RESIDENTIAL MEASUREMENT OF SIX STOREY RESIDENTIAL BUILDING

DESCRIPTION OF ITEM LOCATION NOS Length BREADTH HIGHT QUANTITY TOTAL QTY
Earth Work in foundation
F1 1 8.00 8.00 8.00 512.00 CFT
F2 2 8.00 7.00 8.00 896.00 CFT
F3 2 6.33 6.33 8.00 641.10 CFT
F4 2 6.00 6.00 8.00 576.00 CFT
UGWR 1 21.00 13.33 8.00 2239.44 CFT
G BEAM 1 155.49 1.00 1.50 233.24 CFT
Boundary Wall 18 4.00 4.00 2.00 576.00 CFT
TOTAL= 5673.78 CFT

DESCRIPTION OF ITEM LOCATION NOS Length BREADTH HIGHT QUANTITY TOTAL QTY
SAND FILLING WORK
IN FLOOR 1 48 32 2 3072.00
Foundation 1985.82
Total 5057.82 cft

One Layer Brick Flat LOCATION NOS LENGTH BREADTH QUANTITY TOTAL QTY
F1 1 8.00 8.00 1.00 64.00
F2 2 8.00 7.00 1.00 112.00
F3 2 6.33 6.33 1.00 80.14
F4 2 6.00 6.00 1.00 72.00
UGWR 1 21.00 13.33 1.00 279.93
G BEAM 1 155.49 1.00 1.00 155.49
Boundary Wall 18 4.00 4.00 1.00 288.00
FLOOR 1 35 27 1.00 945.00

TOTAL= 1996.56 SFT

Cement Concrete Work LOCATION NOS LENGTH BREADTH HIGHT QUANTITY TOTAL QTY
(1:3:6) F1 1 8.00 8.00 0.25 16.00
F2 2 8.00 7.00 0.25 28.00
F3 2 6.33 6.33 0.25 20.03
F4 2 6.00 6.00 0.25 18.00
UGWR 1 21.00 13.33 0.25 69.98
FLOOR 1 35 27 0.25 236.25
TOTAL= 388.27 CFT
R.C.C WORK for
FOUNDATION UP TO PL
LOCATION NOS LENGTH BREADTH HIGHT QUANTITY TOTAL QTY
F1 1 8.00 8.00 1.42 90.88
F2 2 8.00 7.00 1.42 159.04
F3 2 6.33 6.33 1.25 100.17
F4 2 6.00 6.00 1.17 84.24
UGWR 1 21.00 13.33 2.00 559.86
WALL 1 39.5 9 0.83 295.07
G BEAM 1 155.50 1 1.5 233.25
C1 1 1.83 1.42 7.5 19.49
C2 2 1.83 1.17 7.5 32.12 CFT
C3 3 1.42 1.17 7.5 37.38 CFT
C2A 4 1.83 1.17 7.5 64.23 CFT
C3A 1 1.42 1.17 7.5 12.46 CFT
15.00
TOTAL= 1703.19 CFT
cft

R.C.C WORK IN COLUMN


BEAM , UP TO G.F. SLAB LOCATION NOS LENGTH BREADTH HEIGHT QUANTITY TOTAL QTY
C1 1 1.67 1.25 9.5 19.83
C2 2 1.67 1 9.5 31.73 CFT
C3 3 1.25 1 9.5 35.63 CFT
C2A 4 1.67 1 9.5 63.46 CFT
C3A 1 1.25 1 9.5 11.88 CFT
BEAM 1 157.33 1 1.5 236.00
SLAB 1 30.12 47 0.42 594.57
STAIR 2 9 4 0.83 59.76 CFT
1 3.5 8.17 0.5 14.30 CFT
1 4.5 8.17 0.5 18.38 CFT
2 9.25 4 0.5 37.00 CFT
False cilling 2 9.42 6 0.33 37.30 CFT
LINTEL 110 1 0.5 0.42 23.10 CFT
1 6 7 0.25 18.90 CFT
1201.83 CFT

M.S. ROD FEBRICATION


WORK.

FOOTING
20mm dia C1 1 1 12 12 144.00
C2 2 1 10 12 240.00
C3 3 1 8 12 288.00
C3A 1 1 10 12 120.00
gb 180 2 1 1 360.00
1152.00 0.75 kg/ft
864 kgs

16 mm dia F1 1 7.50 24.00 2 360.00


F2 2 7.50 24.00 2 720.00
F3 2 5.83 15.00 2 349.80
F4 2 5.50 13.00 2 286.00
UGWR 2 12.83 63.00 1 1616.58
2 20.5 40 1 1640.00
C2A 4 4 9 1 144.00
beam 213 5 1 1 1065.00
6181.38 0.48 kg/ft
2967.06 kgs

12mm dia f1 26 7.5 1 1 195.00


f2a 30 8 1 1 240.00
f2b 19 6 1 1 114.00
11 10 1 1 110.00
36 6 1 1 216.00
875.00 0.27 kg/ft
236.25 kgs

10 mm dia RING 22 5.00 19 1 2090.00


356 4.25 1 1 1513.00
186 11.00 1 1 2046.00
57 17.00 2 1 1938.00
40 21.00 1 1 840.00
90 11.00 1 1 990.00
9417.00 0.18 kg/ft
1695.06 kgs
IN GROUNG FLOOR

FOR COLUMN UP TO
PLINTH LEVEL

20 mm dia BEAM 213 5 1 1 1065.00


5 38 1 1 190.00
col 100 13.5 1 1 1350.00

2605.00 0.75 kg/ft


1953.75 kgs

16 mm dia 213 2 1 1 426.00


20 10 1 1 200.00
8 13.5 1 1 108.00
734.00 0.48 kg/ft
352.32 kgs

10 mm dia Ring Column 11 4.6 33 1 1669.80


350 4.60 1 1 1610.00
225 5.00 1 1 1125.00
Slab 33 19.17 2 1 1265.22
25 46.25 1 1 1156.25
43 29 2 1 2494.00
22 16 1 1 352.00
265 9 1 1 2385.00
20 6 1 1 120.00
26 6 1 1 156.00
12333.27 0.18 kg/ft
2219.99 kgs

12 MM DIA 18 15.33 1 1 275.94 0.27 kg/ft


74.50 kgs

M.S. ROD FEBRICATION 20mm dia 2817.75 Kgs


up to G.Floor 16 mm dia 3319.38 Kgs
10 mm dia 3915.05 Kgs
12 mm dia 310.75 Kgs
Total 10362.9348 Kgs

5" BRICK WORK IN GF :


ground floor 1 160 8 1 1280.00
wall 3 16 9 1 144.00
ground floor 2 22 9 1 198.00
Net Quantity 1622.00 SFT
Plastering Work (OUT SIDE) 1 161.25 60 1 9675.00 SFT

10 5 4.5 1 225.00
DEDUCTION 2 9.58 4.5 1 86.22
2 13.58 4.5 1 122.22
2 10.83 4.5 1 97.47
530.91
NET QUANTITY= 9144.09 SFT

6 62 6 1 2232.00
DRIP COURSE PLASTER 4 210 1 1 840.00
3 55.58 1 1 166.74
10 2 7.5 1 150.00
NET QUANTITY= 3388.74 RFT

1 13.67 15.83 1 216.40


TILES WORK IN FLOOR Ground Floor 1 12 15.83 1 189.96
NET QUANTITY= 406.36 SFT

1 13.67 15.83 1 216.40


TILES WORK IN FLOOR 1st Floor 1 12 15.83 1 189.96
1 16.67 15.42 1 257.05
1 8 16.83 1 134.64
1 16.42 26 1 426.92
1 3 26.25 1 78.75
NET QUANTITY= 1303.72 SFT

NET QUANTITY= 1303.72 SFT


TILES WORK IN FLOOR 2ND FLOOR
NET QUANTITY= 1303.72 SFT
TILES WORK IN FLOOR 3RD FLOOR
NET QUANTITY= 1303.72 SFT
TILES WORK IN FLOOR 4TH FLOOR
NET QUANTITY= 1303.72 SFT
TILES WORK IN FLOOR 5TH FLOOR
NET QUANTITY= 186.85 SFT
TILES WORK IN FLOOR OVER ROOF

1 24.67 7 1 172.69
TILES WORK IN WALL GROUND FLOOR 1 26.33 7 1 184.31
357.00 SFT

2 24.67 7 1 345.38
TILES WORK IN WALL 1ST FLOOR 1 26.33 7 1 184.31
1 13.5 7 1 94.50
1 315 0.5 1 157.50
NET QUANTITY= 1060.50 SFT

NET QUANTITY= 1060.50 SFT


TILES WORK IN WALL 2ND FLOOR
NET QUANTITY= 1060.50 SFT
TILES WORK IN WALL 3RD FLOOR
NET QUANTITY= 1060.50 SFT
TILES WORK IN WALL 4TH FLOOR
NET QUANTITY= 1060.50 SFT
TILES WORK IN WALL 5TH FLOOR
NET QUANTITY= 364.25 SFT
TILES WORK IN WALL OVER ROOF

NET QUANTITY= 6363.00 SFT


WOOD WORK FOR DOOR 6 17.5 0.54 0.25 14.18
CHOWKET 4 16.5 0.54 0.25 8.91
1 17 0.54 0.25 2.30
25.38 CFT

NET QUANTITY= 152.28 CFT

WOOD WORK FOR DOOR 6 2.92 6.83 1 119.66


SHUTTER 4 2.08 6.83 1 56.83
1 2.58 6.83 1 17.62
194.11 SFT
NET QUANTITY= 1164.65 SFT

6 6 36.00 NOS
PLASTIC DOOR

10 5 4.5 1 225.00
ALUMINIUM FABRICATION 2 4 4.5 1 36.00
WORK. 1 5.42 4.5 1 24.39
4 2 2 1 16.00
301.39 SFT
NET QUANTITY= 1808.34 SFT

10 5 4.5 1 225.00
WINDOW GRILL 6 3 4.5 1 81.00
306.00 SFT
NET QUANTITY= 1836.00 SFT

2 15.58 4.5 1 140.22


VERANDAH GRILL 2 5 4.5 1 45.00
185.22 SFT
NET QUANTITY= 1111.32 SFT
COST ESTIMATION OF Six STORIED RESIDENTIAL BUILDING

CIVIL WORKS :

SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT


1 Mobilization of man power, materials and equipment,
preparation of site, clearing of all existing debris to a safe
distance, removing the trees, uprooting trees/grass and
cleaning, layout of the building complex, etc. all complete
as per direction of the Engineer. 1 LS 40000 40000.00

2 Earth Work : Earth in excavation in all kinds of soils for


foundation trenches in/c layout, providing centre lines,
bench marks pillars, levelling, ramming and preparing
the base, fixing, bamboo spikes & giving layout with
chalk powder, providing necessary tools and plants,
protecting & maintaining the trench dry etc, stacking
the excavated earth at a safe distance of up to 60m
lead, removing the spoils etc, all complete as per
direction of the Engineer -in-charge.

a. Foundation 5673.78 cft 5 28368.89

3 Flat Solling : One layer of brick flat solling in


foundation or in floor with 1st class or picked jhama brick
in/cl preparation of bed & filling the interstices with local
sand, levelling in/cl the supply of water, electricity & charge
& costs of tools & plants etc, all complete as per direction of
the Engineer -in-charge.

a. Foundation and floor 1997 sft 31 61893.29

4 Sand Filling :Sand filling foundation trenches & plinth


with coarse & having min.F.M 0.80 in 150 mm layers in/cl
levelling, watering & consoidating each layer up to finished
level (to be used when required as per design suppied by
the design office only ) etc, all complete as per direction of
the Engineer -in-charge.

a. Foundation 5057.82 cft 12 60693.87

5 Damp Proof Course : 75 mm brick damp proof course


(1:1.5:3) in cement concrete with cement, sand
(F.M-1.2) pj bricks or stone chips in/cl breaking chips,
screening, cantering shuttering, casting, curing & finished
with a coat of bitumen in/cl the supply of water, electricity &
charge & costs of tools & plants etc, all complete as per
direction of the Engineer -in-charge.

168.00 Sft 35 5880.00

6 Lean Concrete : Mass concrete (1:3:6) in foundation &


floor with cement sand (F.M 1.2) & picked jhama chips
screening ,mixing laying, compacting to level & curing at
least 7days in/cl the supply of water, electricity & charge &
costs of tools & plants etc, all complete as per direction of
the Engineer -in-charge.
388.27 Cft 125 48533.37
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
7 Brick Work : Brick work with 1st class bricks in cement
morter (1:6) in foundation & plinth, filling the joints interstices
fully with morter racking out the joints, cleaning & socking
the bricks at least 24 hours before use & curing at least
7days etc, all complete (F.M 1.2) in/cl cost of water,
electricity & other charges as per direction of the Engineer -
in-charge.

7.1 250 mm thick or more brick work in foundation upto 0 Cft 135 0
plinth level steps at plinth level & wherever specified
area as per drawing with 1:6 morter proportion.

7.2 125 mm thick brick wall above plinth level in all floor
with proportion 1:4
In Floor 1622.00 SFT 70 113540
8 R.C.C Works : Reinforcement cement concrete works
(1:1.5:3) of specified compressive strength fc 21 Mpa at 28
days on standard cylindered with cement conforming to BDS
232 & ASTM standards, best quality sand (50% quantity of
local sand FM 1.2 & 50% quantity of Sylhet sand or coarse
sand of equivalent FM 2.5) & 20 mm down well graded
stone chips on/cl breaking chips & screening, making,
placing in position, making shutter water tight properly,
placing reinforcement in position maxing with mixer machine
, casting in forms, compacting by vibrator machine & at least
for 28 days, removing cantering -shuttering all complete
in/cl cost of water, electricity, testing & other charges as per
direction of the Engineer -in-charge.

8.1 UP TO FOUNDATION ( Concrete only ) 1703 CFT 260 442828.95

10 R.C.C Works : Reinforcement cement concrete works


(1:2:4) of specified compressive strength fc 19 Mpa at 28
days on standard cylindered with cement conforming to BDS
232 & ASTM standards, best quality sand (50% quantity of
local sand FM 1.2 & 50% quantity of Sylhet sand or coarse
sand of equivalent FM 2.5) & 20 mm down well graded
picket jama chips on/cl breaking chips & screening, making,
placing in position, making shutter water tight properly,
placing reinforcement in position maxing with mixer machine
, casting in forms, compacting by vibrator machine & at least
for 28 days, removing cantering -shuttering all complete
in/cl cost of water, electricity, testing & other charges as per
direction of the Engineer -in-charge.

10.1 For . Slab.lintel .drop wall etc 1202 cft 250 300457.06
###
12 Reinfocement work : Suppling fabrication & fixing to
details as per design formed bar reinforcement in
concrete in accordance with BSTI standard in/cl
straightening & cleaning rust, if any bending & binding
in position in/cl supply of G.I wires etc, complete in all
respects in all floors (a) 60 grade deformed ber
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
12.1 upto G.Floor 10363 KG 65 673590.76
13 Plastering Works :

13.1 Minimum 12 mm thick cement sand (F.M-1.2) plaster


(1:6) with Net cement Finishing to
wall both the exterior surface, finishing the coner & edge
in/cl washing of sand cleaning the surface, curing at least
7days scaffolding necessary cost of water, electricity &
other charges etc,complete in all respect as per drawing &
direction of the Engineer -in-charge.
467 Sft 30 14010.00

13.2 Minimum 12 mm thick cement sand (F.M-1.2) plaster


(1:6) with fresh cement ( Conforming to BDS 232 ) to
wall both the interior surface, finishing the coner &
edge in/cl washing of sand cleaning the surface, curing at
least 7days scaffolding necessary cost of water, electricity &
other charges etc,complete in all respect as per drawing &
direction of the Engineer -in-charge.
0 Sft 26 0.00

13.3 Minimum 12 mm thick cement sand (F.M-1.2) plaster


(1:6) with fresh cement ( Conforming to BDS 232 ) to
wall both the exterior surface, finishing the coner &
edge in/cl washing of sand cleaning the surface, curing at
least 7days scaffolding necessary cost of water, electricity &
other charges etc,complete in all respect as per drawing &
direction of the Engineer -in-charge.
0 Sft 32 0.00
14 Supply & Fitting Fixing Ceramics Wall Tiles ( Local Made) on
20 mm thick morter.Size 8"X12"
0 Sft 87 0.00
15 Supply & Fitting Homogenous Floor Tiles ( Local Made-) on
20 mm thick morter. Size up to 12"X12" to 16"X16"
0 Sft 105 0.00
16 Roof top treatment
0 Sft 80 0.00
17 Parking Tiles by Pavers
0 Sft 55 0.00
18 Cartain Roller For Wall by 19 mm dia aluminium pipe
0 rft 35 0.00

19 Wood Work For Door.

19.1 Supply and making door and window frame ( Chowket ) for
l floor with natural seasoned wood of required size including
painting two coat in the surface with fitting fixing complete
Mehgoi / Akas moni / Local Sal
0 CFT 3500 0.00
0
19.2 Supply and making door and window frame ( Chowket ) for
l floor with natural seasoned wood of required size including
painting two coat in the surface with fitting fixing complete
By Ctg Teak

0 cft 6000 0.00

20 Supply and fitting fixing Flash Door Shutter


(Internal Door) by Partex 0 Sft 220 0.00
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
21 Supply and fitting fixing 1.5" thick Solid Door Shutter
(Main Door) by Ctg teak
0 Sft 1200 0.00
22 Painting Works : 0

22.1 Three coat Plastic Painting Work paint of approved quality


and colour
delivered from authorized local agent of the
manufacturer in a sealed container, made from water
based powder mixed with water (1:1), applying 1st coat,
curing the after six hours for 24 hours, second coat applied
& curing the same for 7 days etc, taking care & cleaning the
surface fully from grease, oil substances, old paints, lime
wash, fungus, algae etc, sand papering the surface before
applying 1st & 2nd coat, complete in/cl cost of electricity,
water & other charges as per direction of the Engineer -in-
charge.
0 Sft 12 0.00

22.2 Weather Coat emulsion paint of approved best quality &


colour delivered from authorized local agent of the
manufacturer in a seal container, applying to wall &
ceiling in two coats in over a coat of brand specified
primer or sealer elapsing specified time for drying / recoating
in/cl cleaning, drying , marking, free from dirt , grease, wax,
removing all chalked & scaled materials, fungus, mending
good the surface defects , sand papering the surface &
necessary scaffolding, spreading by brush roller/spray etc,
all complete in all floor as per direction of the Engineer -in-
charge.

0 Sft 11 0.00

22.3 Painting to door & windows frames & shutters in two


coats with approved best quality & colour of synthetic
enamel paint delivered from authorized local agent of the
manufacturer in a sealed container, having highly water
resistant, high bondibility, faxable, using specific brand
thinner applied by brass roller/spray over a coat of priming
elapsing time for drying in/cl surface cleaning from sand
paper & necessary tools, scaffolding, testing charges etc, all
complete in all floor.
0 Sft 12 0.00

22.4 French polish work in door shutter 0 Sft 45 0.00

23 Grill & Railing :


SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
23.1 Stair Railing : Supplying, fitting & fixing 12 mm dia GI
pipe stair railing of any standard height of any design
& shape with 50 mm * 50 mm * 6 mm MS plate at the
base of 12 mm dia GI pipe & fitted & fixed by welding
placing the pipes vertically @ 125 mm c/c (2 nos
in each steps ) 150 mm embeded into the RCC tread of
stair case after cutting grooves & mending good the
damages with CC & providing 38 * 6 mm FI bar on the top of
GI pipe to provide wooden GI pipe hand rail of any design
in/cl polishing painting etc, all complete. With Hand Rail 112
* 62 mm (finished).

0 Sft 230 0.00

23.2 Windows Grill : Supplying, fitting & fixing of window


Grills of any design made with 10 mm thick square bar
in/cl fabrication, welding, cost of electricity workshop
charges, carriage, cutting grooves, mending good the
damages tools & plants etc, complete for all floors as per
direction of the Engineer -in-charge.
0 Sft 160 0.00

23.3 Collapsible Gate : Manufacturing, supplying, fitting &


fixing collapsible gate of any design & shape made of
3/4" * 3/4" * 1/8" channel placed @ 112 mm c/c vertically &
connecting the same with each other by 20 * 3 mm MS flat
bar scissors 525 mm/6 mm long provide in 3 rows in/cl
cutting the different MS members to required sizes,
fabricating, welding, riveting with required size rivets,
providing required size wheels, pulling handles on both
sides, suitable locking arrangement, electrods, grease &
finally placing the same in position in between 2 nos. 50 * 50
* 6 mm MS Tee Rail made by welding 2 nos. 50 * 6 mm MS
flat bar fitting & fixed at top & bottom with RCC lintel / roof
slab, floors & side wall with required nos. 150 to 250 mm
long 38 mm MS flat bar clamps one end welded with the
gate member & the other end bifurcated & embeded in CC
at the respective point in/cl cutting holes & mending good
the damages by pouring concrete (1:2:4) into the holes &
finishing etc, all complete , painting 2 coats with with
approved best quality synthetic enamel paint over a coat of
anti-corrosive painting, both & carriage in/cl greasing,
electrods, curing etc, all complete as per drawing & design &
direction of the Engineer -in-charge. 0 Sft 380 0.00
24 Supply and fitting fixing of Aluminium sliding window as per
standard specification having 1.2 mm thick outer frame
( Size 75.5 * 32 mm ) Local made frame including 5 mm
thick tinted glass and nescessary specification.
0 Sft 340 0.00
25 Work top Making By R.C.C and Tiles 0 Sft 200 0.00

26 Mongaries Set For Door 0 set 1200 0.00

27 Supply and Fitting Of PVC Door ( Pertex ) 0 nos 5500 0.00

28 Providing drip course or Nosing at the edge of sunshade ###


or cornice with cement sand (F.M. 1.2) mortar (1:2) with
fresh cement including scaffolding, curing at least for 7 days,
cos etc. all complete in all respect as per drawing and
accepted by the Engineer. 0 rft 30 0.00
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
29 SuppLY AND Fitting and fixing stainless steel (SS) ###
stair/ramp railing of standard height with 2mm thick 2.5" dia
pipe for hand-rail including polishing work as per drawing
and accepted by the Engineer. 0 Sft 340 0.00

COST SUMMARY FOR CIVIL WORK 1749796.18

INTERNAL & EXTERNAL SANITARY PLUMBING WORK

SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT


1 Supplying, fitting & fixing European type
glazed porcelain commode "S" type 465 × 340 × 415 mm
in size, approximately 14 kg by weight, plastic seat cover &
preparing the base with cement concrete & with wire mesh
or rods, if necessary, in all floors i
Special Coloured 24 set 11000 264000

2 Supplying, fitting & fixing Bangladesh pattern,


570 × 445 × 290 mm long pan with foot-rest approx 12 kg
by weight, made of Vitreous China & preparing the base of
pan with cement-moter (1:4) & with wire mesh or rods if
necessary, in all floors includin
Special Coloured 2 Each 1100 2200
3 Supplying, fitting & fixing plastic
low-down including all fittings & accessories.. 29 Each 1450 42050

4 Supplying, fitting & fixing white glazed vitreous


W/H Wash Basin 580 × 445 × 235 mm in size approx, 14
kg by weight, including fitting, fixing the same in position
with heavy type C.I. brackets, 30 mm dia PVC waste water
pipe with brass coupling (not
Special Coloured 31 Each 3000 93000

5 Supplying, fitting & fixing Pedestal,


652 × 200 × 205 mm in size, approx, 5.6 kg by weight with
rowel plug & screws etc. all complete approved &
accepted by the Engineer.
Special Coloured 31 Each 1500 46500

6 Supplying, fitting & fixing single bowl stainless steel


sink with sink tray with heavy type C.I. or steel brackets , 12
mm dia C.P. chain plug, 40 mm dia C.P. waste, 40 mm dia
.PVC waste pipe with brass coupling (750 mm length)
including making 11 Each 2600 28600
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
7 Supplying, fitting & fixing of (450 × 600) mm size
& 5 mm thick unframed super quality mirror with hard
boards at the back with all necessary fitting including
making holes in walls & mending good the damages with
cement-mortar (1:4) etc. all com 31 Each 550 17050

8 Supplying, fitting & fixing super quality (600 × 125)


mm coloured glass (plate) shelf having 5 mm thickness
with fancy C.P. brackets, screws & frames including making
holes in walls & mending good the damages with cement-
mortar (1:4) etc. all comple 31 Each 650 20150

9 Supplying, fitting & fixing super quality C.P. Towel rail


of 600 mm long & 20 mm in dia with C.P. holder including
making holes in walls & mending good the damages with
cement-mortar (1:4) etc. all complete approved & accepted
by the Engineer. 31 Each 500 15500

10 Supplying, fitting & fixing of special coloured toilet


paper holder size (150 × 150 × 126) mm including making
holes in walls & mending good the damages with cement-
mortar (1:4) etc. all complete approved & accepted by the
Engineer. 31 Each 522 16182

11 Supplying, fitting & fixing standard size soap tray


including making holes in walls & mending good the
damages with cement-mortar (1:4) etc. all complete
approved & accepted by the Engineer. 41 Each 400 16400

12 C.P. soap tray 41 Each 350 14350

13 Supplying 100 mm inside diameter best quality


uPVC rain water down pipe fitting, fixed in position with
head & shoes, bends, min. 20 mm width F.I. bar clamps &
nails & all accessories such as round grating /domed roof
grating bends, sockets approve 1030 Rft 95 97850

14 Supplying 50 mm inside dia best quality


uPVC soil, waste & ventilation pipe having specific gravity
1.35 - 1.45 mm, wall thickness 2.5 - 3 mm & other physical,
chemical, thermal, fire resistivity properties etc. as per BSTI
approved manufacturer s 339 rft 45 15255

15 Supplying 150 mm inside dia best quality


uPVC soil, waste & ventilation pipe having specific gravity
1.35 - 1.45 mm, wall thickness 4.5 mm - 5.2 mm, & other
physical, chemical, thermal, fire resistivity properties etc. as
per BSTI approved manufactu 180 rft 140 25200

16 Supplying, fitting & fixing G.I. pipe with


all special fittings, such as bends, elbows, sockets,
reducing sockets, Tee, unions, jam-nuts etc. including
cutting trenches where necessary & fitting the same with
earth duly rammed & fixing in walls with hol
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
17
12.5 mm dia G.I pipe with wall thickness
3.25 mm, outside diameter min 21.1 mm, weight 1.45 kg /m,
can with stand min 50kg /cm@ hydraulic pressure. 180 rft 40 7200

18
20 mm dia G.I pipe with wall thickness
3.25 mm, outside diameter min 26.6 mm, weight 1.90 kg /m,
can with stand min 50kg /cm@ hydraulic pressure. 268 rft 55 14740

19
25 mm dia G.I pipe with wall thickness
4.05 mm, outside diameter min 33.4 mm, weight 2.97 kg /m,
can with stand min 50kg /cm@ hydraulic pressure. 170 rft 65 11050

20
32 mm dia G.I pipe with wall thickness
4.05 mm, outside diameter min 42.1 mm, weight 3.84 kg
/m, can with stand min 50kg /cm@ hydraulic pressure. 130 rft 90 11700

21 Supplying different inside dia best quality


uPVC pressure pipe for water supply having specific
gravity 1.35 - 1.45 mm, & other physical, chemical, thermal,
fire resistivity properties etc. as per BSTI approved
manufacturer standards or ASTM,

22 12 mm dia wall thickness 2.8 mm - 3.3 mm 560 rft 18 10080

22.1 19 mm dia wall thickness 2.9 mm - 3.4 mm 140 rft 30 4200

22.2 25 mm dia wall thickness 3.4 mm - 4 mm 180 rft 35 6300

22.3 32 mm dia wall thickness 3.6 mm - 4.2 mm 170 rft 45 7650

23 Supplying, fitting & fixing G.I. union with


sealant etc. complete in all respect approved & accepted
by the Engineer.

23.1 12 mm dia G.I. Union 15 Each 65 975

23.2 20 mm dia G.I. Union 12 Each 85 1020

23.3 25 mm dia G.I. Union 8 Each 152 1216

23.4 32 mm dia G.I. Union 2 Each 185 370

24 Supplying, fitting & fixing best quality


G.M. gate valve with sealant etc. complete approved &
accepted by the Engineer.

25 12 mm dia brass gate valve 15 Each 125 1875

26 20 mm brass gate valve 12 Each 185 2220

27 25 mm brass gate valve 5 Each 268 1340

28 32 mm brass gate valve 2 Each 350 700


SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT

28 12 mm special quality CP bib cock 60 Each 450 27000

30 12 mm plastic bib cock with internal brass thread 3 Each 55 165

31 Supplying, fitting & fixing medium


best quality CP pillar cock etc. complete approved &
accepted by the Engineer.

32 12 mm CP medium quality pillar cock 31 Each 1250 38750


33 Supplying, fitting & fixing best quality
concealed fixed sink cock etc. complete approved &
accepted by the Engineer.

34 12 mm CP concealed fixed cock 12 Each 450 5400

35 12 mm CP concealed moving cock 12 Each 750 9000

36 Moving type 100 mm CP shower rose 24 Each 500 12000

TOTAL COST FOR SANITARY WORK. TK. 889238

INTERNAL & EXTERNAL ELECTRICAL WORKS :

SL DESCRIPTION OF WORKS : Quantity Unit Rate Amount


1
Cable Works : Concealed conduit wiring with the
following PVC insulated stranded cable (BYA) & PVC
insulated green white coloured ECC wire (BYA) through
PVC conduit (Lira brand or equivalent product of other
reputed manufacturer ) complete with 18 SWG GP sheet
pull box with 3 mm thick ebonite sheet cover, fixing
materials, other accessories etc, as required in/cl mending
the damages good.
1.1 IC - 2 * 21.5 sq mm (BYA) cable with 1.5 sq mm (BYA)
ECC wire through PVC pipe of minimum inner dia 16 mm
having wall thickness of 1.5 mm. 340 rft 9 3060

1.2 IC - 2 * 2.5 sq mm (BYA) cable with 2.5 sq mm (BYA)


ECC wire through PVC pipe of minimum inner dia 16 mm
having wall thickness of 1.5 mm. 340 rft 12 4080

1.3 IC - 2 * 4.0 sq mm (BYA) cable with 4.0 sq mm (BYA)


ECC wire through PVC pipe of minimum inner dia 16 mm
having wall thickness of 1.5 mm. 2200 rft 17 37400

1.4 IC - 2 * 6.0 sq mm (BYA) cable with 6 sq mm (BYA)


ECC wire through PVC pipe of minimum inner dia 16 mm
having wall thickness of 1.5 mm. 2200 rft 25 55000

1.5 IC - 2 * 16.0 sq mm (BYA) cable with 10 sq mm (BYA)


ECC wire through PVC pipe of minimum inner dia 16 mm
having wall thickness of 1.5 mm. 1000 rft 32 32000
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
2
ConcealedConduit Wiring : Concealed conduit wiring for
following point looping at the switch board with earth
terminal in/cl circuit wiring with IC-2 * 1.5 sq mm PVC
insulated & sheathed standed cable (BYM) & 1.5 sq mm
PVC insulated green white coloured ECC wire (BYA)
through conduit of minimum 25 mm dia & 1.5 mm wall
thickness complete with 18 SWG GP sheet, switch board &
pull box with 3 mm thick ebonite sheet cover, 5 amps piano
switch, ceiling rose fixing materials etc, as required in/cl
mending the damages good (all electrical contacts shall be
of brass/copper).

3 2-pin 5 amps socket point (outlet) with control switch 48 pts 650 31200

Light Fitting :
4
Providing & fitting of saucer light fitting of 200 mm dia
glass saucer shade with aluminium base carrier, brass
holder, earth terminal, necessary wiring with 2 * 2.4
sqm stranded PVC insulated flexible wire etc, complete
(except lamp) as per sample approved by the Engineer -in-
charge. 70 pts 350 24500

5
Providing & fitting of bath-room light fitting of oxidize/
chromium plated/nickel polished brass frame with
carrier, cylindrical glass shade, brass holder, earth
terminal, necessary wiring with 2 * 0.4 sqm stranded
PVC insulated flexible wire etc, complete
(except lamp) as per sample approved by the
Engineer -in-charge. 22 pts 256 5632

6
Providing & fitting of 1 * 4' * 40 watt fluorescent tube
light (ceiling/wall mounted) fitting of superior quality
ballast, starter, holder, 18 SWG sheet steel stove enamel
base, neccessry wiring with 2 * 4 sqm PVC insulated
(stranded) flexible wire, earth terminal etc, complete (except
lamp) as per sample approved by the Engineer -in-charge. 55 Each 380 20900

7 Socket Outlet :
7.1 Providing & fitting 250 volt, single phase, 3-pin, 15
amps Combined switch socket outlet (concealed type)
mounted on required size 18 SWG galvanized plain
sheet board of 76.2 mm foreign made. 25 pts 500 12500

7.2 Providing & fitting 250 volt, single phase, 3-pin, 5


amps Combined switch socket outlet (concealed type)
mounted on required size 18 SWG galvanized plain
sheet board of 76.2 mm local made. 25 pts 350 8750

8 Fan :
Ceiling Fan : Supply & installation of 230 Vz 50 Hz
capacitor type AC ceiling fan to complete with porcelain
plastic cable connector canopy & suspention rod of
approved length of the following sizes in/cl installation of
2 * 15 mm2 BYA cable from connector to fan.
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
8.1 1425 mm (56") ceiling fan 44 Each 2300 101200

8.2 Exhaust Fan : Supply & installation pf wall window


glass mounted axial flow propeller type single phase
220 V, 50 Hz AC exhaust fan foreign made.

9 300 mm (12") dia, Type -X 22 Each 1250 27500

10 Distribution Board :
10.1 Supply, fabrication & installation of following distribution
board ( including MCCB/MCB approved equivalent ) by
16 ….of the distribution board.
11 Incoming - 1 * 40 ATP MCCB , Out going-20*16 ASP
MCB - 2 * 20 ASP MCB 12 Each 12000 144000

12 Incoming - 1 * 100 ATP MCCB , Out going-4 * 40 ATP


MCCB ( 3 nos Blank) 3 Each 15000 45000

13 Earthing :
13.1

Earthing the electrical installation with 40 mm dia GI


pipe (earth electrode) having 6.35 mm dia hole across the
pipe at 305 mm interval securedly bonded with 2 nos. of no.
2 SWG HDBC earth leads with its protection by 20 mm dia
GI pipe upto plinth level run at a depth of 609.6 mm below
GL upto board to be earthen in/cl necessary connecting
copper socket bolts, nuts etc, complete for maintaining earth
resistance with 1 ohm, Depth of bottom of main electrode at
6858 mm fro GL & length of electrode 6096 mm. 2 Each 7500 15000

14

Construction of earthing inspection pit inside


measurement 600 * 600 250 mm thick brick in cement
morter (1:4) with 100 mm thick RCC to slab (1:2:4) with 1%
reinforcement 450 mm dia water sealed CI man-hole cover
with locking arrangement in/cl necessary earth works, site
filling & brick flat solling 75 mm thick (1:3:6) base concrete
for making inlet channel & 12 mm thick (1:2) cement plaster
with neat finishing etc, all complete upto a depth 0.7 meter. 2 Each 5000 10000

15 Providing & fixing 25.4 mm dia 457 mm long solid


copper rod with sharp top end for arresting lighting
securedly bonded with 6.6 mm thick 150 mm * 150 mm
* 150 mm copper base plate to be recessed in wall
complete with nuts, bolts, CC works etc. 2 Each 1800 3600

16 Provide & drawing No-2 HDBC wire through 12.7 mm


dia GI pipe in/cl fitting ,fixing the GI pipe in wall or column
complete as required. 1 Each 3500 3500
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
17
Main & Meter Board : Supply & installation of meter
board complete with 3 phase meter of 750 mm * 500 mm *
150 mm of 16 SWG sheet steel box with hinged cover &
lock handle glass, 1 * 60 ATP MCCB. 6 * 40 ASP MCB. 1 *
60 ATP meter & adequate bushar, all complete with
necessary requirement & as per direction of the Engineer -
in-charge. 2 Each 5500 11000

18
Supplying & fitting of almirah type 16 SWG suitable
size (minimum 150 mm depth ) sheet steel box with hinged
cover & lock handle glass duly painted with gray hammer
paint on out side & enamel paint in inside surfaces having
built in push type locking arrangement in/cl metal bridge of
suitable size for fixing of all electrical control devices
complete with suitable anchoring arrangement in wall
column & keeping provision for cable inlets & outlets & exits
as required (only front surface of the board will be considerd
for measurement). 12 Each 4500 54000

19 Supply & fixing of 415 volt, 3 phase, 50 Hz capacity


control circuit breaker 150 amps TPM CCB unit with thermal
over current & instantaneous electromagnetic short circuit
release & (adjustable type 100 A rating). 5 Each 15000 75000

20 Provide & fixing on a prepard board 250 volt grade 40


amps, single phase pole miniature circuit breaker
(SPMCBS) having minimum breaking capacity 6 KA with
thermal over current & instantanneous electro magnetic
short circuit release provision. 2 Each 2500 5000

21 Supply & fixing of 415 volt, 3 phase, 50 Hz, 60 amps


TP meter 2 Each 3500 7000
22 200 amps rating 4 nos, of bar each of minimum length
380mm & cross section 150 sqm assembled in 482.60 *
431.80 * 203.20 mm size enclosure complete with porcelain
insulators. 1 Each 3500 3500

TOTAL Cost For Internal Electric Work. TK. 740322

SUMMARY OF COST
SL ITEMS
1 Civil Works ( Up to G.Floor R,C,C & B/W ) TK. 1749796
2 Sanitary, Plumbing & Water Supply Works TK. 889238
3 Internal & External Electrical Works TK. 740322
4 Misc Exp For Gus. Water,Electricity Connection TK. 700000
7 Sollar Pannel TK. 150000
TOTAL TK. 4229356
###
So Cost per sft Tk.1630/=
SL DESCRIPTION OF WORKS : Quantity Unite RATE AMOUNT
7936
27456 63.73092
8253

8253 512.4629
MATERIAL ESTIMATION

Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
1 SAND FILLING 5057.82 cft (g) 6120
2 BRICK FLAT SOLLING (Found +P 1997 sft 5990 5990

3 3" C.C Work 388.27 cft 1.3.6 47 174.72 2970


4 R.C.C Work
a In Fond,G.Beam, S.Col Etc 1703 cft 1.2.4 307 392 392 13319
b (1:1.5:3) 1202 cft 1.1.5:3 264 276 276 9398
4 3/4" THICK CEMENT PLASTER
(a) U.G.W.R (Inside & Outside) 430 sft 1.4 6 31
5 NEAT CEMENT FINISHING
(a) U.G.W.R 467 sft 3

7 5" thick brick work 1622 sft 1:04 38 191 8110


8 MILD STEEL (a) 40 Grade
(b) 60 Grade 10362.93 kg 2818 3319 311
9 3/4" Thick Plaster

Sub Total (Foundation Level) 665 13174 668 0 25687 14100 2818 3319 311
Rate 425 12 35 165 8 8 55 55 55
Amount 282502 2E+05 23385 0 205500 112797 154976.3 182566 17091.46

Total Tk. 1352237

CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT

GROUND FLOOR
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm

Cement Sand in Cft Brick M.S.Rod


Ratio of Gray Picket in Nos
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos 20 mm 16mm 12mm
1 R.C.C WORK
(b) Slub, Beam & Stair, col 1425 cft 1,2,4 257 328 328 11144
3 10" BRICK WORK in/c Foundat 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2716 sft 1.4 68 340 13580
5 3/4" Thick Plaster
(a) Inside Wall 5454 sft 1.6 55 436
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment (Drivers, Guard, e 495 sft 1.4 15 74
8 TILE WORK (Wall Tiles) (1" Thick Morter)
b) Toilet Wall 238 sft 1.3 6 24
10 MARBLE / GRANITE WORK
a) Reception Area 56 sft 1.3 1 6
37 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 419 1350 328 11144 15080 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 161315 16201 9832.5 66861 90480 77025 13650 182650

NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT

FIRST FLOOR

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(a) Column & Shear Wall 100 cft 1.1½.3 22 23 23
(b) Slub, Beam & Stair 1420 cft 1,2,4 256 327 327 11104
3 10" BRICK WORK 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2886 sft 1.4 72 361 14430
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
5 3/4" Thick Plaster
(a) Inside Wall 4845 sft 1.6 48 388
(b) Outside Wall 1520 sft 1.6 15 122
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1480 sft 1.4 44 222
TILE WORK (Wall Tiles) (1" Thick Morter)
8 a) Kitchen Wall Toilet 850 sft 1.3 21 85
19 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 497 1669 350 11104 15930 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 191310 20033 10488 66626.4 95580 77025 13650 182650

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1

2ND FLOOR

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(a) Column & Shear Wall 100 cft 1.1½.3 22 23 23
(b) Slub, Beam & Stair 1420 cft 1,2,4 256 327 327 11104
3 10" BRICK WORK 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2886 sft 1.4 72 361 14430
5 3/4" Thick Plaster
(a) Inside Wall 4845 sft 1.6 48 388
(b) Outside Wall 1520 sft 1.6 15 122
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1480 sft 1.4 44 222
TILE WORK (Wall Tiles) (1" Thick Morter)
8 a) Kitchen Wall Toilet 850 sft 1.3 21 85
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
19 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 497 1669 350 11104 15930 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 191310 20033 10488 66626.4 95580 77025 13650 182650

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1

3RD FLOOR

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(a) Column & Shear Wall 100 cft 1.1½.3 22 23 23
(b) Slub, Beam & Stair 1420 cft 1,2,4 256 327 327 11104
3 10" BRICK WORK 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2886 sft 1.4 72 361 14430
5 3/4" Thick Plaster
(a) Inside Wall 4845 sft 1.6 48 388
(b) Outside Wall 1520 sft 1.6 15 122
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1480 sft 1.4 44 222
TILE WORK (Wall Tiles) (1" Thick Morter)
8 a) Kitchen Wall Toilet 850 sft 1.3 21 85
19 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 497 1669 350 11104 15930 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 191310 20033 10488 66626.4 95580 77025 13650 182650

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm

4TH FLOOR

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(a) Column & Shear Wall 100 cft 1.1½.3 22 23 23
(b) Slub, Beam & Stair 1420 cft 1,2,4 256 327 327 11104
3 10" BRICK WORK 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2886 sft 1.4 72 361 14430
5 3/4" Thick Plaster
(a) Inside Wall 4845 sft 1.6 48 388
(b) Outside Wall 1520 sft 1.6 15 122
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1480 sft 1.4 44 222
TILE WORK (Wall Tiles) (1" Thick Morter)
8 a) Kitchen Wall Toilet 850 sft 1.3 21 85
19 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 497 1669 350 11104 15930 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 191310 20033 10488 66626.4 95580 77025 13650 182650

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1

5TH FLOOR
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(a) Column & Shear Wall 100 cft 1.1½.3 22 23 23
(b) Slub, Beam & Stair 1420 cft 1,2,4 256 327 327 11104
3 10" BRICK WORK 125 cft 1.6 5 40 1500
4 5" BRICK WORK 2886 sft 1.4 72 361 14430
5 3/4" Thick Plaster
(a) Inside Wall 4845 sft 1.6 48 388
(b) Outside Wall 1520 sft 1.6 15 122
6 1/2" Thick Plaster (Ceiling) 1286 sft 1.4 13 103
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1480 sft 1.4 44 222
TILE WORK (Wall Tiles) (1" Thick Morter)
8 a) Kitchen Wall Toilet 850 sft 1.3 21 85
19 MILD STEEL a) 40 Grade 4590 kg 1185 210 2810
b) 60 Grade kg
Sub Total (Ground Floor) 497 1669 350 11104 15930 1185 210 2810
Rate 385 12 30 6 6 65 65 65
Amount 191310 20033 10488 66626.4 95580 77025 13650 182650

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1

ROOF FLOOR

Cement Sand in Cft M.S.Rod


Ratio of Gray Picket Brick
S.L Description of Work Quantity Mixing (bag) Local Sylhet in Nos In Nos 20 mm 16mm 12mm
1 R.C.C WORK
(b) Slub, Beam & Stair 530 cft 1,2,4 95 122 122 4145
3 10" BRICK WORK 125 cft 1.6 5 40 1500
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
4 5" BRICK WORK 840 sft 1.4 21 105 4200
5 3/4" Thick Plaster
(a) Inside Wall 1362 sft 1.6 14 109
(b) Outside Wall 865 sft 1.6 9 69
6 1/2" Thick Plaster (Ceiling) 325 sft 1.4 3 26
7 TILE WORK (Floor Tiles) (1.5" Thick Morter)
(a) Apartment 1286 sft 1.4 39 193
19 MILD STEEL a) 40 Grade 1025 kg 350 675
b) 60 Grade kg
Sub Total (Ground Floor) 186 664 122 4145 5700 350 675
Rate 385 12 30 6 6 65 65 65
Amount 71418 7968 3657 24867.6 34200 0 22750 43875

S.L NOTE: CONCRETE MIXING RATIO MAY BE CHANGED WITH RESPECT TO CYLINDER TEST RESULT
1
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
Ratio
of Cement Sand in Cft Stone Picket Brick M.S.Rod
S.L Description of Work Quantity Unit Mixing Gray (bag) Local Sylhet chips in Nos in Nos 20 mm 16mm 12mm
10mm

3915

3915
55
215327.7 1352237
10mm

10mm

385

385
65
25025 Total Tk. 643040

10mm
10mm

385

385
65
25025 Total Tk. 682388

10mm
10mm
385

385
65
25025 Total Tk. 682388

10mm

385

385
65
25025 Total Tk. 682388
10mm

10mm

385

385
65
25025 Total Tk. 682388
10mm

10mm

385

385
65
25025 Total Tk. 682388

10mm
10mm

65
0 Total Tk. 208735
Compatibility Report for 6 Storied Residential Building Estimate _
Measurement.xls
Run on 8/24/2023 2:35

If the workbook is saved in an earlier file format or opened in an earlier version


of Microsoft Excel, the listed features will not be available.

Minor loss of fidelity # of occurrences

Some cells or styles in this workbook contain formatting that is not supported 108
by the selected file format. These formats will be converted to the closest
format available.
Version

Excel 97-2003

You might also like