Customer: THIQAR OIL COMPANY (TOC)

DEHYDRATION AND DESALTING UNIT FOR NASSIRIYA


Plant:
DEGASSING STATION
Location: NASSIRIYA FIELD - IRAQ
Project Unit Document Code Serial n° Rev. Sheet

PE14017AR 00 NM-0005 01 00 1/2

EFFLUENT LIST

Maikel Tosti
Firmato digitalmente da Maikel Tosti
ND: cn=Maikel Tosti, o, ou,
email=tosti.m@pegitaly.it, c=IT
Roberta Digitally signed by Roberta Lanteri
DN: cn=Roberta Lanteri, o, ou,
Umberto Corsi
Firmato digitalmente da Umberto Corsi
ND: cn=Umberto Corsi, o, ou,
email=corsi.u@pegitaly.it, c=IT

Lanteri
Data: 2018.03.05 17:19:39 +01'00' email=lanteri.r@pegitaly.it, c=IT Data: 2018.03.05 17:19:50 +01'00'
Mod. ST0002_0/xls

Date: 2018.03.05 14:35:05 +01'00'

00 15/02/2018 ISSUED FOR BASIC DESIGN M. TOSTI R. LANTERI U. CORSI

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED/AUTHORIZED

This document is property of Progetti Europa & Global S.p.A. Roma, it may not be copied, reproduced and/or circulated without PEG’s authorization.
Customer: THIQAR OIL COMPANY (TOC)
DEHYDRATION AND DESALTING UNIT FOR NASSIRIYA
Plant:
DEGASSING STATION
Location: NASSIRIYA FIELD - IRAQ
Project Unit Document Code Serial n° Rev. Sheet
PE14017AR 00 NM-0005 01 00 2/2

Flow Rate
Rev. Effluent Phase Temperature °C Destination Notes
[kg/h] [m3/h]

(1) Worst scenario before


0 Gas to Existing Flare System 40600 (1) 38300 (1) Gas ~40 PEG Battery Limit
combustion.

0 Flue gas from 01-H-001 TBD TBD Gas TBD Atm

Liquid+
0 Slurry from 03-F-001 TBD TBD ~60 Package Battery Limit
Solids

(2) 140 m3/h from Desalting Unit


0 Produced Water from 03-P-001 349000 (2) 349 (2) Liquid ~60 PEG Battery Limit + 210 m3/h from Existing 1st
Stage Separator

This document is property of Progetti Europa & Global S.p.A. Roma, it may not be copied, reproduced and/or circulated without PEG’s authorization.