WEEKLY DOWNTOWN LANE/SIDEWALK/STREET CLOSURE REPORT

Downtown Construction Projects - Lane/Sidewalk/Street Closures


AUTHORIZED
ID # PERMIT PROJECT DESCRIPTION STREET FROM TO START DATE FINISH DATE DESCRIPTION / REMARKS
CLOSURE TIME

PUBLIC PROJECTS - LONG TERM

1 Cap Imp ZONA CULTURAL - Commerce Street (Frio to Santa Rosa St) Commerce Santa Rosa Frio 01/25/22 12/31/24 24-hrs Alternating lane closures on Commerce St for the project duration.

The entire street will be reconstructed. A single through lane will remain open to traffic, throughout, between
Commerce and Martin. San Saba is closed between Dolorosa and Nueva from May 2023 until September 2024,
ZONA CULTURAL - San Saba St (Nueva St to Martin St.) San Saba Nueva Martin 01/25/22 12/31/24 24-hrs
San Saba between Dolorosa and Commerce will be closed from May 2023 until May 2024 to perform utility and
road reconstruction work..

ZONA CULTURAL - Santa Rosa Street (Cesar E. Chavez to Martin St) Santa Rosa Martin Cesar Chavez 02/08/22 12/31/24 24-hrs The entire street will be reconstructed. Alternating and full street closures will occur throughout.

2 Cap Imp Broadway Street Broadway Travis IH 37 Overpass 07/20/21 06/30/24 24-hrs This week thru March 2024, the Mccullough St., 3rd St., and Pecan St. intersections will be closed.

Alamo
Crockett Houston
Crockett
3 ROW Alamo Plaza Renovation Project E. Alamo Plz East of Bonham 06/01/20 Permanent Permanent
E. Alamo Plaza;
Total Closure Total Closure
Blum

Proposed redesign of west curb of Flores approaching Cesar Chavez Intersection. The west curb lane of Flores is
4 ROW Flores at Cesar Chavez Traffic Signal Flores Cesar Chavez Old Guilbeau 03/30/21 TBD 24-hrs
closed with concrete barrier.

The entire street will be reconstructed on Alamo requiring various lane closures.
5 Cap IMP South Alamo St (E. Market St. to E. Cesar E. Chavez Blvd.) Alamo Market Cesar Chavez 12/5/2022 3/12/2025 24-hrs

Created By Public Works 3/11/24 Page 1 of 3


PRIVATE PROJECTS - LONG TERM

A mixed-use development that will provide new residential housing and commercial space, blending the historic
6 DSD/ROW Continental S. Laredo St. Dolorosa St. W. Commerce St. Sept. 2023 Sept. 2025 24-hrs buildings on the site with added density in the middle of the block. The parking lane and sidewalk is currently
closed from Laredo St to their east property line.

A mixed-use development that will provide new residential housing and commercial space, blending the historic
7 DSD/ROW Arana Buildings Commerce Laredo St Property line Sept. 2023 03/21/24 24-hrs buildings on the site. This project is anticipated to be complete in September 2025.
Sidewalk closure currently in place thru March.

Dolorosa Laredo St Property line Sept. 2024 07/15/24 24-hrs Sidewalk & parking lane closure currently in place.

UTSA is constructing a new 8 floor building on Dolorosa, between Laredo St. and the river. The bus lane is
8 DSD/ROW UTSA Building Dolorosa Santa Rosa River Bridge 11/20/23 03/31/24 24-hrs currently closed and being used as the ped path until April 2024.. This project is scheduled to be complete in
September 2026.

Mon-Sat New high-rise apartment complex. This project is located between the Witte building and Canopy Hotel on
9 DSD/ROW Floodgate Apartments Commerce Soledad St. Mary's 01/06/20 03/31/24
6am to 6pm Commerce St. Daily lane closure from 6am to 6pm, Mon thru Sat. Full sidewalk closure.

A new retail and residential complex. The east lane of Main, the south lane of Pecan, the north lane on Travis, and
10 DSD/ROW 300 N. Main Main Travis Pecan 03/01/22 06/09/24 24-hrs west lane of Soledad closed for the duration of the project, June 2024. Pedestrian access to the local businesses
will remain open.

Pecan Main Soledad 03/01/22 06/09/24 24-hrs

Travis Main Soledad 03/01/22 06/09/24 24-hrs

Soledad Travis Pecan 08/20/22 06/09/24 24-hrs

11 DSD/ROW Intercontinental Hotel Renovation Martin Soledad The Bridge 10/08/22 07/15/24 24-hrs This hotel is in the city block surrounded by Pecan, Soledad, and Martin.

Pecan St Soledad The Bridge 04/29/24 05/17/24 24-hrs Lane closure for a crane and roof reconstruction.

12 DSD/ROW La Villita Kimpton Hotel Alamo Arcienage Nueva 10/10/22 05/31/24 24-hrs This hotels is in the City block surrounded by Arceinaga St and Alamo St.

13 ROW MCI Fiber Camaron St Houston Travis 02/12/24 03/15/24 7am to 5pm Sidewalk closure on the East side of Camaron.

Travis Camaron Soledad 319/24 05/02/24 9pm thru 5am Sidewalk closure on the South side of Travis St.

Phase I - daily parking lane closure (2/12/24 - 4/17/24)


14 DSD/ROW Aztec Hotel Commerce St. Mary's 120' past property line 02/12/24 03/31/25 24-hrs
Phase II - sidewalk, parking lane and travel lane closure 4/29/24 - 3/31/25)

Created By Public Works 3/11/24 Page 2 of 3


SHORT TERM - PUBLIC/PRIVATE PROJECTS 24-hrs

15 DSD/ROW 175 E. Houston Houston St. St. Mary's The River 04/24/24 04/28/24 9pm - 5am Full street closure - thru traffic to local business will be allowed.
Tower of the
16 ROW Fiber Repair Market Montana 02/14/24 03/22/24 Daily Single lane closure
Americas Way
17 DSD/ROW Gunter Hotel St. Mary's St. Houston Travis 02/12/24 3/292024 9am-3pm Single lane and sidewalk closure

Upcoming Long Term Construction Projects (Dates to be Determined)

AUTHORIZED
ID # PERMIT PROJECT DESCRIPTION STREET FROM TO START DATE FINISH DATE DESCRIPTION / REMARKS
CLOSURE TIME

On Villita St, the two westbound lanes (i.e., one (1) parking lane and one(1) travel lane) will be closed for
approximately 15 months to complete this project. The sidewalk will be closed on Navarro St. in front of the
building. The contractor plans to start renovation of the old CPS Building located at Navarro and Villita St in June
18 DSD/ROW AB Frank Building Villita St S. St. Mary's Navarro St. 06/01/24 10/01/25 24-hrs of 2024. For the project duration, they will close the WB sidewalk and parking lane on Villita St. along their
property line. The WB travel lane on Villita St. may also need to be closed for safety reasons due to poor turning
radius. However, this WB lane closure is still being reviewed/discussed. This project is anticipated to take 15
months

Villita Street, all lanes closed from corner of St Mary's to entrance of parking garage along Villita from July 2024
until April 2026.
19 DSD/ROW Tower of Life Building Villita St S. St. Mary's Navarro St. 07/01/24 4/31/26 24-hrs
St Mary's St. to have re-occurring single lane road closure throughout project.

Event Street Closures


AUTHORIZED
ID # PERMIT EVENT DESCRIPTION STREET FROM TO START DATE FINISH DATE DESCRIPTION / REMARKS
CLOSURE TIME

Guadalupe S. San Jacinto St. S. Flores St. Street Closures Begin at 7:00 AM
20 SAPD 2024 Cesar Chavez March S. Flores Guadalupe Cesar E. Chavez 03/23/24 03/23/24 7:00am to 2:00pm March kicks off at 10:00 AM (route closes at 9:15 AM)
Cesar E. Chavez S. Flores Hemisfair Blvd. Streets Open on Rolling Basis (all open by 2:00 PM)

Created By Public Works 3/11/24 Page 3 of 3