PO/WO Data

PO WO
Manual/ERP Project Sum of Total Sum of Total V Sum of Total
ERP
ADORNIA 1,973,844.21 579,632.11 449,580.42
COURTYARD 9,880,986.75 6,528,113.09 127,835,353.74
SIGNATURE 4,031,229.01
THE ADDRESS 5,373,136.12 2,514,292.64 1,575,590.00
The CREST 8,516,463.76 895,738.00 1,961,981.00
Manual
KAYAR 25,000.00
SIGNATURE 19,075,096.25 ### 2,020,538.07
THE ADDRESS 18,978,087.72 ### 24,658,226.69
Total Result 63,797,614.82 ### 162,557,498.94
VAR% 58% 4%
Sum of Total VAR Value

47,263.00
3,352,152.38

11,600.00

202,053.81
3,109,626.99
6,722,696.18
PO/WO
S.No Date PO/WO Manual/ERP Project Sub Project Vendor Name Details UOM QTY Ex GST Rate GST % Total
Number
45 8/10/2023 PO PO-5119 Manual THE ADDRESS Sri Sai Engg & Fabrications MS Plate Kgs 1140 97.00 18% 130,484.40
114 8/18/2023 WO WO-5006A Manual THE ADDRESS Sri Sai Engg & Fabrications MS & SS Works in 40 villas LS 1 5,983,666.00 18% 7,060,725.88
PO Expiry
Payment Terms Advance% Total VAR Value
Date
15 days from invoice date
10% WO as mobilzation advance 10% 706,072.59
1st Payment on
or Before