1. The daily site report from TEPC & PESTECH JV documents progress on the construction of four 132/33/11kV GIS substations under contract IQP24-MOE-LOT1.
2. Weather conditions and manpower levels are reported for work done at the AL BOAYTHA SUBSTATION site on February 26, 2024.
3. Works completed that day included inspection of the first crush stone layer, supplying sub base for the second layer, supplying steel bar, and laying the second sub base layer.
1. The daily site report from TEPC & PESTECH JV documents progress on the construction of four 132/33/11kV GIS substations under contract IQP24-MOE-LOT1.
2. Weather conditions and manpower levels are reported for work done at the AL BOAYTHA SUBSTATION site on February 26, 2024.
3. Works completed that day included inspection of the first crush stone layer, supplying sub base for the second layer, supplying steel bar, and laying the second sub base layer.
1. The daily site report from TEPC & PESTECH JV documents progress on the construction of four 132/33/11kV GIS substations under contract IQP24-MOE-LOT1.
2. Weather conditions and manpower levels are reported for work done at the AL BOAYTHA SUBSTATION site on February 26, 2024.
3. Works completed that day included inspection of the first crush stone layer, supplying sub base for the second layer, supplying steel bar, and laying the second sub base layer.
Project Name : Construction of Four 132/33/11kV GIS Substations
Contract Number : IQP24-MOE-LOT1 Lot Number : LOT 1 Contractor Name : TEPC & PESTECH JV Substation Abbreviation and Name : AL BOAYTHA SUBSTATION Date : 26/02/2024
Time, Temperature, weather H:M ˚C Weather Condition (Sunny, raining,
condition windy, foggy, dusty ….) 1 st record (starting work at site) 07:00 am 11 (Sunny) 2nd record at noon time 01:00 pm 16 (Sunny) 3 rd record (finishing works at site) 04:00 pm 20 ( raining) Manpower Quantity Machinery, Equip. Tools and Quantities 3 loaders 2 excavator 1 crane 10 dump truck 1 front loader Total No. Civil Electrical Mechanical Installation testing/commis - Engineers 3 3 - - sioning
- Foreman 2 2 - -
- Labors 20 20 - -
The provided Safety Equipment's/Means:
Works and Progress:
1- Inspection done for 1st layer crush stone.
2- Supplying sub base for the 2nd layer 3- Supplying steel bar 4- supplying test for steel bar 5- Laying 2nd layer subbase On behalf of the Contractor Signature: