Professional Documents
Culture Documents
KCC IE MPR February - 2024
KCC IE MPR February - 2024
Independent Engineer
M/s MSV International Inc.in Association with ARMENGE
Engineering and Management Consultants Pvt. Ltd
Concessionaire
M/s KCC Chittoor Highways Private Limited
February -2024
Development of Six Lane Chittoor – Thatchur Highway from Km.0.000 (Varadhrajulu) to Km.61.380 (Veera Kaveri Raja Puram) on HAM
Mode Under Bharatmala pariyojna in the state of Andhra Pradesh and Tamilnadu (Package-1)
2. Project Overview
2.1. Salient Features of Project 81
4. Physical Progress
4.1. Detailed Scope of work & Physical Progress by 94
component
5. Land Acquisition and Clearance
5.1. LA Summary 100
1. Executive Summary
1.1 Construction Progress in current month
Sl.no Key Reporting Metrics Value/%/Amount
Scheduled cumulative Physical Progress
1) 61.89 %
(%)
Cumulative Physical progress up to current
2) 43.05 %
month (%)
3) Physical Progress during current month (%) 2.85 %
4) Financial Progress (%) 50.40%
5) Cumulative Expenditure till Date (Rs. Cr.) 717.26 Cr
Tests passed as % of total tests witnessed
6) 98.00%
by IE
Tests passed as % of total tests Conducted
7) 98.00%
by Concessionaire
8) Number of pending COS proposals Nil
ii. Entire land in the project stretch handed over to the concessionaire. However,
in Tamil Nadu stretch of the project, trench-cut done, Cultivation stopped,
access for the vehicles to reach all major structure allowed; however, farmers
protesting against road works at site demanding payment of Arbitration Amounts
also before taking-up the work.
Recommendation:
i. Concessionaire is requested to mobilize suitable and sufficient skilled staff to
improve work progress at structures, Interchanges, ROB, IOCL Portal structure
and Minor bridge at Ch: 16+361. Shifting of EHT tower of PGCIL at Ch: 17+900
and 35+950 and crossing of Electrical cables at Ch: 12+800, 14+350 and Ch:
36+150 are not taken up for which Main carriage way get affecting. So,
concessionaire is requested to expedite utility shifting works in all balance
locations immediately.
ii. Concessionaire should strictly follow the consumption register for steel, cement,
Bitumen aggregates and other records which are related to consumption of QC
Laboratory.
1. Work unavailability and Length (km) Total 3. Length Completed by layer Service Road
reason for unavailability 2. (LHS+RHS)
(LHS + RHS/2) %
Total Length Length (Km) Total
Length Total 43.800 100 % Scope (LHS+RHS)
(Km) % of MCW %
PQC 0 0 Total Length
Total Length 43.800 100 % of (Service 20.065 (10.31+9.755) 100 %
DLC 0 0 Road)
Total Work front
0.00 0.00% BC 0 0
Unavailable
BC 20.065
Pending Land DBM 20.175 50.33% - -
0.00 0.00%
Acquisition
WMM
20.755 51.78% DBM 0.000 -
(CTB+AIL)
Pending -
0.00 0.00% GSB/CTSB 25.547 62.55%
Clearances AIL 20.065 - -
Sub-Grade 29.547 72.34%
Encumbrances 0.00 0.00% C&G 42.500 97.03% CTSB 20.065 - -
Sub-Grade 20.065 - -
C&G 20.065 - -
Interchange 03 39.07% - 03 0
IOCL Portal 01 - - 0 01
LVUP 20 80.17% 16 01 03
Major Elevated
Structures over Pond 07 41.20% - 07 0
Minor Elevated
Structures over Pond 02 32.02% - 02 0
ROB 01 17.09% - 01 0
VUP 07 85.71% 06 01 0
2 Project Overview
Scheduled
730th Day 100% 04.12.2024 - - -
completion
Chainage Expected
Ongoing/
(s) Length Action(s) date/Actu
Sr. Issue New Concerned Action(s) taken
Type affected Affecte suggested by al date for
No Description Issue/ Authority till now
due to the d (Km) the AE resolving
Resolved
issue issue
Stage-II Forest
Stage-II Forest
clearance
clearance
Working obtained (final
Ch: obtained
permission Other 514.05 approval) on _
1 Resolved Forest (42+245 to (final approval)
required for Clearances Mtrs 1st January
42+759) on 1st January
Forest Land 2024. (Emb
2024. (Emb Work
Work in
in progress)
progress)
NIL
Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojna,
in the state of Andhra Pradesh and Tamil Nadu (Package-I)
KCC Chittoor Highways Pvt. Ltd.
Contract Price Weightages Annexure - I of Schedule G
Weightage Physical Quantity Physical Progress (%)
Stage for in
Total
measurement of Percentage Remark
Item Unit Scope Previous This Upto Previou This
Physical to the Upto Date s
(Quantity) Month Month Date s Month Month
Progress Contract
Price
1 2 3 4 5 6=7+8 7 8 9=10+11 10 11=8/4*5 12
Road works B-New
including Realignment /
Culverts, Minor Bypass
Bridges, 1) Earthwork
Underpasses, upto top of the Km 81.684 14.56% 59.094 55.189 3.905 10.53% 9.84% 0.70%
Overpasses, Sub-grade
Approaches to 2) Granular work
ROB/ RUB / (Sub-base, base,
Major Bridges / shoulders)
Structures (but (a) GSB / CTSB Km 81.684 3.47% 51.094 47.942 3.152 2.17% 2.04% 0.13%
excluding
service roads) (b) WMM / CTB +
Km 80.164 3.58% 41.510 38.900 2.610 1.85% 1.74% 0.12%
AIL
3) Shoulders Km 81.684 0.16% -
4) Bituminous
work
(a) DBM Km 80.164 8.59% 40.350 36.760 3.590 4.32% 3.94% 0.38%
(b) BC Km 86.080 3.63% - - - 0.00% -
5) Rigid
Pavement -
Concrete works
a) DLC Km 1.520 0.27% - - - 0.00% -
b) PQC Km 1.520 1.05% - - - 0.00% -
Elevated
Structure Major
4) Reinforced
earth wall
(includes
Approaches of
Structures ROB,
(elevated Underpasses,
sections, Overpasses,
reinforced Flyover etc.
earth) a) RE Wall
as per
Casting as (10% Sqm 87592 0.35% 55385.000 55,385.000 - 0.11% 0.11% 0.000%
Circular
of total weightage)
b) RE Wall
1679.5
Erection as (90% Sqm 87592 3.14% 53798.577 52,119.000 1.93% 1.87% 0.060%
77
of total weightage)
Utilities
EHT Lines Km 0.545 0.25% - - - 0.00% -
EHT Crossing Nos. 10 3.56% - - - 0.00% -
Electrical and
HT/LT lines
Public Health
(including
Utilities Km 4.240 0.30% 3.790 3.790 0.000 0.27% 0.27% 0.000%
Transformers if
any)
HT/LT line
Nos. 97 0.56% 97.000 97 0.000 0.56% 0.56% 0.000%
crossing
Other Works
(i) Service road /
Slip Roads / Km 20.065 1.70% - - - 0.00% -
Connecting Road
(ii) Toll Plaza
(including main
carriageway Toll
0.10% Plaza and
Interchange
ramp plaza)
(a) - On
Completion of Toll LS - 1.03% - - - -
Plaza
(iii) Road Side
Km 97.030 1.06% - - - 0.00% -
Drains
Pending (ha)
Pending(ha)
(Crore Rs.)
(Crore Rs.)
Total Land
(Crore Rs.)
Disbursed
Deposited
Done(ha)
Done(ha)
Done(ha)
Done(ha)
Acquired
by CALA
Awarded
Pending
Pending
Pending
leftto be
Amount
Villages
Amount
Amount
Amount
(Crore)
CALA
No of
(ha)
(ha)
(ha)
3G
3G
3H
3A
3A
3D
3D
3H
RDO/
25 0 20.08 204.90 0 224.98 0 262.57 0 325.614 124.81 124.81 113.47 11.34
CALA
SDRO 02 0 10.21 13.78 0 23.99 0 28.85 0 34.388 20.41 20.41 9.82 10.59
Grand
27 0 30.29 218.68 0 248.97 0 291.42 0 360.002 145.22 145.22 123.29 21.93
Total
Railways ROBs/RUBs)
Length
Proposal Description Status Current Stage Issues/ Comments
Impacted
Length affected
Date of Date of
Utility Category
Comments
request Progress certificate
(In Mtrs)
was approv Deposit of Estimate
Issue /
by of ion from
Name Status Department Received al by Supervisi Amount
Authority Physical Agency for
from Authori on (in Cr.)
for Shifting Complete
Concerned ty RO Charges
estimate on
Dept.
Shifting
of 400
Estimate
& 765 - PGCIL 24.12.2021 06.05.2022 - 10.11.2022 WIP-30% - 31.16 -
approved
kv
(EHT)
Shifting
of 132 11.11.2022
Estimate 19.01.2022& 30.06.2 -
& 220 - AP Transco 24.12.2021 & WIP -25% - 28.45
approved 19.07.2023 022
kv 05.08.2023
(EHT)
Shifting
Estimate APSPDCL- 11.08.2
of 33 kv - 12.04.2021 28.10.2022 14.02.2023 90% - 2.39 -
approved Reddigunta 022
(LT/HT)
Electrical
Shifting -
Estimate APSPDCL-
of 33 kv - 10.04.2021 09.05.2022 11.08.2 01.10.2022 95% - 1.73 -
approved Chittoor Rural
(LT/HT) 022
Shifting
Estimate APSPDCL- 11.08.2
of 33 kv - 10.04.2021 09.11.2022 14.02.2023 100% - 2.73 -
approved avalakunda 022
(LT/HT)
Shifting
Estimate APSPDCL-SR 11.08.2
of 33 kv - 02.05.2022 08.12.2022 14.02.2023 95% - 2.92 -
approved Puram 022
(LT/HT)
Shifting
Estimate TANGEDCO-
of 33 kv 24.12.2021 24.11.2022 - 17.10.2023 20% - 2.49 -
approved Podaturrpet
(LT/HT)
Recommended
COS by RO In-Principal
Proposal Concessionair Current COS By PD Physical
S.No Amount Approval By HQ
Details e Letter No Status (Approved Lt. Office Progress
(in Cr.)
no)
Construction of
new connectivity
for DRDO
strategic Approved Rs. 21.85
Location at SR Cr
Puram Mandal
Lt No. NHAI/
near Ch: 32+150 NHAI/ PIU-
Lt No. M/s KCC/ NHAI/RO-VJA Bharatmala/CTR/
CTR/15034/COS/
KCCHPL/FY /C-T /Pkg-I / PKG-I/COS/
1 CTR-Pkg-I
2023-24/797, 2024/ 609, DRDO(E-216014) A1 MCW
a. VUP @ Rs. /2024/157,
Dt: 28.12.2023 Dt: 28.02.2024 /999, Foundation
32+150 Approved 18,103,189 Dt: 09.02.2024
Dt: 17.10.2023 work
completed
b. Box Culvert Rs. Segmental
@ 31+400 4,032,801 Erection work
Approved
completed in
MCW Portion
In Principal
Approval NHAI/ PIU-
accorded by CTR/15034/COS/
Lt No. NHAI/ PIU- CTR-Pkg-I -
Lt No. NHAI HQ,s
CTR/CT/PKG- /2024/180,
Project COS KCC/KCCHPL/ (Detailed Rs. 21.55
2 Cr - I/COS (E-file-
Items FY2023-24/681, proposal yet to 219998) /1106, Dt: 13.02.2024
Dt. 18.10.2023 receive from (Detailed proposal
Dt: 13.02.2024
the yet to receive from
concessionair the concessionaire)
e)
Excavation
a. BC @0+400 work in
progress
Top Slab
b. BC @0+940 completed
7. Mobilization of Resources:
Outflow form
Cumulative inflow to Escrow Cumulative outflow to Inflow to Escrow during
TPC(Cr) Escrow during the
Till previous month (Cr.) Escrow till previous month the Month (Cr.)
Month (Cr.)
(Cr.)
Are the Escrow withdrawals in accordance with the order of withdrawal as specified in the concession Agreement? – Yes
Account No 7294588211
As per
Gradation MORT&H As required 5 5 0 0 0 0 5 5 0
Sec. 400
IS: 2720
Proctor
Part - 8
As required 3 3 0 0 0 0 3 3 0
Field IS: 2720
Density Part - 28
As required 5 5 0 0 0 0 5 5 0
Cement Treated
Atterberg's IS: 2720
7 Sub-Base (Mix
Limits Part - 5
As required - 3 3 0 0 0 0 3 3 0
Design)
IS: 2386
AIV Test
Part - 4
As required - 2 2 0 0 0 0 2 2 0
Compressiv IS: 516 &
e Strength IS 89
As required 2 2 0 0 0 0 2 2 0
Sp.Gravity
IS: 2386
&
Part - 3
As required 1 1 0 0 0 0 1 1 0
Absorption
As per
Gradation MORT&H As required - 5 5 0 0 0 0 5 5 0
Sec. 400
Atterberg's IS: 2720
Limits Part - 5
As required - 3 3 0 0 0 0 3 3 0
IS: 2720
Proctor
Part - 8
As required - 3 3 0 0 0 0 3 3 0
Cement Treated
IS: 2386
8 Base (Mix AIV Test
Part - 4
As required - - 2 2 0 0 0 0 2 2 0
Design)
Field IS: 2720
Density Part - 28
As required - 5 5 0 0 0 0 5 5 0
Compressiv IS: 516 &
e Strength IS 89
As required 2 2 0 0 0 0 2 2 0
Sp.Gravity
IS: 2386
&
Part - 3
As required 1 1 0 0 0 0 1 1 0
Absorption
As per
Gradation MORT&H As required - 8 8 0 0 0 0 8 8 0
Sec. 600
Atterberg's IS: 2720
Limits Part - 5
As required - 0 0 0 0 0 0 0 0 0
IS: 2720
Proctor
Part - 8
As required - 6 6 0 0 0 0 6 6 0
IS: 2386
AIV Test
Part - 4
As required - 6 6 0 0 0 0 6 6 0
Dry Lane
Field IS: 2720
9 Concrete (Mix
Density Part - 28
As required - - 0 0 0 0 0 0 0 0 0
Design)
3
IS: 516 Day 8 8 0 0 0 0 8 8 0
s
Compressiv 5 Specimen
7
e Strength
IS: 516 Day - 8 8 0 0 0 0 8 8 0
s
Sp.Gravity
IS: 2386
&
Part - 3
As required - 6 6 0 0 0 0 6 6 0
Absorption
Pavement As per
10
Quality Concrete
Gradation
MORT&H
As required - - 5 5 0 0 0 0 5 5 0
binder
Rate of
As per
Spread of
MORT&H
2 Tests/ Day 150 150 0 15 15 0 165 165 0
Binder
Penetration IS: 1203 1 Test / Lot 131 131 0 12 12 0 143 143 0
Softening
15
Binder(
Point
IS: 1205 1 Test / Lot 313.45 131 131 0 12 12 0 143 143 0
Bitumen) MT
Absolute
Viscosity
IS: 1206 1 Test / Lot 131 131 0 12 12 0 143 143 0
Extraction As per
Test MORT&H
1 Set/400 Tons 158 158 0 37 37 0 195 195 0
Agg.
IS: 2386
Impact
Part - 4
1 Test/ 350 m3 114 114 0 18 18 0 132 132 0
Value
Fl& El IS: 2386
Indices Part - 1
1 Test/350 m3 114 114 0 18 18 0 132 132 0
Stripping
DENSE
Value
IS: 6241 1 Set/Source 2 2 0 0 0 0 2 2 0
BITUMINOUS 6599.06
16 Sp.Gravity
MACADAM IS: 2386 MT
[D,B.M]
&
Part - 3
1 Set/Source 2 2 0 0 0 0 2 2 0
Absorption
Mix As per
Gradation MORT&H
1 Set/400 Tons 158 158 0 37 37 0 195 195 0
Stability of As per
Mix MORT&H
1 Set/400 Tons 158 158 0 37 37 0 195 195 0
Field
As per
Density
MORT&H
1/ 700 m2 463 463 0 64 64 0 527 527 0
(Core)
Extraction As per
Test MORT&H
1 Set/400 Tons 0 0 0 0 0 0 0 0 0
Agg.
IS: 2386
Impact
Part - 4
1 Test/ 350 m3 0 0 0 0 0 0 0 0 0
Value
Fl& El IS: 2386
Indices Part - 1
1 Test/350 m3 0 0 0 0 0 0 0 0 0
Stripping
Value
IS: 6241 1 Set/Source 0 0 0 0 0 0 0 0 0
BITUMINOUS
17 CONCRETE Sp.Gravity 0
IS: 2386
[ B.C] &
Part - 3
1 Set/Source 0 0 0 0 0 0 0 0 0
Absorption
Mix As per
Gradation MORT&H
1 Set/400 Tons 0 0 0 0 0 0 0 0 0
Stability of As per
Mix MORT&H
1 Set/400 Tons 0 0 0 0 0 0 0 0 0
Field
As per
Density
MORT&H
1/ 700 m2 0 0 0 0 0 0 0 0 0
(Core)
M -15 GRADE
07 Days IS: 516 1133.11 620 620 0 55 55 0 675 675 0
As per MORT&H -
28 Days IS: 516 m3 1169 1169 0 70 70 0 1239 1239 0
18 Concrete Cube M -20 GRADE
07 Days IS: 516 197.85 393 393 0 23 23 0 416 416 0
As per MORT&H -
28 days IS: 516 m3 1056 1056 0 57 57 0 1113 1113 0
M - 25 GRADE
Expected
Ongoing / Chainage (s) Length Action(s) Action
S. Concerned Date for
Issue Description New affected due affected taken till suggested Remarks
No Authority resolving
Issues to the issue (km) now by SC
issue
Drying of plants on
1 NA NA NA NA NA NA NA
Median
2 Large Potholes NA NA NA NA NA NA NA
Non Injured
x( Acciden Natur Roa ad ection ath Age Type Type e m
Gravlous
N at Accident ficati ulanc
Minor
M/ t e of Caus d Co type er Of of of respo a
Fatal
o e (am/pm) on of e/
F) Locatio Accid es featu nd and Con Victi Victi Vehicl nsible r
. Accid Patro
n ent res iti Contr diti m m e k
ent l
on ol on Vehic
le
NILL
1. Annexures:
7 VUP Nos. 7 6 1 6
LVUP Nos. 20 19 1 19
8
9 MNB Nos. 10 10 0 10
DATE OF
S.NO LETTER NO FROM TO DESCRIPTION
LETTER Remarks
MSV NCR-33
1 05.02.2024 ARMENGE/IE/NHAI/ IE KCC
CHI-THA/2023/542
MSV Visit to a factory at m/s Miki steel works PVT LTD,
2 07.02.2024 ARMENGE/IE/NHAI/ IE KCC Bangalore for HT Strands-Reg.
CHI-THA/2023/546
MSV Issuance of NCR-34-Reg.
3 10.02.2024 ARMENGE/IE/NHAI/ IE KCC
CHI-THA/2023/548
MSV Submission of QAP and WPSS for fabrication of
NHA
4 12.02.2024 ARMENGE/IE/NHAI/ IE composite I Girder for Span P1-P2 for ROB at
I
CHI-THA/2023/550 Km.6+697-Reg.
MSV Site inspection for the month of January-2024
5 12.02.2024 ARMENGE/IE/NHAI/ IE KCC
CHI-THA/2023/552
MSV Delay in submission of work programe and S curve-
6 14.02.2024 ARMENGE/IE/NHAI/ IE KCC reg
CHI-THA/2023/570
MSV Submission of monthly invoice
NHA
7 14.02.2024 ARMENGE/IE/NHAI/ IE
I
CHI-THA/2023/571
MSV Approval of Cutting Soil Area 42+300 to 42+750
8 14.02.2024 ARMENGE/IE/NHAI/ IE KCC BHS for Embankment and Subgrade layers.
CHI-THA/2023/572
MSV Provisional Approval of Borrow Area 11B for
9 15.02.2024 ARMENGE/IE/NHAI/ IE KCC Embankment and Subgrade layers.
CHI-THA/2023/573
Team Leader
Subratha Mukhopadhyay
Mobilized on 09.03.2022
Resident Engineer
B. Rama Rao
Mobilization on 13.02.2024
Bridge/Structural Engineer Senior Payment Specialist Senior Quality cum Road Safety Expert
E.Prahllada Reddy T . Rajasekhar Material Engineer K.Venkata Ramana Muthy
Mobilized on 21.03.2022 Mobilized on 28.04.2023 Ch:Ramakrishna Rao Mobilized on 28.04.2023
Mobilized on 29.04.2023
Monthly Export
Progress Report-February-2024 144
TBN
Development of Six Lane Chittoor – Thatchur Highway from Km.0.000 (Varadhrajulu) to Km.43.800 (Kumarajpet) on HAM Mode Under Bharatmala
pariyojna in the state of Andhra Pradesh and Tamilnadu (Package-1)
104 BRASS TEST SIEVE DIA: 15 MIC NOS 2 2 0 2 Copper Powder Coated
105 CAP AND PAN 200 MM NOS 4 3 1 4 Copper Powder Coated
106 STOP WATCH DIGITAL. NOS 4 2 2 4
107 MOISTURE CONTAINER 200 GRAM NOS 100 100 0 100 Aluminium
108 MOISTURE CONTAINER 50 GRAM NOS 50 50 0 50 Aluminium
109 HOT PLATES 200 MM NOS 4 3 1 4 1500Watt
110 TRAY - 8''X10'' NOS 6 4 2 6
111 ENAMEL TRAY 5"X7" NOS 6 6 0 6
112 ENAMEL TRAY 4'X4' NOS 6 6 0 6
113 ENAMEL TRAY-600X450X50MM NOS 8 8 0 8
114 ENAMEL TRAY-450X300X40MM NOS 8 6 2 8
115 ENAMEL TRAY-300X250X40MM NOS 10 8 4 12 10 no. old and Damaged
Circular 200mm dia. 04 no. old and
116 ENAMELED BOWL NOS 16 14 2 16
Damaged
Chutes type 31.5mm Aggregate, Min. Three
117 RIFFLE BOX 50 MM NOS 2 2 0 2
Pan Collector
118 SPATULA 4” NOS 15 13 2 15
119 SPATULA. 6" NOS 15 13 2 15
120 WATER TESTING KIT NOS 1 1 0 1
121 FIRST AID BOX. NOS 2 2 0 2
Geared Dwonappx. 120RPM 50 cycles with
LIQUID LIMIT WITH GROOVEING TOOL
122 NOS 1 2 0 2 spares, height block 1cm
MANUAL TYPE
high.
123 CONE PENETROMETER NOS 1 1 0 1
124 GLASS PLATE 20''X 20''X 10MM THICKNESS NOS 2 2 0 2
125 HIGH SPEED STIRRER WITH BEAKER GLASS NOS 1 1 0 1
126 HYDROMETER RANGE 1000-2000 NOS 2 2 2 4
127 HYDROMETER RANGE 995-1030 NOS 4 2 2 4
128 PIPETTE - 10 ML NOS 2 2 0 2
170 SLUMP CONE APPARATUS NOS 15 10 5 15 Slump Cone With Rod (Rod only 10)
171 WHEELBARROW NOS 4 3 1 4 Rubber Tyre (01 Old)
172 RECTANGULAR TRAY - 620X1000 MM NOS 5 5 0 5
173 GAUGED TROWEL NOS 6 4 2 6 Trowel 200mm Long (SSS)
174 SCOOPE 01 NUMBER NOS 10 8 2 10 500 ML (Stainless Steel)
175 SCOOPE 03 NUMBER NOS 6 6 0 6 1000 ML
AGGREGATE IMPACT VALUE TEST With Counter, Metal Measure, Cylindricalcup
176 NOS 2 1 1 2
APPARATUS , Tamping Rod.
LOS ANGELES ABRASION TESTING
177 NOS 1 1 0 1
MACHINE
With 150 mm & 100 mm Dia Core Bit-Hilti
178 CORE CUTTING MACHINE NOS 1 1 0 1 Make for Concrete Core
Cutting
179 CORE CUTTING BIT -100MM NOS 5 13 0 13
180 CORE CUTTING BIT -150MM NOS 5 12 0 12
Glass Jar With Brass Cone , Locking Ring
181 PYCNOMETER FLASK CAPACITY 500 ML NOS 5 5 0 5
and Rubber Seal-One Extra
Glass Jar With Brass Cone , Locking Ring
182 PYCNOMETER FLASK CAPACITY 1 LITER NOS 5 5 0 5
and Rubber Seal-One Extra
DIGITAL COMPRESSION AND FLEXURAL
183 NOS 1 1 0 1 With Peak Hold Facility, 100 KN Capacity
STRENGTH TESTING
LE-CHATELIER'S APPARATUS FOR Conforming IS : 5514-1969 Spring Brass
184 NOS 12 12 0 12
SOUNDNESS OF CEMENT Made.
CUBE VIBRATING MACHINE WITH DIGITAL Vibration Frequency of 12000 +/-
185 NOS 1 2 0 2
TIMER 400/Minute. (01 Nos. damaged)
186 VICAT NEEDLE APPARATUS SET 2 2 0 2 Confirming to IS : 5513-1976 With Dashpot.
187 CUBE MOULD 70.6 MM NOS 27 39 0 39 With ISI Mark IS: 10080-1982
188 STANDARD SAND 25KG GRADE-I BAG 10 10 0 10 Nellore Sand
189 STANDARD SAND 25KG GRADE-II BAG 10 10 0 10 Nellore Sand
190 STANDARD SAND 25KG GRADE-III BAG 10 10 0 10 Nellore Sand
191 LE-CHATELIER FLASK NOS 2 2 0 2 Gay-Lussac Type for Fines and Filler
B PROVING RING
1 PROVING RING 25KN 17-May-23 16-May-24 12 Month done Verified Third Party
2 PROVING RING 25KN 17-May-23 16-May-24 12 Month done Verified Third Party
3 PROVING RING 25KN 17-May-23 16-May-24 12 Month done Verified Third Party
4 PROVING RING 50KN 17-May-23 16-May-24 12 Month done Verified Third Party
5 PROVING RING 2.5KN 17-May-23 16-May-24 12 Month done Verified Third Party
6 PROVING RING 2KN 17-May-23 16-May-24 12 Month done Verified Third Party
C PROVING RING
1 Dial Gauge 17-May-23 16-May-24 12 Month done Verified Third Party
2 Dial Gauge 17-May-23 16-May-24 12 Month done Verified Third Party
3 Dial Gauge 17-May-23 16-May-24 12 Month done Verified Third Party
4 Dial Gauge 17-May-23 16-May-24 12 Month done Verified Third Party
5 Dial Gauge 17-May-23 16-May-24 12 Month done Verified Third Party
D GENERAL
Electronic Balance (Battery operated or
1 17-May-23 16-May-24 1 Year done Verified Third Party
power back up)
Electronic Balance (Battery operated or
2 17-May-23 16-May-24 1 Year done Verified Third Party
power back up)
3 Electronic Balance 17-May-23 16-May-24 1 Year done Verified Third Party
Electronic Balance(Battery operated or
4 17-May-23 16-May-24 1 Year done Verified Third Party
power back up)
5 Platform balance - Digital 17-May-23 16-May-24 1 Year done Verified Third Party
6 Graduated measuring Cylinder Glass 17-May-23 16-May-24 1 Year done Verified Third Party
Graduated measuring Cylinder Glass 25
7 17-May-23 16-May-24 1 Year done Verified Third Party
ml
Graduated measuring Cylinder Glass 50
8 17-May-23 16-May-24 1 Year done Verified Third Party
ml
Graduated measuring Cylinder Glass 250
9 17-May-23 16-May-24 1 Year done Verified Third Party
ml
Graduated measuring Cylinder Glass 500
10 17-May-23 16-May-24 1 Year done Verified Third Party
ml
Graduated measuring Cylinder Glass
11 17-May-23 16-May-24 1 Year done Verified Third Party
1000 ml
Graduated measuring Cylinder Glass 100
12 17-May-23 16-May-24 1 Year done Verified Third Party
ml
Graduated measuring Cylinder Plastic
13 17-May-23 16-May-24 1 Year done Verified Third Party
100 ml
tamping rod.
15 Los Angeles abrasion apparatus 01-May-23 30-Apr-24 1 Year done Verified In House
Core Cutting machine with 150 mm &
16 100 mm dia core bit-Hilti make for 01-May-23 30-Apr-24 1 Year done Verified In House
concrete core cutting
17 Pycno Meter 250ml 01-May-23 30-Apr-24 1 Year done Verified Third Party
18 Pycnometer 500ml 01-May-23 30-Apr-24 1 Year done Verified Third Party
19 Pycnometer1000ml 01-May-23 30-Apr-24 1 Year done Verified Third Party
G CEMENT TESTING EQUIPMENTS
Le Chatelier apparatus for soundness
1 01-May-23 30-Apr-24 1 Year done Verified Third Party
test of cement Set of 6.
High frequency Mortar cube vibrator for
2 01-May-23 30-Apr-24 1 Year done Verified Third Party
cement testing
Vicat needle apparatus for setting time
3 01-May-23 30-Apr-24 1 Year done Verified Third Party
of cement with plunger
4 70.6 x70.6 x 70.6 mm cubes 01-May-23 30-Apr-24 1 Year done Verified In House
Le Chatelier flask for specific gravity test
5 01-May-23 30-Apr-24 1 Year done Verified Third Party
of cement
6 Humidity Chamber 01-May-23 30-Apr-24 1 Year done Verified Third Party
7 Humidity meter 01-May-23 30-Apr-24 1 Year done Verified Third Party
8 Wind velocity meter (anemometer) 01-May-23 30-Apr-24 1 Year done Verified Third Party
9 Flexural Testing Machine 01-May-23 30-Apr-24 1 Year done Verified Third Party
H BITUMINOUS TESTING EQUIPMENTS
Bitumen penetrometer electrically
1 operated with digital timer & 01-May-23 30-Apr-24 1 Year done Verified Third Party
penetration needle
Bitumen laboratory mixer including
2 01-May-23 30-Apr-24 1 Year done Verified Third Party
required accessories (20 lit)
3 Bitumen Viscosity testing (saybolt ) 01-May-23 30-Apr-24 1 Year done Verified Third Party
Kinematic Viscosity & Absolute Viscosity
4 01-May-23 30-Apr-24 1 Year done Verified Third Party
Test App. With U tube
Ductility testing machine with ductility
5 01-May-23 30-Apr-24 1 Year done Verified Third Party
and elastic recovery moulds
Marshall stability machine (complete set
6 01-May-23 30-Apr-24 1 Year done Verified Third Party
100 mm & 150 mm Dia with Rammer)
Monthly Progress Report February-2024
161
Development of Six Lane Chittoor – Thatchur Highway from Km.0.000 (Varadhrajulu) to Km.43.800 (Kumarajpet) on HAM Mode Under Bharatmala
pariyojna in the state of Andhra Pradesh and Tamilnadu (Package-1)
Kotrakona
KCC/KCCCHPL/FY2022- Ultratech Cement Rheoplast Approve
11 M-50 PSC 12-Oct-22 Village G D Nil d
23/164 OPC 53 Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Ultratech Cement Rheoplast Approve
12 M-30 15-Jun-22 Village G D Nil d
23/068 OPC 53 Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Ultratech Cement JSW Rheoplast Approve
13 M-15 to M-35 28-Sep-22 Village G D d
23/152 OPC 53 (GGBS) Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Ultratech Cement JSW Rheoplast Approve
14 M-40 7-Jan-23 Village G D d
23/265 OPC 53 (GGBS) Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Ultratech Cement JSW Rheoplast Approve
15 M-35 to N-50 Village G D d
23/388 23 OPC 53 (GGBS) Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Bharathi Cement OPC Approve
16 M-15 to N-50 7-Jan-23 Village G D Nil Kunal Admixture d
23/261 53
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Bharathi Cement OPC Unirock Approve
17 M-15 to N-50 Village G D Nil d
23/379 23 53 admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Bharathi Cement OPC JSW Unirock Approve
18 M-15 to N-50 Village G D d
23/380 23 53 (GGBS) admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Bharathi Cement OPC Rheoplast Approve
19 M-35 to N-45 Village G D Nil d
23/383 23 53 Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Bharathi Cement OPC JSW Rheoplast Approve
20 M-15 to N-50 7-Jan-23 Village G D d
23/262 53 (GGBS) Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Bharathi Cement OPC JSW Rheoplast Approve
21 M-35 Village G D d
23/384 23 53 (GGBS) Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Ramco Cement OPC Approve
22 M-15 to M-50 7-Jan-23 Village G D Nil Kunal Admixture d
23/263 53
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Ramco Cement OPC Unirock Approve
23 M-15 to M-50 Village G D Nil d
23/377 23 53 admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Ramco Cement OPC JSW Unirock Approve
24 M-15 to M-50 Village G D d
23/378 23 53 (GGBS) admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 21-Nov- Ramco Cement OPC Rheoplast Approve
25 M-15 to M-50 Village G D Nil d
23/205 22 53 Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 30-Mar- Ramco Cement OPC Rheoplast Approve
26 M-35 to M-45 Village G D Nil d
23/385 23 53 Admixture
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 21-Nov- Ramco Cement OPC JSW Rheoplast Approve
27 M-15 to M-50 Village G D d
23/204 22 53 (GGBS) Admixture
Nellore
Source Approval of KCC/KCCCHPL/FY2022- Approve
28 4-Aug-22 Kotrakona Village G D Nellore d
Rock 23/098
KCC/KCCCHPL/FY2023- 23+500 TOLL Approve
29 GSB Mix Design 9-Jan-24 Nil Nil Nil d
24/831 PLAZA
Kotrakona
KCC/KCCCHPL/FY2022- Approve
30 CTSB Mix Design 6-Jan-23 Village G D Nil Nil Nil d
23/260
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- Approve
31 CTB Mix Design 3-Apr-23 Village G D Nil Nil Nil d
23/392
Nellore
Kotrakona
AIL/WMM Mix KCC/KCCCHPL/FY2022- Approve
32 6-Apr-23 Village G D Nil Nil Nil d
Design 23/394
Nellore
Kotrakona
KCC/KCCCHPL/FY2023- 11-Nov- Ramco Cement OPC Approve
33 DLC Mix Design Village G D Nil Nil d
24/727 23 53
Nellore
Kotrakona
KCC/KCCCHPL/FY2022- 16-May- Approve
34 DBM Mix Design Village G D Nil Nil Nil d
23/459 23
Nellore
Design of Filter Kotrakona
KCC/KCCCHPL/FY2022- Approve
35 media & Back Filling 28-Sep-22 Village G D Nil Nil Nil d
23/153
Material Nellore
Ultratech Cement
KCC/KCCCHPL/FY2023- 16-Aug- OPC 53 Ramco Fosroc Approve
36 Grouting Mix design Nil Nil d
24/588 23 Cement OPC-53 Cebex-100
Bharathi Cement OPC
53
Ultratech Cement
KCC/KCCCHPL/FY2022- Approve
37 Grouting Mix design 28-Jan-23 Nil OPC 53 Ramco Nil d
23/291
Cement OPC-53
Kotrakona Under
KCC/KCCCHPL/FY2023- Ultratech Cement Rheoplast
40 PQC 15-Feb-24 Village G D Revie
24/883 OPC 53 Admixture
Nellore w
Kotrakona Under
KCC/KCCCHPL/FY2023- Ultratech Cement JSW Rheoplast
41 PQC 15-Feb-24 Village G D Revie
24/884 OPC 53 (GGBS) Admixture
Nellore w
Remarks : 14 No’s Report to Received from Thirty Party For the month of December -2023 Mpr
11 No’s Report to Received from Thirty Party For the month of January -2024 Mpr
11 No’s Report to Received from Thirty Party For the month of February - 2024 Mpr
Source approval
KCC CHITTOOR HIGHWAYS PVT LTD. MSV INTERNATIONAL INC. ASSOCIATION WITH ARMENGE
SR CONCESSIONAIRE REMAR
Type of Material SOURCE OF MATERIAL PROPERTY DATE IE LETTER NO DATE STATUS
NO LETTER NO. KS
MSV
KCC/KCCCHPL/FY2022- 30-Aug-
1 Aggregate Kotrakona Crusher - 4-Aug-22 ARMENGE/HO/CHI- APPROVED
23/98 22
THA/2023/81
MSV
20+100 LHSCamp-1 (Bore well KCC/KCCCHPL/FY2022- 30-Aug-
- 4-Aug-22 ARMENGE/HO/CHI- APPROVED
No.1) 23/099 22
THA/2022/82
2 Water
MSV
4+300 LHS Camp-02 (Bore well KCC/KCCCHPL/FY2022- 30-Aug-
- 4-Aug-22 ARMENGE/HO/CHI- APPROVED
No.1) 23/099 22
THA/2022/82
MSV
KCC/KCCCHPL/FY2022- 18-Apr-
Ultra tech cement 8-Apr-23 ARMENGE/HO/CHI- APPROVED
23/44 22
THA/2022/08
MSV
The India Cement Ltd( KCC/KCCCHPL/FY2022- 3-May- 23-Jun-
ARMENGE/HO/CHI- APPROVED
Coromandel King) 23/053 22 22
THA/2022/38
MSV
KCC/KCCCHPL/FY2022- 9-May- 14-May-
2 CEMENT Dalmia Cement (Bharat) Ltd OPC 53 ARMENGE/HO/CHI- APPROVED
23/057 22 22
THA/2022/16
MSV
Bharathi Cement Corporaton KCC/KCCCHPL/FY2022- 13-Sep- 5-Jan-
ARMENGE/IE/KCCCHPL/CHI APPROVED
Private Limited 23/141 22 23
-THA/2022/147
MSV
KCC/KCCCHPL/FY2022- 20-Sep-
Ramco Cements Ltd ARMENGE/HO/CHI- 5-Dec-22 APPROVED
23/144 22
THA/2022/135
MSV
Rheoplast PC 2 KCC/KCCCHPL/FY2022- 14-May-
Rehoplast Technology Pvt Ltd 8-Apr-22 ARMENGE/HO/CHI- APPROVED
CS 23/46 22
THA/2022/17
3 ADMIXTURE
MSV
Kunaplast-P- KCC/KCCCHPL/FY2022-
Kunal Conchem Pvt Ltd 8-Apr-22 ARMENGE/HO/CHI- 16-Jul-22 APPROVED
50VC 23/46
THA/2022/56
MSV
KCC/KCCCHPL/FY2022- 18-Apr-
Fosrok Chemical India Pvt Ltd A-201 8-Apr-22 ARMENGE/HO/CHI- APPROVED
23/46 22
THA/2022/10
MSV
KCC/KCCCHPL/FY2022- 18-Apr-
Sika India Pvt Ltd - 8-Apr-22 ARMENGE/HO/CHI- APPROVED
23/46 22
THA/2022/10
MSV
Unicrete PC KCC/KCCCHPL/FY2022- 20-Jun- 22-Jun-
Unirock Chemicals Pvt Ltd ARMENGE/HO/CHI- APPROVED
250-C 23/071 22 22
THA/2022/36
MSV
KCC/KCCCHPL/FY2022- 20-Jun- 20-Aug-
Molecules Conchem Pvt Ltd - ARMENGE/HO/CHI- APPROVED
23/071 22 22
THA/2022/63
MSV
KCC/KCCCHPL/FY2022- 18-Aug-
STP Limited - 13-Jul-22 ARMENGE/HO/CHI- APPROVED
23/082 22
THA/2022/62
MSV
KCC/KCCCHPL/FY2022-
kunal Conchem Pvt. Lt. - 2-Sep-22 ARMENGE/HO/CHI- 8-Sep-22 APPROVED
23/130
THA/2022/98
MSV
KCC/KCCCHPL/FY2022-
Rheoplast Technology Pvt. Ltd. - 2-Sep-22 ARMENGE/HO/CHI- 8-Sep-22 APPROVED
23/130
CURING THA/2022/97
4
COMPOUND MSV
KCC/KCCCHPL/FY2022- 20-Jun-
Unirock Chemicals Pvt Ltd - ARMENGE/HO/CHI- 2-Sep-22 APPROVED
23/071 22
THA/2022/87
MSV
KCC/KCCCHPL/FY2022- 20-Jun- 24-Jun-
Molecules Conchem Pvt Ltd - ARMENGE/HO/CHI- APPROVED
23/071 22 22
THA/2022/43
MSV
KCC/KCCCHPL/FY2022- 3-May- 25-Aug-
5 GGBS Jindal South West (JSW) GGBS ARMENGE/HO/CHI- APPROVED
23/055 22 22
THA/2022/75
MSV
KCC/KCCCHPL/FY2022- 18-Aug-
6 Cebex Fosrok Chemical India Pvt Ltd - ARMENGE/HO/CHI- 5-Sep-22 APPROVED
23/111 22
THA/2022/95
MSV
KCC/KCCCHPL/FY2022- 18-Apr-
Radha TMT FE-500D 8-Apr-22 ARMENGE/HO/CHI- APPROVED
23/45 22
THA/2022/09
MSV
Real ispat & power ltd (GK KCC/KCCCHPL/FY2022- 22-Apr-
7 STEEL FE-500D 8-Apr-22 ARMENGE/HO/CHI- APPROVED
TMT) 23/45 22
THA/2022/55
MSV
Pushpit Steels Pvt. Ltd. (Brand KCC/KCCCHPL/FY2022- 19-Aug- 24-Aug-
FE-500D ARMENGE/HO/CHI- APPROVED
Name-Pulkit TMT Bars) 23/115 22 22
THA/2022/70
MSV
KCC/KCCCHPL/FY2022-
JSW Steel Limitd FE-500D 2-Sep-22 ARMENGE/HO/CHI- 3-Sep-22 APPROVED
23/128
THA/2022/90
MSV
Syam Metalics & Energy KCC/KCCCHPL/FY2022- 23-Feb- 23-Mar-
FE-500D ARMENGE/HO/CHI- APPROVED
Limited 23/339 23 23
THA/2022/196
MSV
KCC/KCCCHPL/FY2022- 3-May- 21-May-
Syam Steel FE-500D,550D ARMENGE/IE/KCCCHPL/20 APPROVED
23/052 22 22
22/21
KCC/KCCCHPL/FY2022- 9-May- MSV ARMENGE/HO/CHI- 23-Apr-
Agrawal Foundries Pvt Ltd FE-500D APPROVED
23/058 22 THA/2022/15 22
MSV
Prakash Ferrous Industries ( PFI KCC/KCCCHPL/FY2022- 21-Dec-
FE-500D ARMENGE/HO/CHI- 4-Jan-23 APPROVED
Tirumala) 23/231 22
THA/2022/146
MSV
Suprem Bituchem India Pvt. KCC/KCCCHPL/FY2022- 30-Mar- 20-Apr-
- ARMENGE/HO/CHI- APPROVED
Ltd 23/390 23 23
THA/2022/236
KCC/KCCCHPL/FY2022- 30-Mar- MSV ARMENGE/HO/CHI- 20-Apr-
Tiki Tar & Shell India Pv. Ltd. - APPROVED
23/390 23 THA/2022/236 23
KCC/KCCCHPL/FY2022- 30-Mar- MSV ARMENGE/HO/CHI- 20-Apr-
Hindcol - APPROVED
23/390 23 THA/2022/236 23
8 Emulsion
Bitumen Corporation (India) KCC/KCCCHPL/FY2022- 30-Mar- MSV ARMENGE/HO/CHI- 20-Apr-
- APPROVED
Pvt. Ltd. (Bitcol) 23/390 23 THA/2022/235 23
KCC/KCCCHPL/FY2022- 10-Apr- MSV ARMENGE/HO/CHI- 20-Apr-
IWL India Ltd. - APPROVED
23/402 23 THA/2022/236 23
KCC/KCCCHPL/FY2022- 10-Apr- MSV ARMENGE/HO/CHI- 20-Apr-
OOMS Polymers - APPROVED
23/402 23 THA/2022/236 23
Bitumen Corporation (India) KCC/KCCCHPL/FY2022- 30-Mar- MSV ARMENGE/HO/CHI- 20-Apr-
APPROVED
Pvt. Ltd. (Bitcol) 23/389 23 THA/2022/235 23
MSV
Bharat Petroleum Corporation KCC/KCCCHPL/FY2022- 30-Mar- 21-Apr-
ARMENGE/HO/CHI- APPROVED
Limited(BPCL) 23/389 23 23
THA/2022/239
9 Bitumen VG-40 MSV
KCC/KCCCHPL/FY2022- 30-Mar- 21-Apr-
IOCL ARMENGE/HO/CHI- APPROVED
23/389 23 23
THA/2022/239
MSV
Hindustan Petroleum KCC/KCCCHPL/FY2022- 30-Mar- 21-Apr-
ARMENGE/HO/CHI- APPROVED
Corporation Limited(HPCL) 23/389 23 23
THA/2022/239
MSV
United Futuristic Trade Implex KCC/KCCCHPL/FY2022- 30-Mar- 21-Apr-
ARMENGE/HO/CHI- APPROVED
Pvt. Ltd. 23/389 23 23
THA/2022/239
KCC/KCCCHPL/FY2022- 18-Aug- MSV ARMENGE/HO/CHI-
Petrochem Specialties WETBOND-S 3-Feb-23 APPROVED
Anti stripping 23/109 22 THA/2022/163
10
agent. KCC/KCCCHPL/FY2022- 18-Apr- MSV ARMENGE/HO/CHI- 3-May-
Zydex Industries Pvt. Ltd. Zycotherm APPROVED
23/417 23 THA/2022/261 23
MSV
KCC/KCCCHPL/FY2022-
11 Hume Pipe Vishnu Spun Pipes - 25-Jul-22 ARMENGE/HO/CHI- 8-Sep-22 APPROVED
23/088
THA/2022/96
MSV
KCC/KCCCHPL/FY2022- 18-Aug-
DP Wire LTD - ARMENGE/HO/CHI- 9-Sep-22 APPROVED
23/112 22
THA/2022/100
MSV
KCC/KCCCHPL/FY2022- 18-Aug-
Usha Martin Limited - ARMENGE/HO/CHI- 9-Sep-22 APPROVED
23/112 22
THA/2022/99
MSV
KCC/KCCCHPL/FY2022- 18-Aug-
13 HT Strands Dynamic Prestress(I)Pvt.Ltd. - ARMENGE/HO/CHI- 9-Sep-22 APPROVED
23/112 22
THA/2022/99
MSV
KCC/KCCCHPL/FY2023- 22-Aug- 18-Dec-
Kataria HT Strands - ARMENGE/HO/CHI- APPROVED
24/593 23 23
THA/2023/473
MSV
KCC/KCCCHPL/FY2023- 11-Nov- 16-Dec-
TATA Steel Limited - ARMENGE/IE/NHAI/CHI- APPROVED
24/726 23 23
THA/2023/466
MSV
KCC/KCCCHPL/FY2022- 15-Feb-
Geo source - 5-Nov-22 ARMENGE/HO/CHI- APPROVED
23/194 23
THA/2022/173
MSV
Techfab (India) Industries KCC/KCCCHPL/FY2022- 15-Feb-
- 5-Nov-22 ARMENGE/HO/CHI- APPROVED
Limited 23/194 23
Geo Synthetic THA/2022/173
14
Material MSV
KCC/KCCCHPL/FY2022- 28-Jan- 15-Feb-
Virendra Textiles - ARMENGE/HO/CHI- APPROVED
23/294 23 23
THA/2022/172
MSV
KCC/KCCCHPL/FY2022- 28-Jan- 15-Feb-
Maruti Rub Plast Pvt. Ltd. - ARMENGE/HO/CHI- APPROVED
23/294 23 23
THA/2022/172
MSV
Deevin Seismic Systems Pvt. KCC/KCCCHPL/FY2023-
- 12-Jul-23 ARMENGE/HO/CHI- 6-Sep-23 APPROVED
Ltd. 24/524
Elastomeric THA/2022/370
15
bearings MSV
KCC/KCCCHPL/FY2022- 31-May-
Kanta Rubber Pvt Ltd - ARMENGE/HO/CHI- 6-Jun-23 APPROVED
23/477 23
THA/2023/290
Monthly Progress Report February-2024
173
Development of Six Lane Chittoor – Thatchur Highway from Km.0.000 (Varadhrajulu) to Km.43.800 (Kumarajpet) on HAM Mode Under Bharatmala
pariyojna in the state of Andhra Pradesh and Tamilnadu (Package-1)
Extended
Bank Guarantee Date of Validity up
Sl no BG Amount BG Issued by validity up Remarks
No Issue to
to
1 IBG120632 Rs. 2,93,00,000 Federal bank 07.12.21 06.06.23 06.09.23 Handed over the
bank Guarantee
2 16090100016297 Rs. 6,00,00,000 Axis Bank 07.12.21 06.06.23 06.09.23
against
Rs. HDFC Bank 07.12.21 06.06.23 06.09.23 Performance
3 191GT02213410005
12,00,00,000 Security as per
the Provisions of
Rs. Yes Bank 07.12.21 06.06.23 06.09.23
4 A25BG01213410001 Clause 9.3 of
22,00,00,000
CA
Rs. - - - -
Total Amount
42,93,00,000
IE-276
Issuance of NCR-05(big boulders are found
MSV ARMENGE/IE/HO/CHI-
5 15.03.2023 IE KCC in Embankment 20th layer at Km17+400
THA/2022/187
TO 17+650)
NCR-06(big boulders are found in
MSV ARMENGE/IE/HO/CHI- Embankment 2nd layer from Km 07+400
6 26.04.2023 IE kcc KCC-461
THA/2022/248 to 07+450 LHS, and Embankment 9th layer
from 08+000 to 08+150 BHS, )
NCR-07(big boulders are found in
MSV ARMENGE/IE/HO/CHI- Subgrade 1st layer from Km 08+250 to
7 26.04.2023 IE kcc KCC-462
THA/2022/249 08+500 BHS, and Subgrade 1st layer from
08+600 to 08+670 BHS)
NCR-08(Major Elevated Structure at Km
MSV ARMENGE/IE/HO/CHI- KCC-
8 29.04.2023 IE kcc 21+510 A2 LHS Retaining wall 1st lift
THA/2022/252 459A
reinforcement )
Issunace of NCR-09-Reg.(rectification of
MSV ARMENGE/IE/HO/CHI-
9 01.05.2023 IE kcc CTB Top Surface locations at 25+320 to KCC-462
THA/2022/254
25+810 RHS & 26+310 to 27+150 RHS )
IE-375
36+545 to 36+740 LHS and 36+545 to
10 25.05.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 36+650 RHS and location 30+740 LHS RE KCC-495
THA/2023/280 wall damaged panels incorporated in the
works)
Issuance od NCR-11-Reg shoulders layer is
filling with soil material at given location
km36+800 to 37+900 BHS and Km 35+320
11 13.06.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC Pending
THA/2023/292
to 36+080 BHS. Km 25+330 to 25+785 BHS
.Km 26+350 to 27+000 LHS. And 35+320 to
35+940 LHS.
big boulders are found in Embankment
layer from Km 25+900 to 26+000 LHS and
12 13.06.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 25+000 LHS which is not allowed as per KCC-597
THA/2023/293 MoRT&H Specifications clause no
305.2.1.4.
VUP@ km 34+130 RHS WALL 1ST LIFT NOT
IN PROPER ALIGNMENT
13 13.06.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC VUP@ km 34+130 ABUTMENT a2 SIDE KCC-584
THA/2023/294 MEDIAN WALL 1ST LIFT BULGED AND
IE-375
PLUMBED OUT
MNB @ 36+378 A2 RHS abutment and
14 13.06.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC return wall final lift corner portion has not KCC-583
THA/2023/295 properly finished MS sheets not removed
BOX culvert at 18+755 A & A2 LHS Wall
15 03.07.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 2nd lift bottom portion bulging outside KCC-598
THA/2023/307 observed and honeycomb also observed
Box culvert at 14+407 A1 LHS parpet Wall
top portion bulging outside observed and
16 03.07.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC KCC-616
THA/2023/308
parpet Wall bottom portion and edges
finsihing also not as per drawing
RE panel errection work is in progress at
17 26.07.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC KCC-599
THA/2023/336
different locations
IE-432
Km: 0+550 to 0+780 the AIL material
20 03.11.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC contains more moisture rather than 722
THA/2023/426 optimum moisture content.
@ Km: 22+850 to 23+080 on RHS laying of
21 04.11.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC CTB has been done on 04.11.2023 without 857 602
THA/2023/427 raising of the RFI.
Km: 12+750 to 12+780 RE Wall portion
embankment layer is filling with oversize
22 06.11.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC boulders also noticed thickness of layer 721
IE-432
THA/2023/430 more than 500 mm which is to be 200 mm
as per specifications of MoRTH.
@ Km: 15+600 to 15+700 VUP backfilling
is carried out with oversize boulders, black
23 06.11.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 723
THA/2023/431
cotton soil, lumps also noticed vegetation
on the filled embankment layers.
11+290 to 11+400 BHS Subgrade layers is
24 25.11.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC Pending
THA/2023/443
filled with full of boulders
25 22.12.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 14+670 MJB A1 LHS return wall 3rd lift top 906 616
THA/2023/483
26 Empty NO
observed at ch:30+810 LHS A2 Side, Km
30+900 A2 side approach of (30+575
27 22.12.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC Pending
THA/2023/486
LVUP). The damage of erected friction slab
crash barrier has been noticed
10+135 MNB A2 RHS Abutment return
28 22.12.2023 MSVARMENGE/IE/NHAI/CHI- IE KCC 907 616
THA/2023/488
wall top lift bottom
Abstract:
S.no NCR -Issued till 29/02/2024 NCR Closed till 29/02/2024 Balance
Pulkit TMT Steel sampling at steel yard for Physical and chemical test at Thirdy-Party
AIL Ch: 31+870 to 32+000 BHS Gradation testing being witnessed by IE Representative
DBM Top laying in progress at Km 24+730 to 24+800 LHS & 24+900 to 24+950 LHS
DBM Top laying in progress at Km 33+190 to 33+330 LHS & 33+190 TO 33+360 RHS