TTMN12H – MITIGATING MEASURES

SECTION: HT409ITM
MITIGATING MEASURES

Group Members: 1. Flores, Ma. Therese B.


2. Sarmiento, Erika Janna R.
3. Usana, Ashley Nicole M.
Group Number: Province (Region): City of Las Pinas

IDENTIFIED RISK CONTINGENCY PLAN ACTION PLAN

1. Infrastructure Risk The National Disaster Risk Reduction As for the action plan of the city of
In the area of Talon Dos, and Management Council (NDRRMC) Las Pinas, they have outlined it
one of the barangays in recognizes Las Piñas for exceptional into three phases, which are:
Las Pinas, is vulnerable to disaster risk management. With that • Preparation Phase - They
“dangerous debris flow” said, here are some of the identify which
during typhoons according contingency plans they prepare in infrastructures are critical
to the study of Mines and case of infrastructure risks: whenever there are
Geosciences Bureau • They assess the typhoons.
through risk assessments infrastructure’s materials and • Response Phase - They
conducted in the city. develop a preventive activate response teams
maintenance schedules in and prioritize response
order to ensure the reliability actions based on the
of the infrastructure severity of the risk in order
components; to mitigate further
• They develop clear damage. The city of Las
procedures for responding to Pinas also take immediate
debris flow, such as alerting steps by isolating the
the key personnel responsible affected areas.
and activating response • Recovery Phase - They
teams; and continually monitor the
• They conduct regular drills to vulnerability of the debris
test the effectiveness of the flow from the
contingency plan during infrastructure to prevent
infrastructure-related risks. future incidents.

2. Environmental Risk • The city government of Las • Once the risk occurs, they
Due to rapid urbanization Pinas conducts a planning activate monitoring
and developments in the workshop regarding the systems to track the
City of Las Pinas, the contingency plan on cleaning progress of the typhoon
low-lying areas are prone up and preserving Manila Bay and flood.
to flooding, particularly area, since the city is near the • They also prepare all the
those who are established Manila Bay which can affect response vehicles and
in hazard-prone areas when a typhoon occurs. equipment.
1

Date: March 15, 2024


TTMN12H – MITIGATING MEASURES

SECTION: HT409ITM
whenever typhoons occur. • They also establish clear • Aside from those, they
procedures for the Risk develop evacuation centers
Disaster Management Team in case of flooding or other
for responding to this kind of risks in order for the
risk. community have a place to
stay in and to avoid the
risk.

REMINDERS:
Please note, all entries in the IDENTIFIED RISKS should be in narrative form.
You need to explain it briefly and CITE THE BASIS for such an assessment.
If you have a groupmate who is a native of the locality, firsthand information may
be included in the IDENTIFIED RISKS, but the person whom you are quoting as a
resource person should, ideally, be named.