Date Tested Layer Location Start End

August 17, 2023 Subgrade Road A 0+360 0+380


August 25, 2023 Subgrade Road A 0+000 0+360
August 26, 2023 Subgrade Road A 0+380 0+700
August 29, 2023 Subgrade Road A 0+700 0+900
September 4, 2023 Subgrade Road A 1+140 1+700
September 5, 2023 Subgrade Road B 0+000 0+340
Subgrade Road A 1+700 1+729.35
Length Unit RFI Number
20 Completed road mock-up
360 Completed
320 Completed
200 Completed
560 Completed
340 Completed
29.35 Pending 106 Damaged due to rain
90 0.5
1620 9 99.32 102.66 96.6 101.37 103.11
1440 8
900 5 103.19 99.98 97.51 97.09 97.89
2520 14
1530 8.5
132.075 0.73375
Date Tested Layer Location Start End
August 30, 2023 Subbase Road A 0+000 0+200
August 31, 2023 Subbase Road A 0+360 0+380
September 5, 2023 Subbase Road A 0+200 0+440
September 9, 2023 Subbase Road A 0+440 0+720
Subbase Road A 0+720 0+880
September 11, 2023 Subbase Road A 1+200 1+380
Road A 1+140 1+200
Road A 1+380 1+500
Length Unit RFI Number
200 Completed
20 Completed road mock-up
220 Completed
160 Completed 103
160 Pending 126 On-going temporary cross drain
180 Completed
60 Pending 127 recompaction needed
120 Pending recompaction needed
900 5
90 0.5
990 5.5
720 4
720 4
810 4.5
270 1.5
540 3
73 103 CORNER 39 TO 40
41 73