DAILY ACTIVITY LOG:

LINE A
PROJECT TITLE:
METRO MANILA
SUBWAY PHASE 01

LOCATION: SHAW BLVD.

RELOCATION OF AM: Sunny DATE: 08/07/23


DRAINAGE WEATHER: DAY:
PM: Sunny

SCHEDULE:

MANPOWER: PROJECT MANAGER: LABOR:


CONSTRUCTION MANAGER: SPOTTER: 1
SITEENGINEER:1 GEN. OPERATOR: 1
FOREMAN:
LEADMAN:1 MASON:5 BACKHOE:
WELDER: PAYLOADER:
WAREHOUSE: BOOMTRUCK:
30T CRANE:
25T CRANE:

TOTAL MANPOWER HR: 72 HRS

EQUIPMENT: BACKHOE 1: BOOMTRUCK:

TIME: TIME:

BACKHOE 2: DUMP TRUCK:

TIME: TIME:

PAYLOADER: Operator: Abdula Kastulan 30T CRANE:


Signal man: Jhovil Diaz
TIME: 9:40 am - 10:10 am TIME:

MINI DUMP TRUCK: 25T CRANE:

TIME: TIME:

TOTAL EQUIPMENT HR: 0.5 hr


ACTIVITY: LINE A:

A7 TO A9 - Dewatering
A8 to A9 - relocation of fence support ( every 3m )
- Manual excavation
A9 - Continuation of fabrication of formworks
A10 - Compaction

ATTACHMENT:

A7 to A8 - Dewatering

A9 - Dewatering

A10 - Soil backfilling


A10 - Surrounding of soil

A10 - Soil compaction using plate compactor

A9 - Continuation of fabrication of formworks

AHEAD SCHEDULE:

PROBLEM ENCOUNTER:

SOLUTION: