DAFTAR UPAH KARYAWAN UNTUK PENAMBANGAN NICKEL ORE

No. Jabatan Jumlah Roster Kerja Roster Cuti Basic/Bln Rp

1 Project Manager 1 8 Minggu 14 Hari

2 Grade Control 2 8 Minggu 14 Hari 8,000,000


3 Mine Plan & Engineering 1 8 Minggu 14 Hari 8,000,000

4 Asisten Grade Control 1 10 Minggu 14 Hari 7,000,000


5 Foreman Infrastruktur & Hauling Road 2 10 Minggu 14 Hari 7,000,000
6 Jr. Mine Plan & Surveyor 1 10 Minggu 14 Hari 6,000,000
7 Safety Officer 1 10 Minggu 14 Hari 6,000,000
8 Analyst X-Ray 1 10 Minggu 14 Hari 6,000,000
9 Foreman Preparasi Sample 1 10 Minggu 14 Hari 6,000,000
10 Foreman Stockpile 1 10 Minggu 14 Hari 6,000,000
11 Mechanik & Electrikal 1 10 Minggu 14 Hari 6,000,000
12 Welder 1 10 Minggu 14 Hari 4,500,000
13 Foreman Barging 1 10 Minggu 14 Hari 4,500,000

14 Admin Generall Database 1 12 Minggu 14 Hari 3,500,000


15 Admin HR&GA 1 12 Minggu 14 Hari 3,500,000
16 Admin Finance 1 12 Minggu 14 Hari 3,500,000
17 Asisten Analyst 1 12 Minggu 14 Hari 3,500,000
18 Logistik & Purchasing 1 12 Minggu 14 Hari 3,500,000
19 Fuel Control 1 12 Minggu 14 Hari 3,500,000

20 Driver LV 1 24 Minggu 14 Hari 2,500,000


21 Stocker 2 24 Minggu 14 Hari 2,500,000
22 Crew Preparasi Sample 5 24 Minggu 14 Hari 2,500,000
23 Crew Sampler GC 6 24 Minggu 14 Hari 2,500,000
24 Crew Sampler ETO 3 24 Minggu 14 Hari 2,500,000
27 Crew Surveyor 1 24 Minggu 14 Hari 2,500,000
28 Helper Mekanik 2 24 Minggu 14 Hari 2,500,000
29 Helper Electrik 1 24 Minggu 14 Hari 2,500,000
30 Driver Fuel Truck 1 24 Minggu 14 Hari 2,500,000
31 Helper Fuel Truck 1 24 Minggu 14 Hari 2,500,000
32 Driver Water Truck 1 24 Minggu 14 Hari 3,500,000
33 Helper Water Truck 1 24 Minggu 14 Hari 2,500,000
34 Flag Man 2 24 Minggu 14 Hari 2,500,000
35 Security 2 24 Minggu 14 Hari 3,000,000

GRAND TOTAL 50 132,500,000


MBANGAN NICKEL ORE

Status PPh21 + BPJS TOTAL

Staff All In Include PPh21 + BPJS 0

Staff All In Include PPh21 + BPJS 16,000,000


Staff All In Include PPh21 + BPJS 8,000,000

Staff Include PPh21 + BPJS 7,000,000


Staff Include PPh21 + BPJS 14,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 6,000,000
Staff Include PPh21 + BPJS 4,500,000
Staff Include PPh21 + BPJS 4,500,000

Staff Include BPJS 3,500,000


Staff Include BPJS 3,500,000
Staff Include BPJS 3,500,000
Staff Include BPJS 3,500,000
Staff Include BPJS 3,500,000
Staff Include BPJS 3,500,000

Non Staff Include BPJS 2,500,000


Non Staff Include BPJS 5,000,000
Non Staff Include BPJS 12,500,000
Non Staff Include BPJS 15,000,000
Non Staff Include BPJS 7,500,000
Non Staff Include BPJS 2,500,000
Non Staff Include BPJS 5,000,000
Non Staff Include BPJS 2,500,000
Non Staff Include BPJS 2,500,000
Non Staff Include BPJS 3,500,000
Non Staff Include BPJS 2,500,000
Non Staff Include BPJS 2,500,000
Non Staff Include BPJS 5,000,000
Non Staff Include BPJS 6,000,000
0
185,500,000