Professional Documents
Culture Documents
PepsiCo EHS Standard 16 - Asbestos MGMT FNL VSN 2
PepsiCo EHS Standard 16 - Asbestos MGMT FNL VSN 2
EHS STANDARD 16
ASBESTOS MANAGEMENT
(Published/Effective: January 2015 [Version 2])
Spray coatings on steel work, or concrete walls and ceilings for fire protection and
insulation
Insulation board for wall partitioning, fire doors and ceiling tiles
Asbestos cement products (transite) such as sheeting on walls and roofs, gutters,
and pipes
Floor tile/adhesives
Roofing materials
Gaskets
Packing
Special filters
The purpose of this Asbestos Management standard is to define the minimum requirements
for a program to:
2) Ensure proper handling and disposal of any ACM that must be removed from the
PepsiCo facility or equipment
Asbestos Management
PepsiCo EHS Standard - 16
This program includes inspection of buildings and the review of building equipment for the
presence of ACM or presumed ACM (PACM), and development of procedures to manage ACM
or PACM in place until verified and/or removed.
2.0 APPLICABILITY
This standard applies to all company-owned businesses, company-managed leased facilities
and majority-owned joint venture operations with structures or equipment that may contain
asbestos materials (Facility/Selling Operation or Facilities/Selling Operations).
3.0 RESPONSIBILITIES
3.1. FACILITY/SELLING OPERATION
In the case of some very small operations where staffing levels or expertise is not enough
to develop and maintain an effective AMP, the operation must obtain support from BU or
Sector level staff, as necessary, to ensure compliance with this standard.
Support the Facilities/Selling Operations in conducting the preliminary evaluation and in the
development of their AMPs. As appropriate, provide example AMP documents or prepared
Sector/BU AMP procedures to smaller facilities, to ensure their compliance with this
standard.
4.0 REQUIREMENTS
Each Facility/Selling Operation constructed prior to the PepsiCo Asbestos Management Date
(AMD) for their region or country, must perform a preliminary evaluation (such as, visual
inspection) of the facility and/or equipment to determine whether ACM or PACM are known
or suspected to be present. Facilities constructed after the AMD (date of the beginning of
construction) may use construction date as evidence to assume that the building structure
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 1 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
does not contain ACM or PACM. Equipment and fixtures (such as, floor coverings) within the
building must be evaluated, regardless of age of building.
The AMD is the date selected by PepsiCo representing the time after which it is deemed
extremely unlikely that ACM was used in the construction of the facility. The AMD varies,
based on the country or region where the facility is located, as follows (all dates are January
1):
AMEA - 2005
Facilities/Selling Operations constructed prior to the AMD must document in a written report
the results of the preliminary evaluation. The report must include the basis for the
determination and the location(s), amount (area of surface insulation, length and diameter
of pipe insulation, approximate volume of bulk materials, etc.) and condition (for example,
well-maintained or potentially friable or dispersible) of all known or suspected ACM or PACM.
Any locations of known or suspected ACM must be labeled to inform employees of its
presence and to indicate that the material shall not be disturbed until pre-work confirmation
sampling is conducted. In rooms or areas with a high incidence of suspected ACM or PACM
it may be acceptable to post general signage warning of suspected ACM or PACM in the area
or room, rather than on each individual object, subject to local regulatory requirements.
Each Facility/Selling Operation that confirms the presence of ACM must then develop and
put into action a written AMP that defines policies and procedures to prevent exposure to
airborne asbestos fibers and complies with applicable regulay standards. The AMP must
address:
Qualified Consultant
Hazard Assessment
Control Measures
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 2 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
Continual Improvement
Small Facilities/Selling Operations, that do not have the staffing levels or expertise to
develop, put into action and maintain an AMP must arrange for staffing support from BU or
Sector representatives to ensure risks associated with ACM are effectively managed in
accordance with this standard and applicable regulatory standards, whichever is more
stringent.
Define and document the roles, responsibilities and accountabilities for all personnel who
play a role in implementing the AMP, including:
Site Management
EHS Managers
Facility Planning
Equipment Procurement
Competent/Responsible Person
Employees
Consultants
Contractors
Human Resources
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 3 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
The AMP must address necessary communications to visitors, per local regulatory
requirements, as well as areas of the facility from which visitors should be excluded.
Any Facility/Selling Operation constructed prior to the AMD must conduct a preliminary
evaluation (such as, visual inspection) to identify suspected asbestos-containing building
materials and equipment components. This preliminary evaluation must be conducted by a
properly trained and qualified individual (competent person). The evaluation must identify
building materials, insulation and equipment components which, based on previous
common-place usage and materials components, may contain ACM. Until verified otherwise
through actual sampling and analysis, these materials must be considered to be presumed
ACM (PACM).
Prior to any work being conducted on identified PACM at the Facility/Selling Operation, pre-
work bulk sampling of the affected PACM must be conducted, as appropriate, to determine if
asbestos is actually present.
If ACM are confirmed present, a hazard assessment must then be conducted and a written
Asbestos Management Program must be developed.
Suspect or confirmed ACM building materials and equipment components may remain in
place if they are undamaged, appropriately labeled and unlikely to be disturbed by
maintenance, construction or other activities. However, materials containing asbestos must
be replaced with non-ACM whenever the materials are likely to be disturbed by such
activities. Additionally, all ACM (and PACM) must be visually inspected annually to verify the
condition of the materials.
The AMP must indicate the control measure(s) required for all ACM and/or PACM identified
at the Facility/Selling Operation. Control measures may include the following:
Containing
Removal
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 4 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
Encapsulation
Enclosure
The criteria for selecting the control measure must be documented and recorded.
During any removal / remediation activities, the facility must ensure building occupants at a
minimum are not exposed to levels of airborne asbestos fibers exceeding 0.1 fibers per
cubic centimeter (100 fibers per cubic meter) on an eight-hour, time-weighted average
(TWA) or 1.0 fibers per cubic centimeter on a 30-minute TWA. Where more stringent local
regulatory limits exist, those limits must be followed.
Operations and maintenance procedures in the AMP must include procedures for employees,
contractors and other potentially exposed individuals who may work in the vicinity of any
ACM or PACM that remain at/in the Facility/Selling Operation. To facilitate proper
management of ACM or PACM left in place in the building, the following must be included:
Requirements for labeling or for other means to alert people to the presence or
possible
presence of asbestos
Records of disposal
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 5 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
Each Facility/Selling Operation must implement a process that ensures the continual
improvement of the AMP. This shall include:
Annual inspections of known or suspect ACM to ensure that they are in good
condition and do not present an exposure hazard to building occupants
Annual review of the appropriate signage to ensure proper location and visibility
Specifications must prohibit the use of ACM in any new construction, as well as in
any new equipment purchased for the facility
Any process equipment that is asset transferred from another PepsiCo facility must
be evaluated for ACM, prior to installation
5.0 REPORTING
A mechanism shall be implemented for the accurate notification, labeling and reporting of
the location of ACM and PACM as per local regulatory requirements and PepsiCo minimum
requirements, such as:
Activities likely to disturb ACM and result in the release of airborne asbestos fibers
An awareness level overview of the AMP shall be included in the standard training for new
and transferred employees.
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 6 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
Results of air monitoring conducted during and after asbestos abatement activities
Training records
7.0 TRAINING
The minimum awareness level training program shall include but is not limited to:
Activities that may damage ACM and result in the release of airborne asbestos fibers
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 7 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
comprehensive performance of the assigned duties. This includes, but is not limited to, the
following:
All training prepared and conducted with regard to this Standard shall also conform fully
with PepsiCo EHS Standard 08-Competence, Training, and Awareness and EHS Standard
03–Contractor Management.
ISO 14001: 4.3.2 (Legal and Other Requirements); 4.4.6 (Operational Control);
4.5.1 (Monitoring and Measurement)
OHSAS 18001: 4.3.2 (Legal and Other Requirements); 4.4.6 (Operational Control);
4.5.1 (Performance Measurement and Monitoring)
9.0 REFERENCES
PepsiCo Global Environmental, Health and Safety Management System (GEHSMS)
10.0 DEFINITIONS
Refer to the PepsiCo EHS Glossary (Document Control module).
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 8 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.
Asbestos Management
PepsiCo EHS Standard - 16
Authorized By: Megan Tranter/Larry Perry Next Review: Jan 2018 Version: 2 Page 9 of 10
Printed copies of this document are for informational purposes only; current, controlled copy is located on MyEHS.