Professional Documents
Culture Documents
Bsibv-Itp-07-2 Pe Itp For 3lpe Coating Dpe Rev. 0
Bsibv-Itp-07-2 Pe Itp For 3lpe Coating Dpe Rev. 0
Bsibv-Itp-07-2 Pe Itp For 3lpe Coating Dpe Rev. 0
echnip.co
m
2018.10.0
8 17:57:29
+04'00'
Site Project Quality Document
INSPECTION AND TEST PLAN - 3LPE COATING
BREDERO SHAW INTERNATIONAL B.V, RAK
Customer Project PO Number
TechnipFMC AQAM Development EPCI 077607C004-230-PO-5530-012-7010
C: Record & Raise Documents H: Hold Point N: Non-Destructive Testing V: Visual 1: 100%
Legend D: Dimensional Inspection I: Random Inspection R/A: Review/APPROVAL W: Witness 2: 10%
E: Examine/Endorse Documents M: Monitor T: Destructive Testing WFO: Witness First Off S: Surveillance
Approval Inspection
BSIBV-
DP-PL-4 Production Test
No. Activity Description QP-07-2 Method / Acceptance Criteria Verifying doc
Rev. 01 Frequency BSIBV TP FMC DPE / TPI
(PP)
1 Raw Material certificates 2.1 / 4.1 Manufacturer test certificate shall be submitted to the Customer. RF 033 Every Batch H R R
a Moisture Content
b Gel Time
c DSC- Thermal Analysis of Powder
Laboratory testing of FBE
4.2 / d Density RF 013E / RF
2 powder (Valspar Pipeclad 5.0 Every Batch H W1 R
Table 1 033
2000) e Sieve Analysis
The acceptance criteria and test method shall be in accordance with
Material manufacturer’s Certificate of Analysis (CoA) for the
laboratory tests.
a Melt Flow Index
Laboratory testing of b Density
4.3 / RF 013F / RF
3 adhesive material (Borealis - 5.0 Every Batch H W1 R
Table 2 The acceptance criteria shall be in accordance Material 033
Borcoat ME0433)
manufacturer’s Certificate of Analysis (CoA) for the laboratory tests.
Certificate
The criteria shall be less than 100-ppm sulphates and chlorides and from
5 Abrasive Material 2.1 100 ppm chlorides. The material manufacture’s certificate shall be Manufacturer Every Batch H W1 R
submitted. / RF 033 / QF
01-3
Verify pipe's identification number in accordance with packing list or
6 Verify pipe identity 2.3 TF-001 All Pipes H W1 R
tally sheet.
Removal of End Caps or The end caps and bevel protectors shall be removed from each end
7 5.1.1 - All Pipes H M R
Bevel Protector of pipes.
Verify pipes are free from major mechanical damages, oil, grease
and surface contamination. Check pipe identification. If oil grease QF-001 /
8 Visual Inspection of Pipes 5.1.1 2.3 contamination observed on pipe will be cleaned in accordance with GloQ-410 / All Pipes H W1 R
SSPC SP-1 Solvent Cleaning. Defective pipes shall be removed RF 002
from the coating line for resolution of defects.
The pipe shall be externally hot water washed prior to Blast cleaning
and each pipe evenly pre-heated to a minimum of 40°C but in no All Pipes, Record in
9 Hot water wash 5.1.1 2.4 QF-001 H V R
case above 180°C, to ensure the steel surface is free from every 30 minutes
moisture.
Abrasive Material No oil/water in accordance with ASTM 4940. The abrasive material QF 07-1 / QF
10 3.1 Once per Shift H W1 R
Contamination Test shall be dry, clean, and free from contamination. 01-3
Check Pipe Temperature,
Steel temperature shall be simultaneously higher than 5°C and Start of Shift / Every 2
11 Relative Humidity and Dew 5.1.1 2.7 / 3.1 QF 07-2b H W1 R
more than 3°C above dew point. Hours
point
The end plugs (Sponges) shall be installed inside both ends of the
pipe after hot water bath to prevent the ingress of abrasive material
during the blast cleaning process. Ensure the end plugs shall be
Protection of pipes during capable to protect the hard stamp (pipe identity punched on bevel)
2.4.1 /
12 Abrasive Blasting and from blasting. - All Pipes H M R
2.6
Coating.
After abrasive blasting, the coupling shall be installed into one end
of the pipe, ensuring that it is free of abrasive particles, clean and
free of oils and lubricants. Open couplings shall be used.
13 Compressed Air Supply 2.5 / 3.1 No trace of oil or water in accordance with ASTM D 4285-83. QF 021 Twice per Shift H W1 R
Cleaning of Blast Cleaned Using clean dry compressed air an operator shall blow out residue
14 2.5 - All Pipes H M R
Pipe Internal Surface which has accumulated on the internal surface.
Abrasive Blast Cleaned Pipe 5.1.2 / Pipe surfaces shall be cleaned to a degree corresponding as a
15 2.5 / 3.1 QF 07-1 All Pipes H W1 R
Surface Visual Standard 8.3.1 minimum to Sa 2 1/2 in accordance with ISO 8501-1.
If the defect or repair size greater than 10 cm² of the pipe surface
area shall be reblasted. And also the pipe shall be reblasted if any
Surface Preparation QF 07-1 /
18 5.1.2 3.1 pipe does not achieve the following requirements, If required H W1 R
Rejection QF 07-2b
- Visual Standard,
- Surface Profile.
Following abrasive blast cleaning, the pipe surface shall be pre- • All production pipes
treated 100% coverage with Phosphoric Acid. Acid Contact time shall be acid treated.
shall be minimum 20 Seconds at a pipe temperature of 43-65°C.
For every °C below 43°C the acid contact time shall be increased by • Acid contact time and
QF 023 / QF temperature shall be
22 Phosphoric Acid Treatment 2.7 / 3.2 1 second. H W1 R
01-3 recorded for first 3 pipes
The pH of acid shall be ≤ 1. The pH of Phosphoric acid shall be and in every 1 hour.
checked in the laboratory at once per hour. The test shall be • pH of acid shall be
recorded on report form QF 01-3. checked once per hour.
The acid treated pipe shall be passing through high-pressure All production pipes
(Minimum 1200 psi) fresh water wash rinse prior to pipe preheating. shall be water washed /
QF 023 / QF pH and conductivity of
23 Water Wash 2.7 / 3.2 H W1 R
The conductivity of water used for water wash shall be less than 30 01-3 water shall be checked
µS. The pH of Water shall be >6 to <8. The pH of water shall be Once per shift from the
checked in the laboratory at once per shift. laboratory
24 Pipe Drying 2.7 Maximum drying effect by use of clean dry compressed air. N/A All Pipes H M R
Minimum thickness of
Smooth even coating. The thickness shall be minimum 150 Every day at the
30 Adhesive layer partially 5.2.2 3.5 / 3.8 QF 07-3 H W1 R
microns and maximum 250 microns. beginning of the shift
coated pipe section
Rough coat Application Additional ‘coat’ shall be spray applied to produce a rough coating
All Pipes (Concrete
32 (Borealis Borcoat HE 7405 - 5.2.4 2.11.1 surface and to improve anti-slip properties on the pipe used for - H M R
coating pipes)
Sinter Coat) concrete coating.
The cut back shall be 130 +20/-0 mm both pipe ends, bevel angle
(chamfer) shall be ≤30°. The FBE Toe shall be15 mm (-
5mm/+15mm).
7.3 / QF 07-3 /
35 Cut Back 2.14 / 3.8 All Pipes (Both ends) H W1 R
8.4.3 QF 01-3
Note: Any damage on the FBE toe without exposing steel and/ or
adhesive residue on the FBE toe shall be accepted as it is, no repair
required.
7.5 /
The Shore D Hardness Test shall be performed in accordance with
45 Shore D Hardness Table 6 / 3.8 QF 07-6 Once per shift H W1 R
ISO 868. The acceptable value shall be ≥ 55.
8.5.4
The defect area shall not exceed 100 cm² and the total number of
defects being repaired shall not exceed three (3) defecta per pipe
joint unless otherwise specified. The above repair criteria is not QF 07-3 /QF
46 Repairs 6.2 2.16 If required H W1 R
applicable for handling damages and repair of test pipes. If the 07-9
damaged areas requiring repair on any single pipe exceed above
values, the pipe shall be stripped and re-coated.
Note: The stencil marking may burnished / rubbed off while transporting or
handling the coating pipe, the coater shall not be responsible for such issues. The
appropriate identification number shall be marked on the internal surface of the
pipe.
Partial / complete release After completion of all the production tests, Inspection release notes
for load-out of coated pipes shall be submitted to BSIBV from Customer Representative, when
50 3.8 QF 032 Accepted pipes H H H
/ Issue of Inspection all QC documents are approved. Partial / complete release shall be
Release Note issued for load-out of coated pipes.
Final documentation shall be submitted to Client/TPI, by BSIBV
51 Final documentation 3.8 once entire documentations are completed. Th final documentation MRB All coated pipes H H R
shall be prepared in accordance with approved MRB Index.