Contractor Daily Site Report Report No.

: BOA-006

Project Name : Construction of Four 132/33/11kV GIS Substations


Contract Number : IQP24-MOE-LOT1
Lot Number : LOT 1
Contractor Name : TEPC & PESTECH JV
Substation Abbreviation and Name : AL BOAYTHA SUBSTATION
Date : 26/02/2024

Time, Temperature, weather H:M ˚C Weather Condition (Sunny, raining,


condition windy, foggy, dusty ….)
1 st record (starting work at site) 07:00 am 11 (Sunny)
2nd record at noon time 01:00 pm 16 (Sunny)
3 rd record (finishing works at site) 04:00 pm 20 ( raining)
Manpower Quantity Machinery, Equip. Tools and
Quantities 3 loaders
2 excavator 1 crane
10 dump truck
1 front loader
Total No. Civil Electrical Mechanical Installation testing/commis
- Engineers 3 3 - - sioning

- Foreman 2 2 - -

- Labors 20 20 - -

The provided Safety Equipment's/Means:


Works and Progress:

1- Inspection done for 1st layer crush stone.


2- Supplying sub base for the 2nd layer
3- Supplying steel bar
4- supplying test for steel bar
5- Laying 2nd layer subbase
On behalf of the Contractor
Signature:

Name: Eng. Abdalkahar Adil


Date: 26/2/2024