MATERIALS ESTIMATES FOR THE PROPOSED NEW GENERATION COLLEGE CLASSROOM AT OLUKOTUN COMPOUND,

ILERO.
ITEMS DESCRIPTION QTY UNIT RATE
FRAME STRUCTURE
MATERIALS SCHEDULE

CONCRETE CASTING GRADE 20KN/mm2 ,


COLUMN BASE+STUMB COLUMN,BEAM,
STAIRCASES AND FLOOR SLAB.
A Cement 12 Ton

B Sand 40 Ton

C Granite 88 Ton

REINFORCEMENT IN COLUMN BASES


D 16mm Bar in column and Beam 1.5 Ton

E 12mm bar in column base and slab 3.25 Ton

F 8mm bar links 0.5 Tons

G Binding wire 5 Roll

Sawn formwork for column and beam slab


H and staircase (25x300x3000) 471 Nr

J Sawn formwork struct(50x75x3000) 122 Nr

K Sawn formwork struct Bamboo 100 Nr

L 3inches nail 3 Bags

SPONSOR BY : PREPARED BY :
REV'D DR AND REV'D MRS S.E.ABRAHAM. JTC Concepts 08028108597,OCT;2023.
MATERIALS ESTIMATES FOR THE PROPOSED NEW GENERATION COLLEGE CLASSROOM AT OLUKOTUN COMPOUND,
ILERO.

Carried to Summary N

SPONSOR BY : PREPARED BY :
REV'D DR AND REV'D MRS S.E.ABRAHAM. JTC Concepts 08028108597,OCT;2023.
MATERIALS ESTIMATES FOR THE PROPOSED NEW GENERATION COLLEGE CLASSROOM AT OLUKOTUN COMPOUND,
ILERO.
AMOUNT

SPONSOR BY : PREPARED BY :
REV'D DR AND REV'D MRS S.E.ABRAHAM. JTC Concepts 08028108597,OCT;2023.
MATERIALS ESTIMATES FOR THE PROPOSED NEW GENERATION COLLEGE CLASSROOM AT OLUKOTUN COMPOUND,
ILERO.

SPONSOR BY : PREPARED BY :
REV'D DR AND REV'D MRS S.E.ABRAHAM. JTC Concepts 08028108597,OCT;2023.
NO DESCRIPTION UNIT QTY RATE AMOUNT
N

BILL NO. 3 - ELEMENT NR 1 - SUB


STRUCTURE (PROVISIONAL

SECON
D GATE
HOUSE

Site clearance

A Clear site of all bushes, shrubs, under- Sq.m 0


growths including grubbing up roots

Site Preparation

B Excavate over site average 150mm deep Sq.m 32 77.53 2,480.96


to remove vegetable soil, wheel a
distance not exceeding 100metres and
deposit, spread and level where directed

Excavation and Earthworks

C Excavate trenches to receive foundation Cu.m 10 485.33 4,853.30


exceeding 0.3m in width and maximum
depth not exceeding 2.0m

D Ditto pits for column bases Cu.m 9 485.33 4,367.97

Disposal

E Backfilling around trenches and pits Cu.m 7 291.20 2,038.40


well compacted.

F Remove surplus excavated materials Cu.m 17 446.50 7,590.50


from site distance not exceeding
100metres and deposit, spread and level
where directed.

Filling

G Imported earth filling to make-up level, Cu.m 7 2,426.64 16,986.48


spread and compacted in layers not
exceeding 150metres.
exceeding 150metres.

H 150mm (average) bed of hardcore well Sq.m 22 2,223.77 48,922.94


compacted and consolidated in layers not
exceeding 150mm thick and blinded with
fine materials to receive concrete.

To collection 87,240.55