NATURAL GAS CHARGING PLAN IN SIMILIPADA, ANGUL AREA THROUGH SR-3

BPCL MECON M/s TGSPL


1. Sri PVJayakrishnan 1. Sri Anuj Kumar |1. SriGyanajit Pattanaik
|2. Sri Shivam Mishra 2.Sri Nitish Kumar Rai |2. SriAjit Pattanaik
Following points were discussed and agreed upon:
TGSPL Views &
S.No List of Activities Target Date
commitment

11.03.2024
1 Flushing of SR 3 MDPE Line- 1.2 Km
Testing of SR 3 MDPE Line- 1.2 Km 12.03.2024
2
|SR fixing (SR 3)& Tapping with 63/32 mm Saddle 13.03.2024

Construction of Pedestals (09 Nos) |14.03.2024


It will be done
|bythe
Concerned SOR
vendor. M/s 14.03.2024
5 Riser Testing- 09 Nos MRC will start
the testing
from
|09.03.2024.
20.03.2024
6 Route Markers - 20 Nos
|20.03.2024
7 Gas charging
It will start
Conversion Team along with accessories & conversion kit (Hose from
pipe with clamp,Testing oven, Nozzle for conversion) 20.03.2024.