PROJECT SCHEDULE

PROJECT NAME: WORKSHOP & GARRAGE MUSSAFAH STORE


Tasks WORK DETAIL MAN POWER DURATION

PACKAGE UNIT INSTALLATION

INSTALATION OF NEW PACKAGE UNIT (10 NOS) ON THE SITE 6NOS 5 DAYS

WALL MOUNTED UNIT INSTALLATION


INSTALLATION OF WALL MOUNTED UNIT(1 NO)
3 NOS 1 DAY
COPPER PIPE INSTALLATION & DRAINAGE WORK

FABRIACTION
GI DUCT FABRICATION AND INSULATION AS PER THE SITE
6 NOS 10 DAYS
MEASUREMENT .
DUCT INSTALLATION
INSTALLATION OF DUCT
NECESSERY SUPPORTS & ACCESSORIES FOR THE DUCT 10 NOS 20 DAYS

SMOKE FAN

INSTALLATION OF SMOKE FANS 4 NOS 4 DAYS

DOOR AIR CURTAIN


INSTALLATION OF DOOR AIR CURTAIN(8 NOS) 4 NOS 5 DAYS
INSTALLATION OF EXHAUST FAN
SUPPLY AND INSTALLATION OF EXHAUST FAN (16NOS) 4 NOS 2 DAYS
ELECTRICAL,DRIANAGE & CLADDING
WORKS

INSTALLATION OF THE THERMOSTAT AND ISOLATOR FOR THE UNIT 6 NOS 3 DAYS

CLADDING FOR THE PACKAGE UNIT 10 NOS 20 DAYS


TESTING AND COMMSIONINING OF THE UNITS 2 DAYS