Project Mussafah Warehouse
Project Mussafah Warehouse
INSTALATION OF NEW PACKAGE UNIT (10 NOS) ON THE SITE 6NOS 5 DAYS
FABRIACTION
GI DUCT FABRICATION AND INSULATION AS PER THE SITE
6 NOS 10 DAYS
MEASUREMENT .
DUCT INSTALLATION
INSTALLATION OF DUCT
NECESSERY SUPPORTS & ACCESSORIES FOR THE DUCT 10 NOS 20 DAYS
SMOKE FAN
INSTALLATION OF THE THERMOSTAT AND ISOLATOR FOR THE UNIT 6 NOS 3 DAYS