TECHNICAL SUBMITTAL

The Engi neer The Cont r act or

Design and Construction of Aerospace Supply Chain Facility


Phase 05 (DS Approval Required)
Reference No. AD212-RAQ-DWG-DD-CHW-000002

Rev. No 1
Originator of
RAQ CONTRACTING CO LLC
Submittal
Date Submitted 14-03-24
Plot AC6-18C , At The Aviation District Of Dubai South, Dubai
Date Hardcopies
Requested by
to be issued
Subject of
DETAILED DESIGN DRAWING FOR CHW PIPING
Submittal
Programme Project Quality Plan Method Statement Others (specify)

Enclosure HSE Plan Subcontractor Approval Handover Form

Pre-Qualification CV (specify trade) Snag List

Contractor's Authorized
MAHMOUD KAIED
Representative Name
Signature and Stamp

ENGI NEER’ S COMMENTS


Date Received by Engineer and
Incoming Ref. No.
signature

ENGI NEER APPROVAL For Information Only


Code 1 Code 2 Code 3 Code 4
STATUS

Engi neer ' s Aut hor i z ed


Repr esent at i ve Name
Si gnat ur e, Dat e and St amp
Outgoing Ref. No.

DUBAI SOUTH COMMENTS

DS APPROVAL STATUS Code 1 Code 2 Code 3 Code 4 For Information Only

DS Technical Team Name and


Position Signature, Date and Stamp
DS Design Manager Name and
Position Signature, Date and Stamp

DS Project Manager Name


Signature, Date and Stamp
Outgoing Ref. No.

CONTRACTOR RECEIVED SIGNATURE

Name Date, Signature and Stamp

DOCUMENT STATUS
Code 1 – Appr oved.
Code 2 – Appr oved as not ed, wor k may pr oc eed s ubj ec t t o i nc or por at i on of c omment s i ndi c at ed.
Code 3 – Revi se & r es ubmi t .
Code 4 – Rej ect ed
Cor r ect i ons or comment s made r el at i v e t o s ubmi t t al s dur i ng t hi s r ev i ew do not r el i ev e t he c ont r ac t or f r om c ompl i anc e wi t h
t he cont r act r equi r ment s and s pec f i c at i ons . Thi s c hec k i s onl y f or r ev i ew of gener al c onf or manc e wi t h t he des i gn c oncept
Any amendment s t o t hi s f or m s houl d be appr ov ed by t he Engi neer and Dubai Sout h pr i or t o us e by t he c ont r ac t or .
DM Technical Submittal (PM Approval Required) Rev 1 190120
The Engi neer The Cont r act or
TECHNICAL SUBMITTAL
Design and Construction of Aerospace Supply Chain Facility (DS Approval Required)
Phase 05
Ref er enc e No. AD212-RAQ-DWG-DD-CHW-000002

Originator of Rev. No 1
RAQ CONTRACTING CO LLC
Submittal Plot AC6-18C , At The Aviation District Of Dubai South,
Date Submitted 14-03-24
Dubai
Date Hardcopies to
Requested by
be issued

DRAWING LIST

S.NO DRAWING REFERENCE REVISION DRAWING DESCRIPTION REMARKS

1 RAQ-RDJ184-DWG-MEP-CHW-000001 B GROUND FLOOR CHILLED WATER LAYOUT

2 RAQ-RDJ184-DWG-MEP-CHW-000001 A B ETS ROOM DETAILS CHILLED WATER LAYOUT

3 RAQ-RDJ184-DWG-MEP-CHW-000002 B MEZZANINE FLOOR CHILLED WATER LAYOUT

4 RAQ-RDJ184-DWG-MEP-CHW-000002A B DETAIL OF ETS ROOM CONTROL SCHEMATIC (P&ID)

5 RAQ-RDJ184-DWG-MEP-CHW-000003 B SERVICE FLOOR CHILLED WATER LAYOUT

6 RAQ-RDJ184-DWG-MEP-CHW-000004 B SCHEMATIC CHILLED WATER LAYOUT

7 RAQ-RDJ184-DWG-MEP-CHW-000005 B STANDARD DETAIL - BTU METER

8 RAQ-RDJ184-DWG-MEP-CHW-000000 B SETTING OUT PLAN CHILLED WATER LAYOUT

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

DM Technical Submittal (PM Approval Required) Rev 1 190120


Project Name: Aero Space Supply Chain 05

Client: Dubai South

Consultant: Consultant HSS

Main Contractor: RAQ Contracting Co.

Submittal No. AD212-RAQ-DWG-SCH-CHW-000002-B Date: 13.03.2024

RESPONSE SHEET TO CONSULTANT'S COMMENTS

S. No. Consultant's Comments Contractor's Response Remarks

1 Vertical inline pump installation details to be provided The horizontal split top discharge unit is provided.
2 missing IV for discharge line to be provided Noted.
3 typical details for FAHU, AHU installation to be provided . Provided.Refer Drawing No:RAQ-RDJ184-DWG-MEP-MEC-00005

4 By pass for valve Chamber in schematic diagram drawing is missing. Provided.Refer Drawing No:CHW-01A

5 Fcu locations to be co-ordinated with toilet walls ( ex:WH11) Noted.


FCU type for MTR room to be revalidated. Installation of ducted units
6 Refer latest layouts.
outside the building is not acceptable
7 Location of DPT shall be confirmed with BMS supplier Shall be a Part of shop Drawings.
8 BMS drawings shall be part of detail design Shall be a Submiited by a specialist.
9 All sensing elements to be provided as per Specialist requirements Noted.
10 Comply with South energy regulations and requirements Noted.

11 All installation details related to PHEX to be submitted in DD submission Shall be a Part of shop Drawings.

Duct height shall be verified in the mezzanine floor and the diffuser shall
12 Noted.
be selected for suitable throw
Decorative DX units to be proposed for LV room ,BMS room, CCTV room
13 Substation cooliing by DEWA.As per DEWA regulation.
etc.
14 Installation details of pressurization unit and dosing unit to be provided Shall be a Part of shop Drawings.
Project Name: Aero Space Supply Chain 05

Client: Dubai South

Consultant: Consultant HSS

Main Contractor: RAQ Contracting Co.

Submittal No. AD212-RAQ-DWG-DD-CHW-000002-B Date: 13.03.2024

RESPONSE SHEET TO CONSULTANT'S COMMENTS

S. No. Consultant's Comments Contractor's Response Remarks

1 Compliance statement to previous comments to be provided Noted and Schematic Design compliance statement provided seperately.

2 Chilled water schematic shall be complete with pipe sizing Complied. Refer Drawing No: RAQ-RDJ184-DWG-MEP-CHW-000004
Valve chamber location to be confirmed with district cooling supplier and
3 Awaiting from Authority
availability of district cooling network
4 Provide HAP calculation Provided. Refer HAP Calculation sheet

5 Provide equipment schedule for AC and show the flow requirement Provided. Refer Drawing No:RAQ-RDJ184-DWG-MEP-MEC-000004

6 2 Nos of FCU to be provided in the GF area as per contract drawings Provided based on the Heat Load Calculation.

The total Chilled Water Flow Rate is 25.24 L/s. So we can consider 2 duty
Provide type of chilled water pump and pressurization unit/ chemical
7 and 1 standby. Each capacity (13 L/s) Horizontal split top discharge unit. 500
dosing pump schedule L/s is a pressurization unit.
General Installation Details provided. Refer Drawing No: RAQ-RDJ184-DWG-
8 Where are the general installation details ??
MEP-CHW-000005 & RAQ-RDJ184-DWG-MEP-MEC-000005
9 Where is the setting out plan chilled water layout ? Provided. Refer Drawing No: RAQ-RDJ184-DWG-MEP-CHW-000000
10 Where are the pumps in the plan ? ETS room details ? Provided. Refer Drawing No: RAQ-RDJ184-DWG-MEP-CHW-000001A
11 Provided drawings cannot be considered as a detail design. Refer the Revised Layouts.
BTU meters to be provided at 1.2m from FFL as per previous project and
12 as per south energy requirements. Location shall be as per previous Noted and followed.
phases
Chilled Water Piping Re routed. Refer Drawing No: RAQ-RDJ184-DWG-MEP-
13 Its not accepted to run the main chilled water pipes inside warehouses.
CHW-000001
By-pass is only provided for the heat exchanger. Not required for FCUs and
14 Bypass to be provided for FCUs, heat exchangers & air separator.
Air Separator

Provide missing details for BMS control (DPS across pumps, flow meter, Shall be submitted in shop drawing submission stage with confimation by
15
FCU control...etc) to be checked & coordinated with BMS contractor. Specialist

Provide installation details for chemical dosing unit, pressurization unit,


16 Shall be submitted in shop drawing submission stage
air separator, underground pipes with leak detection...etc
KEYPLAN:-

PLOT

NOTES:-

ROAD ROAD ROAD


+48.00= 0.00 lvl

+48.01
+48.25 +48.25
IMI +0.00 L OT
L

L
T

Road.Lvl.

IMI
L OT

P
T LEGEND

CHWS CHILLED WATER SUPPLY PIPE


113 114 115 116 117 118 119 120

covered parking

CHWR CHILLED WATER RETURN PIPE


SLOPE =3%

SLOPE =3%

SLOPE =3%

SLOPE =3%

SLOPE =3%

SLOPE =3%
IV ISOLATING VALVE
NRV NON RETURN VALVE
SLOPE =4%

SLOPE =4%

SLOPE =4%

SLOPE =4%

SLOPE =4%

SLOPE =4%
HEAT EXCHANGER
FAN COIL UNIT
DECORATIVE UNIT
SERVICE BLOCK

MAIN BUILDING

Project
( PLOT : AC6-18C ) Design and construction of Aerospace
Supply Chain Facility Phase 05
Plot AC6-18C, At The Aviation District
of Dubai South, Dubai

Client
Panel tank
63.00 cum
7.0 m x 3.0 m x 3.0 m
DUBAI SOUTH
8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 %
ELV CARS

ELV CARS

ELV CARS

ELV CARS

8.00 %

8.00 %

8.00 %

8.00 %

8.00 %
8.00 %

8.00 %

8.00 %

8.00 %

8.00 %

8.00 %
47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
Design consultant
+48.45 +48.45
+48.30 +48.45 +48.30 +48.45 +48.30

112 111 110 109 108 117 116 115 114 113 112 111 110 109 108 107 106 105 104 103 102 101 100 99 98 97 96 95 94 93 92 91 90 89 88 87 86 85 84 83 82 81 80 79 78 77 76 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48

LANDSCAPE &

(BY OTHERS)
IRRIGATION
LANDSCAPE &
IRRIGATION
(BY OTHERS) covered parking covered parking covered parking covered parking covered parking covered parking covered parking covered parking
T P
IMI

L OT
T
P

L
Main Contractor
L

L OT IMI

SETTINGOUT PLAN
Sub Contactor

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 06.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

SETTING OUT PLAN


CHILLED WATER LAYOUT

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000000 B
KEYPLAN:-

PLOT

NOTES:-

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

189.50
8.750 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.600 8.750
IMI L OT
L

L
T

IMI
L OT

T
P
123 124 125 126 127 128 129 130

LEGEND
covered parking

CHWS CHILLED WATER SUPPLY PIPE


CHWR CHILLED WATER RETURN PIPE
IV ISOLATING VALVE
NRV NON RETURN VALVE
HEAT EXCHANGER
FAN COIL UNIT
CAGE
LADDER
DECORATIVE UNIT
A

6.00
B

5.50
Substation
C

6.00
D
LV room

6.00
43.50
UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5 UNIT 6 UNIT 7 UNIT 8 UNIT 9 UNIT 10 UNIT 11
738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2 738.8 m2
E
MTR

5.50
BMS&CCTV

F
Project

6.00
ETS
Design and construction of Aerospace
Supply Chain Facility Phase 05
UP

UP

UP

UP

UP
UP

UP

UP

UP

UP

UP
G
DOWN DOWN DOWN DOWN DOWN DOWN DOWN DOWN DOWN DOWN
DOWN
Pantry.
Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry.

Plot AC6-18C, At The Aviation District

4.25
F F F F F F F F F F F

of Dubai South, Dubai


Shower

Shower

Shower

Shower

Shower
Shower

Shower

Shower

Shower

Shower
Shower

Toil. Toil.
Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil. Toil.
Male Female Male Female Male Female Male Female Male Female Male
H

4.25
Panel tank Female Male Female Male Female Male Female Male Female Male
63.00 cum Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash
7.0 m x 3.0 m x 3.0 m
portal portal portal portal portal
Client
Store Store Store Store Store Store Store portal Store Store Store Store

8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 % 8.00 %


J
8.00 %

DUBAI SOUTH
Metal railing
ELV CARS

ELV CARS

ELV CARS

ELV CARS

8.00 %

8.00 %

8.00 %

8.00 %

8.00 %
8.00 %

8.00 %

8.00 %

8.00 %

8.00 %

8.00 %
150x150mm size fins 150x150mm size fins 150x150mm size fins 150x150mm size fins 150x150mm size fins

47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1

Design consultant

122 121 120 119 118 117 116 115 114 113 112 111 110 109 108 107 106 105 104 103 102 101 100 99 98 97 96 95 94 93 92 91 90 89 88 87 86 85 84 83 82 81 80 79 78 77 76 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48
covered parking covered parking covered parking covered parking covered parking covered parking covered parking covered parking
T P
IMI

L OT
T
P

L
L

L OT IMI
HEAT EXCHANGER SCHEDULE

Main Contractor

CHILLED WATER PUMP

Sub Contactor

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

GROUND FLOOR
CHILLED WATER LAYOUT

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000001 B
KEYPLAN:-

PLOT

NOTES:-

LEGEND

CHWS CHILLED WATER SUPPLY PIPE


CHWR CHILLED WATER RETURN PIPE
IV ISOLATING VALVE
NRV NON RETURN VALVE
CHWP-02
HEAT EXCHANGER
FAN COIL UNIT
DECORATIVE UNIT

HEAT EXCHANGER CONNECTION DETAILS SECTION-B


SCALE 1:25

Project
Design and construction of Aerospace
Supply Chain Facility Phase 05
Plot AC6-18C, At The Aviation District
of Dubai South, Dubai
D C
Client

DUBAI SOUTH

Design consultant

Main Contractor

PHEX-02

Sub Contactor
2000

1500

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 05.03.24 AK SK MJB ISSUED FOR APPROVAL


Rev. Date Drn. Chk. Apr. Description
Revision History

Drawing Title

ETS ROOM DETAILS


SECTION-A CHILLED WATER LAYOUT
SCALE 1:25

1500 Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000001A B
KEYPLAN:-

PLOT

NOTES:-

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

189.50
8.75 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.75

CAGE
LADDER

6.00
LEGEND

CHWS CHILLED WATER SUPPLY PIPE


B CHWR CHILLED WATER RETURN PIPE
IV ISOLATING VALVE

5.50
e

NRV NON RETURN VALVE


op
Sl

HEAT EXCHANGER
C
FAN COIL UNIT
DECORATIVE UNIT

6.00
e
op
Sl

open below open below open below open below open below open below open below open below open below open below open below D

6.00
43.50
43.00
+5.06
flat roof combo system

E
Sl

5.50
op
e

6.00
G
e
op

Pantry.
Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry. Pantry.

4.25
Sl

F F F F F F F F F F F
Shower

Shower

Shower

Shower

Shower
Shower

Shower

Shower

Shower

Shower
Shower

Toil. Toil.

Male
FUTURE OFFICE UNIT 01 FUTURE OFFICE UNIT 02 Toil. Toil. Toil. Toil. FUTURE OFFICE UNIT 03 FUTURE OFFICE UNIT 04 Toil. Toil. Toil. Toil. FUTURE OFFICE UNIT 05 FUTURE OFFICE UNIT 06 Toil. Toil. Toil. Toil. FUTURE OFFICE UNIT 07 FUTURE OFFICE UNIT 08 Toil. Toil. Toil. Toil. FUTURE OFFICE UNIT 09 FUTURE OFFICE UNIT 10 Toil. Toil. Toil. Toil. FUTURE OFFICE UNIT 11
Female Male Female Male Female Male Female Male Female Male
TOILET BY TENANT TOILET BY TENANT TOILET BY TENANT TOILET BY TENANT TOILET BY TENANT
H
Female8.55 Male

4.25
Female Male Female Male Female Male Female Male
Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash Hand wash

block work wall block work wall block work wall


void void void void void

Project
Design and construction of Aerospace
Supply Chain Facility Phase 05
Plot AC6-18C, At The Aviation District
of Dubai South, Dubai

Client

DUBAI SOUTH

Design consultant

Main Contractor

Sub Contactor

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

MEZZANINE FLOOR
CHILLED WATER LAYOUT

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000002 B
KEYPLAN:-

PLOT

NOTES:-

LEGEND

CHWS CHILLED WATER SUPPLY PIPE


CHWR CHILLED WATER RETURN PIPE
IV ISOLATING VALVE
NRV NON RETURN VALVE
HEAT EXCHANGER
FAN COIL UNIT
DECORATIVE UNIT

Project
Design and construction of Aerospace
Supply Chain Facility Phase 05
Plot AC6-18C, At The Aviation District
of Dubai South, Dubai

Client

DUBAI SOUTH

Design consultant

Main Contractor

Sub Contactor

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A
05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

DETAIL OF ETS ROOM


CONTROL SCHEMATIC (P&ID)

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000002A B
KEYPLAN:-

PLOT

NOTES:-

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

189.50
LEGEND
8.75 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.60 8.75 CHWS CHILLED WATER SUPPLY PIPE
CHWR CHILLED WATER RETURN PIPE
IV ISOLATING VALVE
NRV NON RETURN VALVE
HEAT EXCHANGER
CAT CAT
LADDER LADDER FAN COIL UNIT
DECORATIVE UNIT
A

6.00
B

5.50
e
op
Sl

6.00
e
op
Sl

D
open below open below open below open below open below open below open below open below open below open below open below

6.00
43.50
E
Sl

5.50
op
e

F
Project

6.00
Design and construction of Aerospace
G Supply Chain Facility Phase 05
e
op

Plot AC6-18C, At The Aviation District

4.25
RAILING RAILING
RAILING
RAILING RAILING RAILING
Sl

RAILING RAILING RAILING RAILING


+9.64 FCL +9.64 FCL +9.64 FCL +9.64 FCL

of Dubai South, Dubai


+57.64 FCL RAILING +9.64 FCL +9.64 FCL
+57.64 FCL +57.64 FCL +57.64 FCL
+57.64 FCL +57.64 FCL

open below open below RAILING open below open below open below H
service open below service service service service service

4.25
open

open

open

open

open
open
open

open

open

open

open
RAILING
void
RAILING
void
RAILING void RAILING void RAILING void RAILING
Client
J

DUBAI SOUTH

Design consultant

Main Contractor

Sub Contactor

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

SERVICE FLOOR
CHILLED WATER LAYOUT

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000003 B
KEYPLAN:-

PLOT

NOTES:-

AHU-02 FAHU-01
AHU-01 FAHU-01 TYP-(02-10) TYP-(02-10) AHU-11 FAHU-11

SERVICE Ø32 CHWS&R Ø32 CHWS&R Ø32 CHWS&R


BLOCK Ø50 CHWS&R 0.42 L/s Ø50 CHWS&R 0.42 L/s Ø50 CHWS&R 0.42 L/s
1.44 L/s 1.29 L/s 1.46 L/s
Ø50 CHWS&R Ø50 CHWS&R Ø50 CHWS&R
1.86 L/s F/B 1.71 L/s F/B PICV 1.88 L/s F/B

OFF-FCU-1 PICV Ø20 CHWS&R Ø20 CHWS&R PICV


OFF-FCU-02 OFF-FCU-02A 0.17 L/s OFF-FCU-11
OFF-FCU-1A 0.17 L/s Ø20 CHWS&R
TYP-(2-10) TYP-(2-10) OFF-FCU-11A 0.18 L/s

Ø65 CHWS&R Ø65 CHWS&R


2.05 L/s F/B-T/A Ø50 CHWS&R
2.2 L/s F/B-T/A 2.24 L/s F/B-T/A

OFFICE-01 OFFICES-(02-10) OFFICE-11

CONDENSING UNIT CONDENSING UNIT

MEZZANINE
FLOOR CONDENSING UNIT FOR CONDENSING UNIT FOR
LV ROOM BMS,MTR ROOM DRV DRV DRV

Project
Design and construction of Aerospace
FCU-02
Supply Chain Facility Phase 05
FCU-1
TYP-(2-10) Plot AC6-18C, At The Aviation District
SB-FCU-2 SB-FCU-1,1A
of Dubai South, Dubai

PICV Client
SB-DX-LV PICV FCU-11
PICV PICV
Ø20 CHWS&R
Ø20 CHWS&R
0.19 L/s
Ø20 CHWS&R 0.35 L/s Ø20 CHWS&R Ø20 CHWS&R DUBAI SOUTH
0.17 L/s 0.17 L/s
0.11 L/s

Design consultant

LV ROOM ETS ROOM WH-PORTAL-01 WH-PORTAL-(02-10) WH-PORTAL-11

Main Contractor
ETS

BTU METER BTU METER BTU METER


CHW
RETURN Ø150 CHWS&R
25.24 L/s Sub Contactor
CHW Ø150 CHWS&R
SUPPLY 25.24 L/s

GROUND FLOOR

B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

A 05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title

SCHEMATIC
CHILLED WATER LAYOUT

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000004 B
KEYPLAN:-

ENERGY CALCULATOR PLOT

THIS TYPE OF OUTPUT SIGNAL


SHALL BE LINK TO ENERGY
CALCULATOR WAS WALL
NOTES:-
MOUNTED IN MECHANICAL
RISER ROOM AR EACH LEVEL.

SUPPLY TEMP
FLOW METER
ISOLATION VALVE ISOLATION VALVE
Normal Open Normal Open

CHILLED WATER RETURN


RETURN TEMPERATURE
DOWNSTREAM UPSTREAM
SENSOR

PIPING CONNECT TO
FAN COIL UNITS
ISOLATION VALVE
Normal Open

CHILLED WATER SUPPLY


SUPPLY TEMPERATURE
Y STRAINER SENSOR
UPSTREAM OF TEMPERATURE
SENSOR

01 TYPICAL INSTALLATION DETAIL OF


AC BTU METERING SYSTEM (HORIZONTAL)

Project
Design and construction of Aerospace
Supply Chain Facility Phase 05
LEGEND Plot AC6-18C, At The Aviation District
PICV PRESSURE INDEPENDENT CONTROL VALVE of Dubai South, Dubai
A.A.V AUTOMATIC AIR VENT
PRESSURE INDEPENDENT 2 PORT FULL STROKE Client
T.P TEST POINT
MODULATING CONTROL VALVE (PICV)
D.C DRAIN COCK
DUBAI SOUTH
NC NORMALLY CLOSED
F.C.U FAN COIL UNIT
AHU AIR HANDLING UNIT BINDER SELF SEALING TEST POINT (T.P.) Design consultant
FAHU FRESH AIR HANDLING UNIT
A.A.V WITH VALVE (TYP)
FLANGED FLEXIBLE
A.A.V CONNECTION
(FLANGED TYPE)
IV T.P. T.P. Main Contractor
DI-ELECTRIC UNION

FULL BORE
Sub Contactor
BY-PASS VALVE (F.C.U OR AHU OR FAHU)
(NC= NORMALLY CLOSED) THERMOMETER

IV T.P. STRAINER T.P.

D.C

TO CONDENSATE INSULATED EXTENDED B 13.03.24 AK SK MJB REVISED AS PER COMMENTS

DRAIN STACK DRIP TRAY FOR VALVE PACKAGE A 05.03.24 AK SK MJB ISSUED FOR APPROVAL

Rev. Date Drn. Chk. Apr. Description


Revision History

Drawing Title
01 TYPICAL CONNECTION DETAIL OF (F.C.U/AHU/FAHU) STANDARD DETAIL -
AC WITH 2-PORT VALVE WITH DRAIN PAN BTU METER & ALL UNITS

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-CHW-000005 B
KEYPLAN:-

PLOT

NOTES:-

Project
Design and construction of Aerospace
Supply Chain Facility Phase 05
Plot AC6-18C, At The Aviation District
of Dubai South, Dubai

Client

DUBAI SOUTH

Design consultant

Main Contractor

Sub Contactor

00 06.03.24 AK SK MJB ISSUED FOR APPROVAL


Rev. Date Drn. Chk. Apr. Description
Revision History

Drawing Title

EQUIPMENT SCHEDULE

Drawn Checked Approved Scale/A1


AK SK MJB 1:350

Drawing No. Rev.


RAQ-RDJ184-DWG-MEP-MEC-000004 00