Professional Documents
Culture Documents
P6F 1 7 Practice
P6F 1 7 Practice
2. To create a calendar, click Add, and then specify work time and non-work time.
• Select the Default check box next to a calendar to set the default calendar assignment for all new
projects added to the database.
• Change the default calendar assignment for an individual project on the Defaults tab in Project Details.
• Link resource and project calendars to global calendars. Any changes made to a global calendar is
automatically applied to all resource and project calendars linked to it.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
2
Viewing a Global Calendar
At the top of the dialog box, select Total work hours/ day for a numeric total, or selected Detailed work hours/day
for an hour-by-hour view. The colors in the calendar indicate the type of work time defined for each day:
6. Click OK.
7. Click Close.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
3
Adding a project Calendar
Create a project calendar to reflect work time for a specific project. To create this calendar, you will use the
Standard 5 Day Workweek global calendar as a template.
3. Select Project.
4. Click Add.
6. In the Calendar Name field, type <3 Day Workweek>, and then press Enter on your keyboard.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
4
Linking the Holidays Calendar and Setting the Workweek
Instead of manually entering company holidays, the global calendar containing holidays can be lined to the new
project calendar. Select the global calendar to use in the Inherit holidays and exceptions from Global Calendar
list.
Click Workweek to set the number of work hours for each day.
Select Total work hours/day to view the total number of work hours in the selected day in the Work hours/day
field.
Select Detailed work hours/day to view each work hour in the selected day. You also can set work time in 30-
minute increments.
Link a global calendar’s holidays to the newly created calendar and set the workweek.
1. In Calendars dialog box, confirm that 3 Day Workweek is selected, and then click Modify.
3. In the Inherit holidays and exceptions from Global Calendar list, select Signature Corp Holidays.
4. Click Workweek.
5. In the Calendar Weekly Hours dialog box, type <0> hours for Monday and Friday, and then click OK.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
5
Setting Non-Work Time
A project calendar may need to have non-work time days that are different than those in the global calendar to
which it is linked. To allow this, you can manually enter non-work time into the project calendar.
2. Click Nonwork.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
6
Setting Exceptions
There are times when you need to set an exception in the calendar – a regularly scheduled non-work day that
needs to become a work day. For example, you may need to change some non-work days to work days because
the project is behind schedule. When you schedule the project, activities that use the modified calendar will
schedule accordingly.
2. Click Work.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
7
Viewing and Assigning Calendars
The calendar selected in the Defaults tab is Project Details is automatically assigned to new activities.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
8
To assign a different calendar to an activity, manually change the assigned calendar on the General tab in Activity
Details. Assign a specific calendar to a resource in the Details tab in Resource Details.
2. In the Activity Table, select an activity, BA5100 – Install Exterior Doors and Windows.
5. On the Select Activity Calendar Display Options bar, click Project Calendars.
Dates in the project schedule will not reflect the new calendar assignment until the project is
rescheduled.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
9
Lesson Review
Key Concepts
• Specify a calendar as global, project, or resource-specific.
• Assign global calendars to projects, activities, and resources.
• The calendar type determines whether you can use calendars on activities, resources, or both.
• The default project calendar is automatically assigned to new activities.
Review Questions
2. True or False: Activity type determines whether an activity uses an activity calendar or the
calendar of its assigned resource(s).
3. True or False: You cannot enter non-work days in a project calendar if it is linked to a global
calendar.
Copyright © 2020, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks of Oracle and/or its affiliates. Other names may be trademarks of their respective owners.
10