Low Voltage Switchgear

Date : 05 Maret 2024 Location : Switchyard

Project Name : Peusangan 1 HEPP Equipment Name : LV Switchgear

Client/Customer : PT. PLN (Persero)

Interlock Scheme Test

Scheme No. Incoming Bus Tie Incoming Non Bus Tie Incoming Status
from BS TR 1 No. 1 From DG Set Essential No.2 from BS TR 2 Ok/ Not
Ok
Ok
Off Open Open Open Open Open Open
Normal Open Close / Open Ok
Close Close Close
Operation 1 (Can’t Close) Open (Can’t Close)
Normal Open Open Close / Ok
Close Close Close
Operation 2 (Can’t Close) (Can’t Close) Open
Black Start Open Close /
Close Close Close Close Ok
(DG Opration) (Can’t Close) Open