Master Program

Proposed
Two Storey Total Duration: 10 months
Project Name: House for
Mr. Fernando
at Koswatta Strart
Date: 9-Mar-23 End Date: 9-Jan-24

TASK DESCRIPTION STATUS START DATE END DATE DURATION


Mobilization 3/9/2023 4/18/2023 40
Site Preperation 3/31/2023 5/28/2023 58
Exacavtion 5/16/2023 6/5/2023 20
Concrete Works 5/16/2023 8/4/2023 80
Masonary Works 8/6/2023 10/16/2023 71
Water Proofing 6/17/2023 9/5/2023 80
Structural Metal Work 10/20/2023 11/24/2023 35
Metal Work 10/20/2023 11/24/2023 35
Doors & Windows 10/20/2023 11/29/2023 40
Roof Covering and Roof
10/10/2023 11/25/2023 46
plumbing
Finishes 10/25/2023 12/14/2023 50
Plumbing and Sanitary
10/25/2023 12/14/2023 50
Installations
Electrical Installations 9/10/2023 11/24/2023 75
Painting 10/25/2023 12/4/2023 40
External
Handing Works
Over & 11/4/2023 12/9/2023 35
Demobilization 12/20/2023 1/9/2024 20

START DATE DURATION

MOBILIZATION 3/9/2023 40

SITE PREPERATION 3/31/2023 58


EXACAVTION 5/16/2023 20

CONCRETE WORKS 5/16/2023 80

MASONARY WORKS 8/6/2023 71

WATER PROOFING 6/17/2023 80

STRUCTURAL METAL WORK 10/20/2023 35

METAL WORK 10/20/2023 35

DOORS & WINDOWS 10/20/2023 40

ROOF COVERING AND ROOF


PLUMBING
10/10/2023 46

FINISHES 10/25/2023 50

PLUMBING AND SANITARY


INSTALLATIONS
10/25/2023 50

ELECTRICAL INSTALLATIONS 9/10/2023 75

PAINTING 10/25/2023 40

EXTERNAL WORKS 11/4/2023 35

HANDING OVER &


DEMOBILIZATION
12/20/2023 20