Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Document Cover Page Document Ref.

1TB02011-011C49-FFC-CHK-PH-0001

Policy Document Management Revision C0

Document No - 1TB02011-011C49-FFC-CHK-PH-0001

Rev - C0

Inspection Checklist for Domestic Water Distribution Piping (Inside Building)

Page 1 of 2
Document Cover Page Document Ref. 1TB02011-011C49-FFC-CHK-PH-0001

Policy Document Management Revision C0

Revision History
Revision Revision - Revision Approved
No. June-Date by by Description of Revision Status
Inspection Checklist for For Review
Rashad Domestic Water
C0 11-09-23 SIHJ Distribution Piping
Arab
(Inside Building)

Distribution
Name Title Department Date Issued

Page 2 of 2
TRIPPLE BAY ROSEWOOD HOTEL PROJECT

MEP WORKS PACKAGE

CONTRACT NUMBER : 1TB02-011C49-5010

Checklist Description: Domestic Water Network Installation & Specialties ITP No: ITP-ME-0001

WIR Description: Inspection Checklist No:CHK-PH-0001

Location of Inspection: Date of Inspection:

Drawing No: Work Inspection Request No:

SL.NO. Description of Inspection YES NO N/A REMARKS

1. GENERAL

1.1 Ensure the Shop Drawing is Approved

Ensure the Material Technical Submittal & Method statement is


1.2
Approved

1.3 Ensure the Material Inspection Request ( MIR ) Approved

All Piping, Accessories, labeling & identification, cladding is


1.4
installed as per approved shop drawing

2. HANGERS & SUPPORTS

Hangers and supports are complete with necessary attachments,


2.1
inserts, bolts, rods, nuts, washers, and other accessories.

Hangers and supports with galvanized metallic coatings for piping


2.2
and equipment are utilized

Non-Metallic Piping is supported using metallic clamps with rubber


2.3
lining or approved isolation between two surfaces

Ensure Pipe hangers follow approved spacing, span length, sizing


2.4
for clamps, Channels, Thread rods, nuts, bolts etc.

3. PPR Pipes & Fittings Installation

Check piping level with 0.25 percent slope downward toward drain
3.1
and plumb.

Ensure Installation of expansion joints to have sufficient flexibility


3.2 to prevent end thrust and movements caused by thermal expansion
and contraction causing damage to piping and joints.

Ensure Piping is concealed from view and protected from physical


3.3 contact by building occupants unless otherwise indicated and
except in equipment arooms and service areas.

Ensure Provision of fire stopping where combustible piping


3.4
penetrates fire walls and barriers.

3.5 Piping is free of sags and bends.

Fittings for changes in direction and branch connections are


3.6
utilized , avoid bending of pipes.

Page 1 of 3
TRIPPLE BAY ROSEWOOD HOTEL PROJECT

MEP WORKS PACKAGE

CONTRACT NUMBER : 1TB02-011C49-5010

Checklist Description: Domestic Water Network Installation & Specialties ITP No: ITP-ME-0001

WIR Description: Inspection Checklist No:CHK-PH-0001

Location of Inspection: Date of Inspection:

Drawing No: Work Inspection Request No:

SL.NO. Description of Inspection YES NO N/A REMARKS

In Concrete Slab, both Hot and Cold water PPR pipes shall be pre-
insulated by the manufacturer, any insulation of the pipes using
3.7
Elastomeric insulation need to be approved by Authority Having
Jurisdiction.

Ensure Pipe & fittings are welded as per approved Method and all
3.8 welded joints are visually free from deformity, burrs, uneven
seams and other similar welding defects.

4. PEX Pipes & Fittings Installation (Q&E)

Wall embedded pipes are in Secondary containment so that the


4.1
16mm Pex water pipe can be replaced, if necessary.

Fittings for PEX Tube: ASTM F 1807, metal-insert type with copper
4.2 crimp rings and matching PEX tube dimension. Or as per approved
MTS (Q&E type)

Installation of piping is concealed from view and protected unless


4.3 otherwise indicated and except in equipment rooms and service
areas.

Installed PEX piping are with a loop at each change of direction of


4.4
more than 90 degrees or with approved fitting.

Unions are installed for final connection to each piece of


4.5
equipment, machine, or plumbing speciality.

Concealed piping having diameter below 25 mm are installed in a


4.6
conduit of approved type

Pipes in the system should be installed in parallel (no crossing


4.7
allowed).

4.8 Conduit Color Coding for Hot & Cold is followed

Hot & Cold Droppers are spaced atleas 150 mm to aviod Heat
4.9
Transfer

The radius of bending for the pipe and its conduit, when rising from
the floor to the wall, should be [at least) 8 times the outer
4.10 diameter of the conduit pipe (R=B D) to allow free motion of the
inner pipe, inside its conduit, including easy threading and
extraction.

Page 2 of 3
TRIPPLE BAY ROSEWOOD HOTEL PROJECT

MEP WORKS PACKAGE

CONTRACT NUMBER : 1TB02-011C49-5010

Checklist Description: Domestic Water Network Installation & Specialties ITP No: ITP-ME-0001

WIR Description: Inspection Checklist No:CHK-PH-0001

Location of Inspection: Date of Inspection:

Drawing No: Work Inspection Request No:

SL.NO. Description of Inspection YES NO N/A REMARKS

Conduit piping and water piping between terminal points and the
4.11 distributor should be laid in one whole unit, with no branching or
couplers

5. LEAKAGE TESTING

Ensure the test has been carried out in the presence of the Client
5.1 representative who shall verify the test results as per attached
Test form. (1.5 times working pressure or as per site requirement)

REMARKS: Status of Inspection:


1. Approved

2. Approved with Comments


3. Revise and resubmit
REQUESTED BY WITNESSED BY APPROVED BY
FIRST FIX QC ENGINEER SUPERVISON CONSULTANT CLIENT - AMAALA

Name: Name: Name:

Signature: Signature: Signature:

Date: Date: Date:

Page 3 of 3
TRIPPLE BAY ROSEWOOD HOTEL PROJECT

MEP WORKS PACKAGE

CONTRACT NUMBER : 1TB02-011C49-5010

Checklist Description: Hydrostatic Testing of Pipes ITP No: ITP-ME-0001

WIR Description: Inspection Checklist No:CHK-PH-0001

Location of Inspection: Date of Inspection:

Drawing No: Work Inspection Request No:

Hydrostatic Pressure Test Record Form


Pressure Test Record Number:- Date: Contract No.

Location: Area:

Test Parameters
Required Test pressure: Test Fluid: Water Other

Test Starting Time:

Test Ending Time: Actual Holding Time:

Test Equipment
Type: Range: Calibration date:(From) Calibration date:(TO)

Pressure Gauge 1

Pressure Gauge 2

Results Test start time:(Pressure) Test End time:(Pressure)

Pressure Gauge 1:

Pressure Gauge 2 :

Inspection Satisfactory UnSatisfactory


Pressure Test: PASS FAIL
Loading Time Pressure Remarks

Releasing Time Pressure Remarks

REMARKS: Status of Inspection:


1. Approved

2. Approved with Comments


3. Revise and resubmit
REQUESTED BY WITNESSED BY APPROVED BY
FIRST FIX QC ENGINEER SUPERVISON CONSULTANT CLIENT - AMAALA

Name: Fasuludeen Abdul Jabbar Name: Name:

Signature: Signature: Signature:

Date: Date: Date:

Page 1 of 1

You might also like