Rainwater pond work estimation

Date
15-03-2024

S. no Description of item Rate per Units/Qnty No of Days Total price


(with all Included) day/no’s
Transport -
1 Tata Hitachi 110 model 7,000 (Up & Down) 7,000

2 Tata Hitachi 110 model 17,600 800 𝐦𝟑 7 days 1,23,200

3 tractors 3500 4 no’s 4 days 56,000


-
4 Np2 Rcc pipes 1500 7 no’s 10,500
Manpower
5 (np2pipe laying, - - 2 days 15,000
plumbing,chipping,Gp2
chemical, Dressing,etc)
Total 2,11,700

Two lakh eleven thousand seven hundred rupees

 Total Excavation area = 800 cubic meter


 Pond depth = 3.00 meter