Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to
km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojana, in
the state of Andhra Pradesh and Tamil Nadu (Package-I).
1. PRESTRESSING WORKS
A) Scope: -
2) Stressing of tendons.
3) Grouting of tendons.
These are dealt in detail in the following sections in this method statement.
1) Hydraulic Jacks
2) Hydraulic Pumps
3) Bearing plate
4) Permanent wedges
5) Master wedges
9) Abrasion cutter
A. Uncoiling of Strand:-
The operation will be carried out on elevated platform to prevent contact with
earth / mud. The strand will be uncoiled very carefully since the end of the coil
has the tendency to fly with a jerk. The elevated platform on which the coil is
placed is termed as coil dispenser with supporting frames to avoid jerking of the
strand end.
2|Page
Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to
km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojana, in
the state of Andhra Pradesh and Tamil Nadu (Package-I).
The uncoiled strands will be laid on the elevated platform and cut to the required
length as given in the drawings including the jacking length required at the time
of stressing. The cutting of strands will be done by abrasive cutter only.
2) The strands should be free from dust, grease, and oil stains.
4) The anchor head is cleaned well (to remove anti corrosive oil which was
applied before dispatch). The taper holes should be free from dust and oil
stains.
5) The H.T Strands will be inserted one by one into the anchor head, and they
will be secured firmly by wedges.
1) Stressing of Tendons will be carried out after the concrete attains the required
strength. Before stressing the following points will be checked mentioned
below.
a) Calculate the maximum pressure required as per the jack details and
apply correction factors depending on the calibration certificate of the
pressure gauge and the jack.
c) The wedges will be cleaned to remove dust or oil traces from the threads
of the wedges.
d) The grip lengths of the H.T Strands will be cleaned to remove dirt or oil
traces.
3|Page
Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to
km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojana, in
the state of Andhra Pradesh and Tamil Nadu (Package-I).
3) The hydraulic jack with wedge seating (collar plate) device will be
assembled over the Anchor Head.
4) The hydraulic jack and wedge-seating device will be connected to a hydraulic
pump by high and low-pressure hoses.
5) The stress operations will begin after aligning the hydraulic jack and an
initial force will be given to remove any slackness in the tendon. Ram
movement will be noted from this stage. The pressure will be increased
slowly in stages up to the maximum required pressure. Ram movement will
be noted for each increment of pressure.
8) After wedges locking, the jack will be released and shifted to another tendon
as per stressing sequence. All observations will be recorded in the Stressing
Report.
4|Page
Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to
km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojana, in
the state of Andhra Pradesh and Tamil Nadu (Package-I).
4) Grout caps
5) Marsh cone
6) Thermometer
7) Cube moulds
C. Materials Required for Grouting: -
▪ Cement grout will be prepared at site by mixing cement, water, Ice and
Cebex 100/200 or similar as per the approved mix design.
D. Pre-Grouting Operations: -
▪ The tendon duct will be washed well with water and then this water will be
flushed by compressed air.
E. Grouting Operations: -
▪ The mixing of the grout will be done in the mixing drum as per the mix design,
the grout will be agitated thoroughly by agitator. The temperature of grout
will be maintained at 25 degrees Celsius by adding Ice to the water.
▪ The consistency of mixed grout from the mixing drum will be checked
before commencement of grouting.
▪ Grouting will be started with a low pressure of injection. As the grout fills
up and flows forward, the pressure will be increased and allows flow of grout
through outlet until required consistency come out.
▪ At this stage, pumping will be stopped. The outlet will be closed, and the
pumping will be resumed. The pressure will be increased and we will be
allowed to build 3 to 5 Kg / Sq. Cm. This pressure will be maintained for about
1 min.
▪ After this the inlet will be closed and grout pipe will be shifted to another tendon.