PIRAMAL SCHOOL OF EDUCATION LEADERSHIP PROJECT

ACTIVITY CHECKLIST : INTERNAL PLASTER

Project 0 Format No PSL/Cheklist/000

Client Piramal School of Education Leadership Date:

PMC --- Report/WIR No.

Contractor 0 Drawing No.


Location:

SN Description of Work Yes No Remark

PRE CHECKING

Is gap between completion of masonry and commencement of plaster work


1
maintained ?

2 Check Shelf life & Condition of materials

3 Is scaffolding arrangement done ?

4 Is cleanliness of RCC surface and filling of tie rods done ?

5 Is hacking of RCC surface and application of bonding agent done?

6 Is electrical and plumbing work completed ?

7 Is Fiber mesh over electrical conduit and joints of RCC and masonry fixed ?

POST CHECKING

Check the plaster for line, level, window edges, window jambs, door frame, vertical
1
plumb, finishing at corners, fan hook finishing etc.

2 Plaster is scratched up to wall tile cladding level

3 Check post cleaning work

4 Check Curing of plaster

Comments,If any :