering 12mm 10 sqm 0.45 301.50 1.05 635.25 2.80 1568.00 2504.75 0.00 2504.75
7 Plastering 20 mm thick 10 sqm 0.45 301.50 1.05 635.25 2.80 1568.00 2504.75 0.00 2504.75
8 Flooring with vitrified/ Ceramic tiles 10 sqm 0.96 643.20 2.24 1355.20 3.30 1848.00 3846.40 0.00 3846.40
8 Flooring with Granite Slabs 10 sqm 3.00 2010.00 1.00 605.00 8.00 4480.00 7095.00 0.00 7095.00
9 Impervious coat 20mm thick 10 sqm 0.66 442.20 1.54 931.70 3.70 2072.00 3445.90 0.00 3445.90
10 Mixing of mortor ( Manual) 1 cum 0.00 0.00 0.00 0.00 0.20 112.00 112.00 0.00 112.00
Mazdoor
Painter Painter
750.00 605.00 (Unskilled) 560.00 Gross for
Sl No Description of item Unit 1st class 2nd class
Rural areas
Qty Amount Qty Amount Qty Amount
11 Wall primer-1 coat/Wood primer 10 sqm 0.21 157.50 0.49 296.45 0.00 0.00 453.95 0.00 453.95
12 Painting with 2 coats of plastic emulsion 10 sqm 0.36 270.00 0.84 508.20 0.00 0.00 778.20 0.00 778.20
Painting with weather proof / Plastic exterior emulsion - 2
13 10 sqm 0.21 157.50 0.49 296.45 1.50 840.00 1293.95 0.00 1293.95
coats
14 Red Oxide primer-1 coat 10 sqm 0.21 157.50 0.49 296.45 0.00 0.00 453.95 0.00 453.95
15 Painting with syn enamel to new Iron work- 2 coats 10 sqm 0.33 247.50 0.77 465.85 0.00 0.00 713.35 0.00 713.35
16 Painting with syn enamel to new Wood work- 2 coats 10 sqm 0.36 270.00 0.84 508.20 0.00 0.00 778.20 0.00 778.20
Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in Nandyal Division of Operation Circle,
Kurnool
DATA 2023-24

Rate/per CM(1:2) CM(1:3) CM(1:4) CM(1:5) CM(1:6)


Sl
Material
No
Rate Unit Qty Amount Qty Amount Qty Amount Qty Amount Qty Amount

1 OP cement 4.22 1Kg 720.00 3038.40 480.00 2025.60 360.00 1519.20 288.00 1215.36 240.00 1012.80

2 Sand for mortar 1726.90 1Cum 1.05 1813.25 1.05 1813.25 1.05 1813.25 1.05 1813.25 1.05 1813.25

3 Mixing charges 112.00 1Cum 1Cum 112.00 1Cum 112.00 1Cum 112.00 1Cum 112.00 1Cum 112.00

Cement Mortar Rate/ 1 Cum = 4963.65 3950.85 3444.45 3140.61 2938.05


Name of work:- Construction of Rudravaram Section Office building at 33/11 KVSS, Rudravaram in Nandyal Division of Operation Circle, Kurnool

LEAD STATEMENT 2023-24


Average
Sl Conveyance Loading Unloading Seigniorage
Material Source lead in Intial cost Total
No charges charges Charges charges
Km
O.P.Cement 53 Grade (G.O.Ms.No. 25 Dated: 17-05-
1 2022) Local 5.00 4.22 1 Kg - - - - 4.22

Reiforcement steel Fe-500D(MAT-00063)


(As per Minutes of the Sub-Committee meeting held in
the chambers of the Engineer-in-Chief
2 (A.W./I.W.),Water Resources Department on Local 5.00 64,500.00 1MT 59.80 105.00 105.00 - 64,769.80
13.04.2023 to review and recommend Steel Rates for the
Month of March-2023)

Structural steel (MAT-00070)


(As per Minutes of the Sub-Committee meeting held in
the chambers of the Engineer-in-Chief
3 (A.W./I.W.),Water Resources Department on Local 5.00 61,000.00 1MT 59.80 105.00 105.00 - 61,269.80
13.04.2023 to review and recommend Steel Rates for the
Month of March-2023)
Jammalmadugu
4 Sand for filling (MAT-00028) 65.00 460.00 1Cum 905.90 100.00 1,465.90
(Kadapa)
Jammalmadugu
5 Sand for Concrete(MAT-00027) 65.00 605.00 1Cum 905.90 100.00 1,610.90
(Kadapa)
Jammalmadugu
6 Sand for mortar (MAT-00029) 65.00 721.00 1Cum 905.90 100.00 1,726.90
(Kadapa)
7 40mm HBG metal (MAT-00220) Allagadda 25.00 1,000.00 1Cum 383.70 90.00 1,473.70
8 Crushed 20mm HBT metal (MAT-00218) Allagadda 25.00 1,622.00 1Cum 383.70 90.00 2,095.70
9 crushed 13.5/12.5mm HBT metal (MAT-00217) Allagadda 25.00 1,306.00 1Cum 383.70 90.00 1,779.70
R.R Masonry Work (other than Granite, Dolomite and
10 Trap) (MAT-00414) Palukuru 60.00 138.90 1Cum 787.90 90.00 1,016.80
1000
11 Burnt Clay Bricks (BMT-A.01) Ayyalur (Nandyal) 35.00 8,164.00 856.50 73.00 73.00 - 9,166.50
Nos
14 Gravel (MAT-00177) Local 10.00 155.00 1Cum 173.90 45.00 373.90

You might also like